Hardy Street Investors v. Texas Water Rights Commission

536 S.W.2d 85, 1976 Tex. App. LEXIS 2643
CourtCourt of Appeals of Texas
DecidedMarch 31, 1976
Docket5521
StatusPublished
Cited by12 cases

This text of 536 S.W.2d 85 (Hardy Street Investors v. Texas Water Rights Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardy Street Investors v. Texas Water Rights Commission, 536 S.W.2d 85, 1976 Tex. App. LEXIS 2643 (Tex. Ct. App. 1976).

Opinion

OPINION

JAMES, Justice.

This is an appeal from an order of an administrative body, involving the substantial evidence rule.

Plaintiff-Appellants Hardy Street Investors, a partnership, and Kingsbridge Development Corporation challenged an order of Defendant-Appellee Texas Water Rights Commission as being invalid and void because it was not supported by substantial evidence. After review of the facts, the trial court’s judgment upheld the validity of the order, from which Plaintiff-Appellants appeal. We affirm.

Inverness Forest Improvement District (hereinafter called “District”) applied to Defendant-Appellee Texas Water Rights Commission (hereinafter called “Commission”) for its approval of a drainage project and the issuance of $170,000.00 of the District’s bonds to finance it, under the provisions of Article 51.421 of the Texas Water Code pertaining to water control and improvement districts. The District is a water control and improvement district operating and existing pursuant to Chapter 51, Texas Water Code, and Article XVI, Section 59, of the Texas Constitution. Plaintiff-Appellants Hardy Street Investors and Kingsbridge Development Corporation each own a tract of land within the District.

The District on May 10, 1974, filed an application to the Commission for approval of an engineering project and the economic feasibility of the issuance of bonds therefor. The application consisted of the engineer’s report, several maps, and the plans and .specifications for the proposed construction. The application and supporting engineer’s report originally requested approval of $125,000 in bonds, but this request was subsequently increased to $170,000 because of revised cost figures. The engineering project as submitted to the Commission was designed to correct a condition of advancing erosion which threatened to destroy and contaminate the District’s sewage lift station and water well, as well as destroy the lateral support for a county road.

The District’s application and engineering report as submitted to the Commission incorporate into the cost figures a calculation of two (2) years prepaid interest at the rate of 7% per annum. The contract documents involved for the proposed construction work contemplate a sixty calendar day “actual construction period” after the District’s engineer has given the contractor written notice to commence work. C. R. Miertschin, Director of the District Division of the Ap-pellee Commission, testified that six months would be a reasonable, actual construction time for the project from the beginning to the completion thereof.

Staff members of the Commission made an on-site inspection on June 5, 1974, and after review of the engineer’s report, the Commission determined that two years prepaid interest at 7% per annum was reasonable, as applied for by the District, and in its order approving the project authorized such interest. “Prepaid interest” is an amount of money derived from the actual sale of the bonds which is placed in an interest and sinking fund to meet debt service requirements pending completion and commencement of operation of the facilities being constructed and may not be used for any other purpose by the District.

The Commission’s order appealed from is dated September 30, 1974 and in effect approves the District’s application in the following language:

“Now Therefore, Be it Resolved by the Texas Water Rights Commission that the *87 engineering plans, specifications, and estimate of costs in the sum of $170,000 for the project of Inverness Forest Utility District be and the same are hereby approved, and the issuance of $170,000 of bonds for the purpose of financing said improvements in accordance with said plans, specifications, contract documents and engineering reports as filed heretofore with the Commission is hereby approved.”

As heretofore stated, the trial court after reviewing the facts held that the Commission’s order was “valid and supported by substantial evidence,” from which judgment Plaintiff-Appellants appeal asserting in effect that the Commission’s order is not supported by substantial evidence.

The crux of Appellants’ argument is this: The construction period of the project was sixty days, and in any event not more than six months; yet the project calls for two years interest at 7% per annum; that if six months’ interest is allowed instead of two years the project would total only $152,150 instead of $170,000; that the project calls for $17,850 too much interest and therefore that the Commission’s order is arbitrary and unreasonable and should be held void. We do not agree with this contention and accordingly overrule Appellant’s point of error and affirm the trial court’s judgment.

This appeal is governed by the substantial evidence rule.. The order of the Defendant-Appellee Texas Water Rights Commission is presumed to be legal and valid, and the burden is on those attacking the order (here, the Plaintiff-Appellants) to show that the order is not reasonably supported by substantial evidence. City of San Antonio v. Texas Water Commission (Tex.Sup.1966) 407 S.W.2d 752; Gibraltar Savings and Loan Association v. Falkner (Tex. Sup.1963) 371 S.W.2d 548; Hewlett v. Texas Alcoholic Beverage Comm. (Waco CA 1973) 492 S.W.2d 686, NRE.

The test in determining whether an administrative decision finds reasonable support in substantial evidence is whether the evidence as a whole is such that reasonable minds could not have reached the conclusion that the agency must have reached in order to justify its action. Railroad Commission v. Shell Oil Co. (1942) 139 Tex. 66, 161 S.W.2d 1022; Trapp v. Shell Oil Co. (1946) 145 Tex. 323, 198 S.W.2d 424; Southern Canal Co. v. State Board of Water Engineers (1958) 159 Tex. 227, 318 S.W.2d 619; State ex rel. Blooming Grove I.S.D. v. County Board of School Trustees (Waco CA 1960) 334 S.W.2d 588, NRE; Bichsel v. Strickland (Waco CA 1963) 371 S.W.2d 785, no writ history; Cruz v. City of San Antonio (Waco CA 1969) 440 S.W.2d 924, no writ history.

Under the record before us, we cannot say that the Commission’s order was not reasonably supported by substantial evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ronald Elan Martin v. State
Court of Appeals of Texas, 2002
Texas Alcoholic Beverage Commission v. Wishnow
704 S.W.2d 421 (Court of Appeals of Texas, 1985)
TEX. ALCOHOLIC BEVERAGE COM'N v. Wishnow
704 S.W.2d 425 (Court of Appeals of Texas, 1985)
Lindsay v. Sterling
681 S.W.2d 708 (Court of Appeals of Texas, 1984)
Kittman v. St Bd. of Pharmacy of Tx
607 S.W.2d 26 (Court of Appeals of Texas, 1980)
State Banking Board v. Valley National Bank
604 S.W.2d 415 (Court of Appeals of Texas, 1980)
United Savings Ass'n of Texas v. Vandygriff
594 S.W.2d 163 (Court of Appeals of Texas, 1980)
TEXAS HEALTH FAC. COMM'N v. Baptist Gen. Convention
573 S.W.2d 575 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
536 S.W.2d 85, 1976 Tex. App. LEXIS 2643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardy-street-investors-v-texas-water-rights-commission-texapp-1976.