Hammermill Paper Co. v. Rust Engineering Co.

243 A.2d 389, 430 Pa. 365, 1968 Pa. LEXIS 710
CourtSupreme Court of Pennsylvania
DecidedJuly 1, 1968
DocketAppeal, 186
StatusPublished
Cited by116 cases

This text of 243 A.2d 389 (Hammermill Paper Co. v. Rust Engineering Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammermill Paper Co. v. Rust Engineering Co., 243 A.2d 389, 430 Pa. 365, 1968 Pa. LEXIS 710 (Pa. 1968).

Opinion

Opinion by

Mb. Justice Jones,

This appeal is from a judgment entered on the pleadings by the Court of Common Pleas of Erie County.

On March 5, 1956, Rust Engineering Company (Rust) submitted to Hammermill Paper Company (Hammermill) a proposal to “construct additional Finishing Facilities at (Hammermill’s) Erie, Pennsylvania, plant, consisting essentially of a Finishing Building Extension, Roll Storage Building and Packaging Materials Building.” No drawings or specifications were submitted at that time, nor was a price included in the proposal, 1 although, when executed, the contract, in this respect, provided: “When drawings and specifications are sufficiently developed, an estimate of the total cost of engineering and constructing the above facilities will be furnished (Hammermill).” Article XIII of Rust’s proposal, titled “Approval After Acceptance”, stated “This proposal is subject to the approval of the President ... of (Rust) and is not binding on (Rust) until so approved after acceptance by (Hammermill) whereupon it shall become a contract.” Hammermill “accepted” the proposal on March 28,1956, and Rust approved said acceptance on April 30, 1956.

*368 The ’ instant controversy involves the construction and. later collapse of a brick curtain wall, 14' 8" high and 165' in length, which was erected as a “vertical extension to a third story height of the existing east wall of Building No. 75.” Hammermill contends the wall collapsed because of faulty and negligent construction, while Rust’s pleaded position is that the cause of the collapse was an “Act of God”, that Hammermill had paid Rust for and accepted the work involved in constructing the original wall and in reconstructing it after collapse and was, thereby, estopped from further complaint, and finally that Hammermill has been adequately compensated by its insurance carrier for any “use and occupancy” loss incurred by the collapse of the wall. Said “use and occupancy” loss in the averred amount of $70,392.56 arose by reason of the interruption of Hammermill’s paper-making operation caused by the collapse of the wall through the roof of the Building No. 75 and onto machinery in the operation, and there is an additional averred loss of $11,-757.53 for clean-up, maintenance and reconstruction costs involving machinery and Building No. 75, making a total claimed loss of $82,150.09, which amount was apparently paid to Hammermill by its insurance carrier under a binder to its fire insurance policy. 2

Hammermill’s insurance carrier in the name of Hammermill instituted this assumpsit action against Rust in the Court of Common Pleas of Erie County to recover $82,150.09. Rust filed an answer containing new matter, Hammermill filed a reply thereto and Rust moved for judgment on the pleadings, which motion was granted. The court below, granting Rust’s *369 motion for judgment on the pleadings, concluded that Rust was “. . . an employee agency under the direct control of Hammermill” and that Hammermill alone was at fault, having retained the control and responsibility for the construction of the wall. With those conclusions of the court below we do not agree.

The pleadings fail to disclose the extent of the controls and approvals to be exercised by Hammermill and the interrogatories taken likewise fail to make such disclosure.

Article III of the contract between the parties entitled “Engineer-Constructor’s Services” provides: “A. With respect to the ‘Scope of Work’, as outlined above, (Rust) proposes to act as (Hammermill’s) engineering, purchasing and construction departments, performing the work with his own forces and subletting parts when it is to the best interest of and approved by (Hammermill). The specific services to be performed by (Rust), and the controls and approvals to be exercised by (Hammermill) shall be itemized in a job procedure to be prepared jointly by (Hammermill) and (Rust).

“B. (Rust) shall check all material and labor entering into the work and keep such detailed accounts as may be necessary to proper financial management under this contract, and the system shall be such as is satisfactory to (Hammermill) or to an auditor appointed by (Hammermill). (Hammermill) shall be afforded access to the work and to all (Rust’s) records relating to this contract.” (Emphasis added).

Nowhere in the agreement is there any specific language which gives Hammermill the responsibility for final approval of the designs and specifications to be prepared by Rust, nor any indication that Hammer-mill, following the guidelines of such design and specifications, was to supervise, inspect and approve as the work progressed. In this agreement, Hammermill *370 contracted to engage the independent services of Rust to accomplish a particular result. Hammermill was interested, primarily, in the result, and secondarily, in keeping an eye on the costs incurred. It is apparent from a reading of this agreement in its entirety that a certain modicum of control was agreed upon by the parties but such control was to enable Hammermill to regulate the costs of the project.

.While no hard and fast rule exists to determine whether a particular relationship is that of employer-employee or owner-independent contractor, certain guidelines have been established and certain factors are required to be taken into consideration:

“Control of manner work is to be done; responsibility for result only; terms of agreement between the parties; the nature of the work or occupation; skill required for performance; whether one is engaged in a distinct occupation or business; which party supplied the tools; whether payment is by the time or by the job; whether work is part of the regular business of the employer, and also the right to terminate the employment at any time.” Stepp v. Renn, 184 Pa. Superior Ct. 634, 637, 135 A. 2d 794 (1957). See also: Hader v. Coplay Cement Mfg. Co., 410 Pa. 139, 150, 189 A. 2d 271 (1963).

The fact that Hammermill retained control necessary to supervise and exercise direction over the costs feature of the work, that it secured the necessary work permits and that it retained the right to add to or subtract from the work to be done, does not convince us that Hammermill thereby occupied the status of an employer of Rust. Naturally, Hammermill was interested in the result and the cost of attaining such result but the indicia of such interest as delineated in the agreement do not constitute an assumption of responsibility for the manner.in which the work was to *371 be done by Bust. Rust was a specialist and possessed expertise in tbe construction field and it was certainly cognizant of the application of building codes to actual jobs and tbe standards of strength and quality to be put into a particular job, taking into consideration tbe owner’s needs, local surface and sub-surface conditions and tbe effect of weather on tbe resultant construction. Between tbe parties, Rust, and only Rust,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D&R Construction v. H. Suarez (WCAB)
Commonwealth Court of Pennsylvania, 2025
Williams, A. v. FemmePharma Consumer
Superior Court of Pennsylvania, 2024
MONTGOMERY v. BOBST MEX SA
E.D. Pennsylvania, 2024
WOODHOUSE v. SPEARMAN
E.D. Pennsylvania, 2023
Nationwide Mutual Fire Ins. Co. v. Benjamin, L.
Superior Court of Pennsylvania, 2021
R. Shannon v. WCAB (Ogden Newspapers of PA)
Commonwealth Court of Pennsylvania, 2020
Abbasi Communications & Phoenix Ins. Co. v. WCAB (Cramer)
Commonwealth Court of Pennsylvania, 2019
Q.H. Zhang v. WCAB (Chopstix 4041, LLC and UEGF)
Commonwealth Court of Pennsylvania, 2019
F. Baykhanov v. WCAB (Onixe Express)
Commonwealth Court of Pennsylvania, 2018

Cite This Page — Counsel Stack

Bluebook (online)
243 A.2d 389, 430 Pa. 365, 1968 Pa. LEXIS 710, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammermill-paper-co-v-rust-engineering-co-pa-1968.