Hamilton Construction Co., V. Dept. Of L&i

CourtCourt of Appeals of Washington
DecidedOctober 12, 2021
Docket54578-1
StatusUnpublished

This text of Hamilton Construction Co., V. Dept. Of L&i (Hamilton Construction Co., V. Dept. Of L&i) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamilton Construction Co., V. Dept. Of L&i, (Wash. Ct. App. 2021).

Opinion

Filed Washington State Court of Appeals Division Two

October 12, 2021

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

HAMILTON CONSTRUCTION CO., No. 54578-1-II

Appellant,

v. UNPUBLISHED OPINION

DEPARTMENT OF LABOR & INDUSTRIES OF THE STATE OF WASHINGTON,

Respondent.

MAXA, J. – The Department of Labor and Industries (DLI) issued a citation against

Hamilton Construction Company for violations of regulations under the Washington Industrial

Safety and Health Act of 1973 (WISHA), chapter 49.17 RCW, related to demolition work on a

highway overpass in Bonney Lake. The citations arose from an incident in which two Hamilton

workers for Hamilton’s subsidiary were using a curb saw to cut a concrete rail barrier on the

overpass when the barrier fell onto the roadway below and killed three people in a passing

vehicle.

DLI cited Hamilton for failing to have a written engineering survey, failing to ensure that

nobody was working below the bridge during the cutting operation, and failing to ensure that the

barrier was secured or braced during demolition. The Board of Industrial Insurance Appeals

(Board) issued a decision and order that affirmed three violations. On appeal, the superior court

affirmed the Board’s decision and order. No. 54578-1-II

We conclude that (1) substantial evidence supports the Board’s findings that Hamilton

was a subcontractor and an “employer” subject to liability under WISHA, (2) substantial

evidence supports the Board’s findings of fact and conclusions of law affirming the three

WISHA violations, and (3) substantial evidence supports the Board’s implied findings of fact

that Hamilton had actual or constructive knowledge of the WISHA violations. Accordingly, we

affirm the superior court’s order affirming the Board’s decision and order.

FACTS

Background

Hamilton operates as a prime contractor on construction projects and primarily builds

bridges. Hamilton is the parent company of American Concrete Company, which specializes in

concrete cutting, including saw cutting, grinding, and surface preparation. American Concrete

operates as a subcontractor on most projects. American Concrete had approximately 20

employees at the time of the DLI inspection.

When a third party wants American Concrete to perform concrete cutting on a project,

the procedure is to contact American Concrete’s dispatcher with the details of the project. Based

on the information given from the third party, American Concrete determines the type of

equipment necessary to complete the requested cut and which operators should be sent for the

job. American Concrete typically provides its own equipment for a job.

If the third party request involves a large project or requires American Concrete to be

involved in the planning process, then American Concrete will enter into a written contract with

the requesting party. If the third party request is on short notice or for a project lasting a day or

less, no contract typically is created because usually there is not enough time to complete the

paperwork and execute a contract before the work takes place.

2 No. 54578-1-II

Bonney Lake Project

The City of Bonney Lake contracted with a general contractor to modify and/or repair a

bridge on State Route 410, which was an overpass over another road. The general contractor

hired a number of subcontractors, including Staton Companies, to work on the Bonney Lake

project. Staton was a demolition subcontractor.

On April 12, 2015, a Staton employee contacted Rick Garrick, an American Concrete

dispatcher, about the Bonney Lake project. Staton wanted to hire American Concrete to remove

a concrete rail barrier on a bridge deck.

Because of the small size of the job, no written contract was created. Based on the

information given from Staton, Garrick dispatched two American Concrete employees, Richard

Dugan and Donald Corkhill, with a large curb saw on a trailer, a vacuum truck, a water tank, and

other equipment. A curb saw is a large machine, eight feet long and five feet wide, that is used

to cut concrete.

Dugan was a trained curb saw operator while Corkhill was a vacuum operator. Dugan

operated the curb saw, which involved spraying water from the water tank to cut concrete. This

produced a liquid substance called slurry, a mixture of concrete and water. Corkhill vacuumed

the slurry behind the curb saw.

On April 13, Dugan and Corkhill met the Staton foreman, Morgan Marney, at a freeway

exit away from the jobsite. Dugan and Corkhill did not know where the job was located until

they were taken there. When they arrived at the job site, Marney showed schematic as-built

diagrams to Dugan. The as-built diagrams showed how the bridge originally was built but did

not provide information as to how Dugan should cut the barrier. Dugan explained that the as-

built diagrams showed where the steel was located to give him an idea as to how deep he needed

3 No. 54578-1-II

to cut. The as-built diagrams did not accurately depict the bridge deck at the time the work was

to be performed. There were important differences between the bridge deck depicted and the

bridge deck at the time the demolition was being performed. Dugan and Marney discussed the

as-built diagrams and agreed as to how Dugan would cut the barrier.

Hamilton did not perform an engineering survey. And at no time were Dugan and

Corkhill presented with a written engineering survey of the structural integrity of the bridge or a

demolition plan for the job. Dugan was unaware of any engineering survey. However, Dugan

was aware of Staton’s demolition plan and performed saw cutting activities consistent with the

plan.

According to Dugan, the plan was to make a horizontal cut of the concrete rail barrier at

the edge of the bridge along the full length of the bridge, followed by vertical cuts with a

different saw to divide the barrier into smaller pieces that an excavator could detach and remove

safely. The excavator was on site and manned by employees from a different company. Marney

had control of the use of the excavator. The excavator was supposed to be used to brace or

stabilize the barrier during the concrete cutting operation. However, the curb saw was so large

that the excavator could not be used as anticipated. This left the cut portions of the barrier

unbraced. In addition, the excavator was missing an attachment that was supposed to help brace

the structure. No other method of bracing was provided. Regardless, Dugan and Corkhill began

their concrete cutting operation.

Two WHH Nisqually employees were present on the roadway below the bridge to

monitor and stop traffic on the road when the last cut was made. Carla Vandiver was a traffic

control supervisor who was supervising one other flagger, Shelby King. Marney was responsible

for calling Vandiver before American Concrete made the final cut.

4 No. 54578-1-II

Only Dugan, Corkhill, and Marney were present in the immediate concrete cutting area.

Marney was responsible for overseeing the job, but Dugan stated that Marney was not allowed to

operate the curb saw machine. Dugan made two complete horizontal cuts of four and eight

inches deep. The concrete barrier remained stable during those cuts. A larger blade was used for

the third and final horizontal cut. Approximately 50 feet into the cut, Dugan and Corkhill

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nationwide Mutual Insurance v. Darden
503 U.S. 318 (Supreme Court, 1992)
Stute v. P.B.M.C., Inc.
788 P.2d 545 (Washington Supreme Court, 1990)
White v. Department of Labor & Industries
294 P.2d 650 (Washington Supreme Court, 1956)
Jones v. Halvorson-Berg
847 P.2d 945 (Court of Appeals of Washington, 1993)
Mountain States Contractors v. Thomas Perez
825 F.3d 274 (Sixth Circuit, 2016)
Potelco, Inc. v. Department Of Labor And Industries
433 P.3d 513 (Court of Appeals of Washington, 2018)
Afoa v. Port of Seattle
296 P.3d 800 (Washington Supreme Court, 2013)
Wilcox v. Basehore
389 P.3d 531 (Washington Supreme Court, 2017)
Martinez Melgoza & Associates, Inc. v. Department of Labor & Industries
106 P.3d 776 (Court of Appeals of Washington, 2005)
Grange Insurance v. Roberts
320 P.3d 77 (Court of Appeals of Washington, 2013)
Potelco, Inc. v. Department of Labor & Industries
361 P.3d 767 (Court of Appeals of Washington, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Hamilton Construction Co., V. Dept. Of L&i, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamilton-construction-co-v-dept-of-li-washctapp-2021.