Hall-Vesole Co. v. Durkee-Atwood Co.

35 N.W.2d 601, 227 Minn. 379, 1949 Minn. LEXIS 493
CourtSupreme Court of Minnesota
DecidedJanuary 7, 1949
DocketNo. 34,746.
StatusPublished
Cited by5 cases

This text of 35 N.W.2d 601 (Hall-Vesole Co. v. Durkee-Atwood Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hall-Vesole Co. v. Durkee-Atwood Co., 35 N.W.2d 601, 227 Minn. 379, 1949 Minn. LEXIS 493 (Mich. 1949).

Opinion

Loring, Chief Justice.

This is an appeal from an order denying defendant’s motion for a new trial. The evidence was presented before a jury, and during the court’s charge the parties agreed that three interrogatories should be submitted to the jury. All other questions involved were, by stipulation, submitted to the court for findings and conclusions upon the jury’s answers to the interrogatories and the evidence in the case. Plaintiff prevailed on the interrogatories, the findings, and the conclusions of the court.

*380 Hall-Vesole Company, a corporation, brought suit to recover for alleged overcharges on services performed by defendant between August 19áá and December 31, 1945, consisting of coating cloth or paper with luminous material and special adhesives in connection with a war contract awarded by the government to plaintiff’s assignor and predecessor, the Hall-Vesole Company, a partnership (hereinafter referred to as Hall-Vesole), composed of Dr. Ray E. Hall, who was the technician developing the special process and supervising production; A. J. Casteleiro, the salesman; and W. M. Loberg, the auditor and financial clerk. The assets of the partnership, Hall-Vesole, including this claim against defendant for the amounts paid to defendant in excess of the agreed compensation, were acquired by plaintiff on or about May 1, 1946.

As a result of negotiations during August and September 1944, defendant agreed orally to perform coating services for the partnership at an agreed price per man hour for the time its employes were engaged in such production. At the trial, it was disputed whether the price per hour agreed upon was $3 per man hour or $3.30 per man hour. From month to month, the defendant rendered debit memoranda to the partnership for such services. These memoranda simply stated: “Spreader Room charges for [naming the month].” The writing did not state the hourly basis of compensation on which they were computed, nor. the total number of man hours performed during the month for which the account was rendered. A copy of a typical memorandum appears in a footnote. 2 In addition, state *381 ments summarizing the costs of materials, waste, salvage charges, slitting room and spreader room charges, and credits were occasionally furnished in the form set out in the footnote. 3 Defendant also maintained a ledger account sheet which showed the running account for Hall-Vesole, but did not itemize charges. 4 No “Remarks” appeared on the ledger sheets.

*382 Viewing the testimony, as we must, in its aspects most favorable to plaintiff, there was evidence tending to prove that there was some discussion between the parties, but no actual agreement was made, that the method of charging for services on an hourly basis would be changed to a yardage basis when mass production was reached and development beyond the experimental state was attained. This point was reached about January 1, 1945. From then on, defendant computed its debit memoranda on that basis without so indicating on the bills or notifying plaintiff. Prior to that time, however, by oral agreement, the spreader room charges were increased about 10 percent. There was a dispute as to whether the new rate of compensation was $3.30 per man hour, as claimed by plaintiff, or whether the rate then became $3.60 per man hour, as computed by defendant, as a basis for its debit memoranda. The jury found for plaintiff. During the six-month period in 1945 when production reached a stabilized output level, bills were computed by defendant on the basis of $22.44 per 100 square yards of material given three coats of adhesive and luminous substance, and $28.17 per 100 square yards of material given four coats. After June 30, 1945, production dropped, and debit entries were computed by defendant on a basis of $3.60 per man hour, again without notifying plaintiff. Hall-Vesole paid the amounts noted on the debit memoranda as rendered, obviously on the assumption that the bills were correct and according to agreement and without checking the number of man hours or hourly rate or other basis upon which each memorandum was computed.

The court below, basing its findings upon the jury’s answer to interrogatories, found that the partnership paid $36,929.19 to defendant through December 31, 1945, all of which was paid on or before June 7, 1946, and that defendant was entitled to payment for services in the spreader room in the total sum of only $26,564.41. Judgment was ordered against defendant for $10,364.78 with interest at six percent from January 3, 1947, together with costs and disbursements. Defendant was awarded $1,376.18 on a counterclaim for services performed in the spreader room and slitting room during *383 1946, which amount was deducted by the court from overcharges collected by defendant.

After the evidence had been presented and during the court’s charge to the jury, the parties stipulated as follows:

“It is stipulated by and between plaintiff and defendant, through their respective attorneys that the court may submit to the jury the three interrogatories which are agreed upon and conditioned upon the answers the issues remaining undetermined shall be decided by the court in the findings of fact and conclusions of law based upon the answers to such interrogatories and the evidence in this case.”

The three special interrogatories submitted to the jury and its answers thereto’were as follows:

“I.
“When the Hall-Vesole Company and the Durkee-Atwood Company first agreed upon the price to be charged Hall-Vesole Company for spreader room service, was that agreed price $3.00 per man hour, as claimed by plaintiff, or $3.30 per man hour as claimed by the defendant? $3.00.
“II.
“When the price for spreader room services was increased on November 20, 1944, was the new agreed price $3.30 per man hour as claimed by plaintiff, or $3.60 per man hour as claimed by the defendant? $3.30.
“III.
“Did the Hall-Vesole Company at any time impliedly agree, that the charge for spreader room services for the period from January through June of 1945 should be computed on a yardage basis instead of the man-hour basis fixed on November 20, 1944? No.”

Of course no general verdict was returned.

Counsel for defendant contends that the monthly memoranda rendered by defendant and paid by Hall-Vesole constituted an account stated and that it cannot be impeached or set aside on the ground of unilateral mistake; that Hall-Vesole was under a duty *384

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roehrdanz v. Schlink
368 N.W.2d 409 (Court of Appeals of Minnesota, 1985)
Trimble Cattle Co. v. Henry
592 P.2d 1310 (Court of Appeals of Arizona, 1979)
Cavanagh v. Bostitch, Inc.
162 A.2d 785 (Supreme Court of Rhode Island, 1960)
Meagher v. Kavli
88 N.W.2d 871 (Supreme Court of Minnesota, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
35 N.W.2d 601, 227 Minn. 379, 1949 Minn. LEXIS 493, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hall-vesole-co-v-durkee-atwood-co-minn-1949.