Hagerstown Elderly Associates Ltd. Partnership v. Hagerstown Elderly Building Associates Ltd. Partnership

793 A.2d 579, 368 Md. 351, 2002 Md. LEXIS 99
CourtCourt of Appeals of Maryland
DecidedMarch 12, 2002
Docket29, Sept. Term, 2001
StatusPublished
Cited by9 cases

This text of 793 A.2d 579 (Hagerstown Elderly Associates Ltd. Partnership v. Hagerstown Elderly Building Associates Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hagerstown Elderly Associates Ltd. Partnership v. Hagerstown Elderly Building Associates Ltd. Partnership, 793 A.2d 579, 368 Md. 351, 2002 Md. LEXIS 99 (Md. 2002).

Opinions

RAKER, J.

Appellant, Hagerstown Elderly Associates Limited Partnership, is the owner of a public housing facility in Hagerstown, Maryland known as Elizabeth Court. On or about October 14, 1995, a portion of an exterior wall of the eleven-story building fell to the ground. A year later, on October 16, 1996, appellant filed suit in the Circuit Court for Washington County against appellees Hagerstown Elderly Building Associates (HEBA), the contractor that erected the building, and Seaboard Surety Company (Seaboard), the surety on the performance bond filed by HEBA in connection with that construction, to recover the expense of restoring the building and correcting what appellant regarded as deficient work. Vari[354]*354ous subcontractors were eventually added as third-party defendants.

The Circuit Court granted summary judgment to appellees on the grounds that (1) the action against the contractor, HEBA, was barred by the ten-year statute of repose codified in Maryland Code (1957, 1998 RepLVoL, 2001 Supp.) § 5-108(b) of the Courts and Judicial Proceedings Article1 and (2) the action against the surety, Seaboard, was barred by the twelve-year statute of limitations codified in § 5-102. We granted certiorari on our own initiative, prior to any decision by the Court of Special Appeals, to review the issues presented in those rulings.

We find no error in the Circuit Court’s granting of summary judgment to HEBA on Count I and shall, therefore, affirm that judgment. We find, however, that the court erred in granting summary judgment to appellees on Count II and shall, therefore, reverse that judgment.

I.

Elizabeth Court is a public housing facility for elderly and disabled persons. Construction of the project was financed by the State Community Development Administration (CDA) and the Maryland Housing Fund (MHF), using funds provided by the United States Department of Housing and Urban Development. The construction contract between appellant and HEBA, dated October 22, 1982, required HEBA to provide a payment and performance bond assuring appellant and CDA that the contractual work would be completed, and, in conformance with that obligation, appellees issued such a bond, running jointly to appellant and CDA. The bond obligated appellees, jointly and severally, to appellant and CDA in the amount of $4,284,000 — the construction contract price — for the prompt and faithful performance of the contract, but provided that any suit under the bond must be instituted before the [355]*355expiration of two years “from the date on which final payment under the Contract falls due.”

HEBA subcontracted the installation of the exterior wall system to Novinger’s, Inc. That system, referred to by the parties as an exterior insulation finish system (EIFS), consisted of multiple layers of different materials intended to provide thermal insulation and protection against infiltration of the elements.

The City of Hagerstown conducted a final inspection and issued a Use and Occupancy Permit for the building on December 16, 1983. HEBA and the architect filed a Certificate of Substantial Completion on December 21,1983. On the same day, appellant granted permission for the occupancy of all 110 units of the project. Pursuant to the Certificate of Substantial Completion, HEBA was presented with a “punch list” of final items to be corrected or completed, for which, in accordance with the construction contract, part of the final payment was placed in escrow. On February 28, 1984, HEBA advised the architect that it had completed all of the items listed on the architect’s final inspection report and requested that the architect reinspect those items so that no escrow would be required at final closing. CDA applied to MHF for insurance of the advance of mortgage proceeds on October 10, 1984. On October 26, 1984, MHF approved an advance of $316,818.00. A final loan closing, for the release of the remaining funds, was set for and took place on November 1, 1984. Final payment was made to HEBA the following day, on November 2, 1984.

On October 14, 1995, an unusually severe storm hit Hagers-town, during which a large section of the exterior wall surface of the building blew out and fell to the ground. After conducting an investigation, appellant concluded that the incident occurred because of faulty construction of the EIFS system, causing the wall surface to debond and eventually fall. Appellant claimed that it had no knowledge, and no reason to know, of the faulty construction until the actual collapse. On October 16, 1996, appellant filed this suit, seeking in Count I of its [356]*356complaint to recover against HEBA for breach of contract and in Count II to recover against HEBA and Seaboard under the performance bond.

The Circuit Court for Washington County granted summary judgment in favor of appellees on both counts of the complaint. With respect to Count I, the court found that the action was barred by statute of repose contained in § 5-108(b). With respect to Count II, the court declined to apply the two-year statute of limitations provided for in the performance bond, holding that, by virtue of Maryland Code (1957, 1998 Repl.Vol., 2001 Supp.) § 12-104 of the Insurance Article, that provision was against public policy and void.2 The court concluded that the applicable period of limitations was that set forth in § 5-102(a)(2) — namely, that an action on a bond shall be filed within twelve years of accrual of the cause of action. Although the court found the two-year limitations period set forth in the bond unenforceable, it looked to that provision to determine the parties’ intent as to when the accrual time commenced, which was “the date on which final payment under the Contract falls due.” Although the court consulted Article 3C of the contract and § 9.9.2 of the General Conditions, it ultimately found dispositive CDA’s October 10, 1984 request for final payment from MHF of the “punch list” items, in which CDA declared its belief that that amount was then “payable.” As the suit was filed twelve years and six days after that date, the court held Count II to be barred by limitations.

II.

In this appeal, appellant urges that (1) the statute of repose set forth in § 5 — 108(b) does not bar the action in Count I [357]*357because it does not apply to breach of contract actions or claims arising out of injury to the property containing the allegedly defective and unsafe condition and (2) the Circuit Court erred in fixing the final payment due date for purposes of the action on the performance bond as October 10, 1984, rather than November 1, 1984. Appellant contends that § 5-108(b) is not applicable for two, somewhat overlapping, reasons. First, appellant claims that the section is directed only at tort actions and not at actions based on breach of contract. The language, it urges, “is expressly couched in the classic terminology of tort, not contract.” Second, it argues that the section applies “only to actions either for personal injury or for damages to real or personal property other than the property containing the defective and unsafe improvement.” (Emphasis added). It posits that the section “expressly refers only to situations where (a) a defective and unsafe ‘condition’ of an improvement to real property separately causes (b) a separate injury to other

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SVF Riva Annapolis LLC v. Gilroy
187 A.3d 686 (Court of Appeals of Maryland, 2018)
Gilroy v. SVF Riva Annapolis LLC
168 A.3d 1130 (Court of Special Appeals of Maryland, 2017)
Anderson v. United States
46 A.3d 426 (Court of Appeals of Maryland, 2012)
Streeter v. SSOE SYSTEMS
732 F. Supp. 2d 569 (D. Maryland, 2010)
ST. PAUL TRAVELERS v. Millstone
987 A.2d 116 (Court of Appeals of Maryland, 2010)
Millstone v. ST. PAUL TRAVELERS
962 A.2d 432 (Court of Special Appeals of Maryland, 2008)
Janey v. State
891 A.2d 355 (Court of Special Appeals of Maryland, 2006)
Meeks v. Dashiell
890 A.2d 779 (Court of Special Appeals of Maryland, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
793 A.2d 579, 368 Md. 351, 2002 Md. LEXIS 99, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hagerstown-elderly-associates-ltd-partnership-v-hagerstown-elderly-md-2002.