Hagerman v. United States

180 F. Supp. 181, 1960 U.S. Dist. LEXIS 5268
CourtDistrict Court, D. Wyoming
DecidedJanuary 22, 1960
DocketCiv. No. 4269
StatusPublished

This text of 180 F. Supp. 181 (Hagerman v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hagerman v. United States, 180 F. Supp. 181, 1960 U.S. Dist. LEXIS 5268 (D. Wyo. 1960).

Opinion

KERR, District Judge.

Earl W. Hagerman, doing business as Hagerman Construction, brings this suit against the United States of America under the Tucker Act, 28 U.S.C.A. § 1346 (a) (2), for damages arising from an alleged breach of contract by the defendant. The defendant has filed an answer and subsequent thereto filed a motion for summary judgment, urging that the case falls clearly within the rule announced by the Supreme Court of the United States in United States v. Howard P. Foley Co., 329 U.S. 64, 67 S.Ct. 154, 91 L.Ed. 44; H. E. Crook Company v. United States, 270 U.S. 4, 46 S.Ct. 184, 70 L.Ed. 438; United States v. Rice, 317 U.S. 61, 63 S.Ct. 120, 87 L.Ed. 53. The matter is before the Coux-t on the motion for summary judgment.

The basic facts can be stated and the relevant history told from the pleadings, the contract, affidavits, correspondence, opinion of the Board of Contract Appeals, all of which are uncontradicted so far as the record of the case is concerned.

The complaint alleges in substance as grounds for recovery that notwithstanding the agreement of the defendant to furnish metal pipe and accessories necessary for the completion of the work undertaken by the plaintiff, and in violation of the terms of the-agreement, defendant failed and neglected to furnish such materials within the time reasonably necessary for the proper completion of the work and furnished defective materials, by reason of which plaintiff was unreasonably and improperly delayed in the prosecution of the construction work, all to his damage in the sum of $7,214.36.

The cause of the delay encountered in the completion of the contract becomes of vital importance. Northwestern Engineering Co. v. United States, 8 Cir., 154 F.2d 793.

On December 30,1957, plaintiff entered into a written contract with defendant, acting through W. B. Wallace, Area Administrator of the Bureau of Land Management, Department of the Interior, for the construction by plaintiff of a 21,000 cubic yard detention type dam in Washakie County, Wyoming. This contract constitutes the subject of this controversy.

On March 17, 1958, the defendant awarded an independent contract to the Eaton Metals Products Company (hereinafter referred to as “Eaton”) to supply corrugated metal pipe and accessories to be used in the construction of said retention dam and to be delivered within 45 days from the date of the receipt of the order for a price of $3,306.26. The order was received by Eaton March 24, 1958. The contract with Eaton required that the corrugated pipe should be water tight for low heads, which, according to accepted industry practice, would be any head up to 20 feet. On April 10, 1958, defendant called Eaton and explained the urgent need for the materials to be furnished by it and requested an earlier delivery date than that called for under their contract. Eaton advised the defendant that it thought the delivery would probably be made the last week in April 1958 and also stated it would call [183]*183'by telephone on April 14 or 15 to indicate the exact date. No call was received from Eaton. On May 1, 1958, Eaton wrote defendant as follows:

“This is to advise that we have begun fabrication April 30, 1958, a. m. on this material with the exception of the 30" pipe and elbows. This material covering this 30" pipe will not arrive in Billings until May 5, 1958, from our supplier. The rest of the material will be delivered to you on approximately the week of May 5, 1958, or right around May 7, 1958. The balance of the material we hope to have to you by May 13, 1958.”

On the basis of the aforesaid letter and on May 7, 1958, defendant gave notice to Hagerman to proceed with the work under the contract. The contract completion time was 35 days, thus setting the completion date for June 11, 1958. It will be observed that the notice to proceed was issued in anticipation by the defendant that the materials to be furnished by Eaton would be available for use by the plaintiff in the normal course of construction work and under the belief that the materials would be delivered on or before May 13, 1958. On May 13, 1958, the contractor was on schedule. Eaton made deliveries under its contract to defendant on May 12, 22, 27, 28 and June 4, 1958.

Final delivery of materials to be furnished by the defendant was not made until June 4, 1958, at which time the materials were installed by the plaintiff and tested in accordance with Paragraph 9, “Specifications”, of the contract. During the test made by the plaintiff latent defects in the materials furnished by Eaton were brought to light and determined to be such that the necessary repair could not be completed on the job. On June 6, 1958, plaintiff was ordered to remove the materials and on June 9 and 10, 1958, they were picked up by Eaton for repairs. The pipe was removed at Eaton’s expense. The pipe was repaired by Eaton and returned for installation on June 23,1958. The second installation was delayed by further disclosure of defects in the re-test of the pipe, necessitating a further shut down of operations while repairs were being made. On July 9, 1958, the defendant accepted the pipe as satisfactory, at which time construction work was resumed. As a result of the delays caused by Eaton the defendant extended the completion date of the contract as authorized in the “Delays” clause to August 8, 1958, and the work was completed on said date.

The record discloses the defendant made telephone calls and sent wires to Eaton on April 10, May 14,19, 22, 23, 28, 29, June 6, 18, July 3 and 5, urging them to expedite the delivery of the materials.

The above recitation of facts contained in this memorandum are taken from the affidavits of the agents of the defendant and stand without challenge or controversy.

An examination of the contract fails to disclose the defendant promised to deliver the pipe at any specified time. Obviously if the defendant did not deliver the pipe within the completion date of the contract Hagerman had a right to ask for an extension of such completion date. This was done.

Finally, there is no evidence or document in the record, including the complaint, which tends to show the government was in any way at fault in failing to exert its best efforts to obtain the pipe it had agreed to furnish. On the contrary, I find it exercised great diligence in an effort to secure the pipe and its inability to do so was not attributable to any fault or neglect on the part of the government. It is equally clear the delay was caused by Eaton furnishing defective materials.

Paragraph 6 of the Additional General Provisions of the contract specifically provides: “The Contracting Officer’s Authorized Representative may give written notice to the Contractor ordering stoppage of the work because of * * * faulty equipment, * * *. * * * If such work interruption is beyond the [184]*184control of and not due to the fault or negligence of the contractor, he shall not be charged for the delay”. (Emphasis supplied.)

I am unable to distinguish the case at bar from United States v. Howard P. Foley Co., 329 U.S. 64, 67 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wood v. United States
258 U.S. 120 (Supreme Court, 1922)
H. E. Crook Co. v. United States
270 U.S. 4 (Supreme Court, 1926)
United States v. Rice
317 U.S. 61 (Supreme Court, 1942)
United States v. Howard P. Foley Co.
329 U.S. 64 (Supreme Court, 1946)
Northwestern Engineering Co. v. United States
154 F.2d 793 (Eighth Circuit, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
180 F. Supp. 181, 1960 U.S. Dist. LEXIS 5268, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hagerman-v-united-states-wyd-1960.