Northwestern Engineering Co. v. United States

154 F.2d 793, 1946 U.S. App. LEXIS 3130
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 11, 1946
DocketNo. 13153
StatusPublished
Cited by1 cases

This text of 154 F.2d 793 (Northwestern Engineering Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern Engineering Co. v. United States, 154 F.2d 793, 1946 U.S. App. LEXIS 3130 (8th Cir. 1946).

Opinion

WOODROUGH, Circuit Judge.

The Northwestern Engineering Company, a corporation, brought this action against the United States of America under the Tucker Act, 28 U.S.C.A. § 41(20), for damages arising from an alleged breach of contract by defendant, and for costs of suit and interest from date of judgment. 28 U.S.C.A. §§ 258, 284. Judgment was entered for defendant and plaintiff appeals.

In 1941 defendant was engaged in improving an airbase owned by the City of Billings, Montana. The work was a Works Progress Administration project sponsored by the City. In connection with the project, defendant advertised for bids for use of a travelling road building machine and operating .crew, to be paid for on a production basis. The instructions for bidders contained a description of the work to be performed, and a warning that each bidder should inspect the site, investigate the character of materials and examine the specifications. The specifications required the machine furnished to have a capacity sufficient to place at least 150 tons of material per hour, described the method to be employed in mixing and spreading and provided for payment based on square yards in place as measured by defendant. They further provided that defendant would furnish aggregate, placed in windrows, and necessary bituminous paving materials delivered alongside the paving machine, and would furnish rolling and compacting operations and aggregate for a surface course laid down on the base course in properly sized and spaced windrows. The specifications also provided that the successful bidder should not remove the equipment furnished from the project prior to its release unless authorized to do so by the Works Progress Administration state procurement officer.

The plaintiff, being the successful bidder, obtained a machine having a capacity of 180 tons per hour for which plaintiff was [795]*795required to pay the owner $3,000 per month rental, which was stipulated by the parties to be a reasonable rate. The machine and its crew were at the airport ready for work on July 9, 1941. The plaintiff contends that if sufficient aggregate had been furnished by the Government to enable plaintiff to keep its machine operating at substantial capacity for two 8-hour shifts each day, the work could have been completed and the machine released on or about July 31, 1941, which plaintiff contends was the contract date for completion of the work. However, the aggregate was not furnished in quantities sufficient to finish the job by that date, the work continued throughout the summer, and the machine furnished by plaintiff was not released until October 17, 1941.

The plaintiff was paid in full on a production basis for the actual work performed in connection with the contract, and this action is for damages resulting from the delay in completion of the contract during the period from August 1, 1941, to October 17, 1941, during which time the machine and its crew were kept on the job allegedly beyond the contract period.

The original “Invitation, Bid and Acceptance” signed by representatives of the parties contained no specific reference to a date for completion of the work to be performed nor a date for expiration of the contract. However, copies of the invitation, bid and acceptance furnished by defendant to plaintiff and to defendant’s job superintendent, contained a typewritten notation that the contract was to expire not later than July 31, 1941. The plaintiff contends that the typewritten notation constituted a contractual obligation of the parties and that failure of defendant to furnish aggregate sufficient to complete the job by July 31 constituted a breach of contract for which defendant must respond in damages. The copies containing the notation were not executed by the parties and cannot be considered as duplicate originals. Under elementary principles, the instrument signed by representatives of the parties sought to be bound constituted the contract and rights and obligations of the parties must be determined from an examination of that instrument, without regard to the unexplained notation appearing on the unsigned copies. We sustain the holding of the trial court that the contract did not by its terms require the work to be performed at any particular time and that plaintiff’s contention that defendant had the absolute duty to supply aggregate in sufficient quantities to assure completion of the work by July 31, 1941, is without merit.

The contract provided that the equipment furnished by plaintiff was “to be operated at times and places designated by the government’s instructions,” and provided for compensation based solely on production. The District Court held, and we think correctly, that under this contract plaintiff could not recover for loss sustained as a result of delay in absence of arbitrary or inexcusable failure or neglect on the part of defendant. The defendant in agreeing to furnish the aggregate and in requiring a machine having the capacity to mix and spread a minimum of 150 tons per hour, was under the implied obligation to proceed with the work with reasonable diligence. United States v. Smith, 94 U.S. 214, 24 L.Ed. 115; United States v. Mueller, 113 U.S. 153, 5 S.Ct. 380, 28 L.Ed. 946. As stated in the Smith case, supra [94 U.S. 217], “There was no time specified within which the work must be done, neither was there any power reserved in the United States to direct its suspension. Under such circumstances, the law implies that the work should be done within a reasonable time, and that the United States would not unnecessarily interfere to prevent this.” In the present case there was an implied condition that defendant would not delay plaintiff in the performance of the work. Kuney v. United States, 95 Ct.Cl. 512. Defendant could not, without reasonable excuse, fail to furnish material to keep plaintiff’s machine in operation, but time was not declared to be of the essence and the defendant’s duty to furnish sufficient material was not an absolute one. The court has no power to make a new and different contract for the parties. United States v. Cunningham, 75 U.S.App.D.C. 95, 125 F.2d 28.

The cause of the delays encountered in completion of the contract becomes of vital importance. The defendant contends that the delays resulted from inclement weather and other conditions over which it had no control. The plaintiff contends that the delays, at least those occurring in July and August, 1941, resulted from defendant’s use of inexperienced labor and supervision in connection with the preparation of the [796]*796aggregate. The District Court found as a fact that the delays were caused by “the weather, climate and other conditions over which defendant had no control,” and against which it did not undertake to insure plaintiff, and concluded that defendant was in no way liable for the loss resulting from the delays and failure to release the machine until October 17, 1941.

In determining the fact question involved we are mindful that the findings of fact of the District Court will not be disturbed unless they are clearly erroneous. Federal Rules of Civil Procedure, rule 52, 28 U.S.C.A. following section 723c; Smith v. Porter, 8 Cir., 143 F.2d 292; Sandlin v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hagerman v. United States
180 F. Supp. 181 (D. Wyoming, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
154 F.2d 793, 1946 U.S. App. LEXIS 3130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-engineering-co-v-united-states-ca8-1946.