H. O'CONNOR, INC. v. JR Autenreith, Inc.

343 So. 2d 1090
CourtLouisiana Court of Appeal
DecidedMay 5, 1977
Docket7732
StatusPublished
Cited by5 cases

This text of 343 So. 2d 1090 (H. O'CONNOR, INC. v. JR Autenreith, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. O'CONNOR, INC. v. JR Autenreith, Inc., 343 So. 2d 1090 (La. Ct. App. 1977).

Opinion

343 So.2d 1090 (1977)

HUGH O'CONNOR, INC.
v.
J. ROBERT AUTENREITH, INC. and Plumbers and Steamfitters Local 60 Home Association, Inc.

No. 7732.

Court of Appeal of Louisiana, Fourth Circuit.

January 12, 1977.
On Rehearing March 15, 1977.
Writ Refused May 5, 1977.

*1091 Rene A. Pastorek, Gretna, for plaintiff-appellant.

Dodd, Barker, Boudreaux, Lamy & Gardner, C. Paul Barker, New Orleans, for defendant-appellee.

Before BOUTALL, SCHOTT and BEER, JJ.

SCHOTT, Judge.

This suit grew out of a building contract between Plumbers and Steamfitters Local 60 Home Association, Inc. (Plumbers) as owner and Hugh O'Connor, Inc. (O'Connor) as general contractor, for the construction of a union hall and training school. The owner's architect was Mathes, Bergman, Favrot and Associates, Inc. (Bergman) and the mechanical subcontractor was J. Robert Autenreith, Inc. (Autenreith).

On April 7, 1969, a standard AIA form of agreement was signed between Plumbers and Bergman for the design of the building and for the usual architectural services in connection with employing a contractor and administering the contract. On September 4, 1970, Bergman issued an invitation for bids on the project which included the following:

"Mechanical work: The General Contractor is not to obtain bids for mechanical work. The Owner will furnish the General Contractor with an estimate for accomplishing the mechanical work which he is to include in his proposal."

On September 11, 1970, Bergman notified all prospective bidders that they were to use Autenreith's bid to perform the mechanical work at a price of $173,856. On September 18 the building contract was signed between Plumbers and O'Connor for a price of $727,300. On October 6 a subcontract was entered into between Autenreith and O'Connor for the mechanical work at Autenreith's price of $173,856.

On September 10, 1971, as the work on the project neared completion Autenreith requested that Bergman release the 10% retainage on his subcontract. Autenreith stated that there was an agreement between it and Plumbers to do the mechanical work at Autenreith's cost with the understanding that a fee would be negotiated *1092 between Plumbers and Autenreith upon completion of the job. Bergman then wrote Plumbers as follows:

"We have a letter from Mr. J. Robert Autenreith in connection with the retainage which is being held on the work accomplished by his firm in the new building. Due to the fact that he is doing this on a cost basis and any fees to be paid to him would be negotiated between you and his firm, we feel that the retainage is certainly not necessary. . . ."

Bergman went on to recommend that the retainage be released as Autenreith requested. On September 24 Bergman notified O'Connor that he might include in his requisition for that month the full amount due Autenreith without regard to the usual retainage. On September 27 Autenreith submitted to O'Connor a request for payment of the $17,385.60 retainage. But on September 29 O'Connor addressed the following letter to Bergman:

"With reference to your letter of September 24, we would be happy to release the retainage held on the contract with J. Robert Autenreith, Inc. except for the fact that we have been notified by letter and by telephone from two of Mr. Autenreith's subcontractors that they have not been paid and holding us responsible for this payment, as is the law.
"However, if you would contact the Owners and have them send us a letter releasing us and our bonding company, Highlands Insurance Company, from any possible liens or claims on this job from Autenreith's subcontractors or material suppliers, we will release this retainage immediately.
"I'm sure you can appreciate the fact that it is necessary to insist on this protection since we are potentially liable to all material suppliers on the job, particularly when they have formally put us on notice of non-payment."

In response to that letter on October 5, Bergman said that there was no reason to have retainage on the Autenreith contract since the contract between Plumbers and Autenreith was for cost. The letter concluded:

"We are perfectly willing to release you and your bonding company from any liens or claims in connection with Autenreith's subcontractors or materials suppliers."

On November 5, 1971, Bergman wrote Plumbers referring to his earlier recommendation that the retainage on Autenreith's contract be released. Bergman stated that he had been at that time aware of two claims by Autenreith's suppliers but he was now aware of many other items due by Autenreith totaling in excess of the amount due Autenreith by O'Connor. The letter concluded as follows:

"In our letter of October 5, to Hugh O'Connor Company in which we stated that joint checks would be made to Autenreith and his material suppliers we stated that we were willing to release O'Connor Company and their bonding company from any liens and claims in connection with the subcontracts or material suppliers. This statement was made in connection with the retainage on the contract only and inasmuch as this retainage has not been released to O'Connor Company we should withdraw the statement entirely. Previously in this letter we stated that the retainage should be withheld for a complete accounting and we also feel that it should be withheld due to the possibility of any misunderstanding concerning the release of O'Connor or their bonding company and any obligations."

Autenreith defaulted and ended up in bankruptcy but the retainage was never paid by O'Connor despite the discussions among the parties. Autenreith's work was completed by O'Connor subject to an agreement between O'Connor and Plumbers under which the parties reserved their rights to determine who would be ultimately responsible for the excess cost of the work originally undertaken by Autenreith. This appeal is from a judgment dismissing O'Connor's suit against Plumbers.

*1093 O'Connor contends that there was a separate contract for the mechanical work between Autenreith and Plumbers and relies on De Lambre v. Williams, 36 La.Ann. 330 (1884) as authority for the proposition that it is not liable for Autenreith's default under the circumstances. O'Connor further contends that Bergman in his letter of October 5, 1971, gave O'Connor a release which was either then binding on Plumbers or subsequently ratified by Plumbers.

At the trial of the case the testimony of Edward J. Bertoneau, President of Plumbers, J. Robert Autenreith and others was admitted over the objection of counsel for Plumbers in an attempt by O'Connor to show that there was a separate contract for the mechanical work. The trial judge did not make a specific factual determination as to whether there was such a contract or not, but he nevertheless distinguished the case from the De Lambre case on its facts. From our review of the record we have concluded that the evidence is insufficient to establish that there was such a separate contract between Autenreith and Plumbers.

The evidence shows that Autenreith and Plumbers had a close relationship for many years prior to Plumbers' decision to construct the Union hall and school. Autenreith testified that in his discussions with Bertoneau he agreed to do the mechanical work at his cost because of the "prestige of doing it" and because he wanted to help the local Union.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guillot v. Blue Cross of Louisiana
690 So. 2d 91 (Louisiana Court of Appeal, 1997)
Pesson v. Kleckley
526 So. 2d 1220 (Louisiana Court of Appeal, 1988)
Cowley Corp. v. Shreveport Packing Co.
440 So. 2d 1345 (Louisiana Court of Appeal, 1983)
Lewis v. Washington Metropolitan Area Transit Authority
463 A.2d 666 (District of Columbia Court of Appeals, 1983)
Hugh O'Connor, Inc. v. J. Robert Autenreith, Inc.
345 So. 2d 59 (Supreme Court of Louisiana, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
343 So. 2d 1090, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-oconnor-inc-v-jr-autenreith-inc-lactapp-1977.