Schultz v. Gund

19 So. 2d 682
Louisiana Court of Appeal·Decided November 6, 1944·No. No. 18133.·Published·Cited by 1 cases

Opinion

This is a suit for damages arising out of a building contract which was made by the plaintiff, Ernest M. Schultz, as owner, with Martin G. Gund as contractor.

The particular complaint of plaintiff is that the contractor installed a defective heating system in his residence at #530 Harrison Avenue in New Orleans and that, as a result, he has been damaged in the sum of $832, which is alleged to be the cost of repairing the system so that it will perform the functions guaranteed by the contractor in the plans and specifications of the building contract. The contractor, Gund, and his surety, the U.S. Fidelity and Guaranty Company, are made parties defendant to the action.

Denying that the heating system installed in plaintiff's residence is defective or that it failed to comply with the guarantee set forth in the specifications of the building contract, the defendants alleged that the system was installed by Holzer Sheet Metal Works, a copartnership, under a subcontract; that the latter be called in warranty and that, if it should be held that plaintiff's complaint is well founded, they have judgment in warranty against the sub-contractor. In addition, the defendant Gund filed a reconventional demand in the sum of $146.71 for furnishing certain extras which were not included in the building contract and for which he had not been paid.

On the allegations contained in defendants' answer, an order was issued by the trial judge calling the sub-contractor, Holzer Sheet Metal Works, in warranty. In due course, the Holzer Company appeared in response to the call in warranty and admitted the subcontract but denied that the heating system installed by it was in any wise defective or that it did not comply with the terms and conditions of its agreement. In addition, it set forth other defenses which we shall hereinafter consider.

On the issues thus formed by the pleadings, a protracted trial was had at which many motions and other pleas were interposed by the defending litigants. After due consideration of these pleas, the evidence and arguments, the trial judge entered a decree in plaintiff's favor against Gund and his surety for damages in the sum of $610 with interest and attorneys' fees and further granted judgment in favor of Gund and his surety against Holzer Sheet Metal Works, defendant in warranty, for a like amount. The reconventional demand of Gund was dismissed. From the adverse judgment, defendants and Holzer Sheet Metal Works have appealed.

As heretofore stated, numerous points and contentions have been made by appellant, Holzer Sheet Metal Works, in which it advances some six grounds for a reversal of the decree below. The complaints of the other appellants, Gund and his surety, are of a similar nature. We do not find it necessary to state or discuss all of these contentions inasmuch as a perusal of the record has been sufficient to disclose that there is no merit in most of them. We shall, therefore, confine our discussion to the three main points set forth by appellant, Holzer Sheet Metal Works, in its brief, viz.:

(1) That its commitment as sub-contractor was based upon its accepted bid, the terms and conditions of which contain no guarantee whatsoever.

(2) That, subsequent to the acceptance of its bid, the plaintiff, without its knowledge and consent, changed the specifications of the main contract, which called for a *Page 684 brick veneer outer surface of the house, to a stucco surface and that this change relieved it from any obligation to comply with the guarantee contained in the specifications, respecting the heating system, and

(3) That, if liability exists on its part, the quantum of damages is excessive.

Examination of the record discloses the following facts which are not open to serious dispute: During the latter part of 1940, plaintiff, being desirous of building a home, employed an architect, Mr. Edward F. Sporl, Sr., to prepare plans and specifications and let out a contract for the work. Mr. Sporl accepted this employment, undertook to draw the necessary plans and specifications and to receive bids in order to ascertain the cost of the residence. On October 1, 1940, he received a bid from Holzer Sheet Metal Works in which it quoted the price of $441 for the installation of a warm air heating system, supplying a heater manufactured by the American Furnace Company. This bid was not accepted until some time after February 5, 1941, when plaintiff entered into a building contract with the defendant, Gund, wherein the latter agreed to construct a residence for plaintiff for the sum of $9380. The specifications attached to and made part of this building contract provided for the installation of a re-circulating warm air control heating system and the furnishing of one No. 220-A Lo-Boy "Quaker" oil burning furnace, or equal. It was further provided in said specifications that "The above system is to be guaranteed to keep the building at 70° F. dry bulb temperature when the outside temperature is 30° F. dry bulb temperature".

Free access — add to your briefcase to read the full text and ask questions with AI

Schultz v. Gund, 19 So. 2d 682 (La. Ct. App. 1944).

19 So. 2d 682 (Schultz v. Gund) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

H. O'CONNOR, INC. v. JR Autenreith, Inc.
343 So. 2d 1090 (Louisiana Court of Appeal, 1977)