Schultz v. Gund

19 So. 2d 682
CourtLouisiana Court of Appeal
DecidedNovember 6, 1944
DocketNo. 18133.
StatusPublished
Cited by1 cases

This text of 19 So. 2d 682 (Schultz v. Gund) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schultz v. Gund, 19 So. 2d 682 (La. Ct. App. 1944).

Opinion

This is a suit for damages arising out of a building contract which was made by the plaintiff, Ernest M. Schultz, as owner, with Martin G. Gund as contractor.

The particular complaint of plaintiff is that the contractor installed a defective heating system in his residence at #530 Harrison Avenue in New Orleans and that, as a result, he has been damaged in the sum of $832, which is alleged to be the cost of repairing the system so that it will perform the functions guaranteed by the contractor in the plans and specifications of the building contract. The contractor, Gund, and his surety, the U.S. Fidelity and Guaranty Company, are made parties defendant to the action.

Denying that the heating system installed in plaintiff's residence is defective or that it failed to comply with the guarantee set forth in the specifications of the building contract, the defendants alleged that the system was installed by Holzer Sheet Metal Works, a copartnership, under a subcontract; that the latter be called in warranty and that, if it should be held that plaintiff's complaint is well founded, they have judgment in warranty against the sub-contractor. In addition, the defendant Gund filed a reconventional demand in the sum of $146.71 for furnishing certain extras which were not included in the building contract and for which he had not been paid.

On the allegations contained in defendants' answer, an order was issued by the trial judge calling the sub-contractor, Holzer Sheet Metal Works, in warranty. In due course, the Holzer Company appeared in response to the call in warranty and admitted the subcontract but denied that the heating system installed by it was in any wise defective or that it did not comply with the terms and conditions of its agreement. In addition, it set forth other defenses which we shall hereinafter consider.

On the issues thus formed by the pleadings, a protracted trial was had at which many motions and other pleas were interposed by the defending litigants. After due consideration of these pleas, the evidence and arguments, the trial judge entered a decree in plaintiff's favor against Gund and his surety for damages in the sum of $610 with interest and attorneys' fees and further granted judgment in favor of Gund and his surety against Holzer Sheet Metal Works, defendant in warranty, for a like amount. The reconventional demand of Gund was dismissed. From the adverse judgment, defendants and Holzer Sheet Metal Works have appealed.

As heretofore stated, numerous points and contentions have been made by appellant, Holzer Sheet Metal Works, in which it advances some six grounds for a reversal of the decree below. The complaints of the other appellants, Gund and his surety, are of a similar nature. We do not find it necessary to state or discuss all of these contentions inasmuch as a perusal of the record has been sufficient to disclose that there is no merit in most of them. We shall, therefore, confine our discussion to the three main points set forth by appellant, Holzer Sheet Metal Works, in its brief, viz.:

(1) That its commitment as sub-contractor was based upon its accepted bid, the terms and conditions of which contain no guarantee whatsoever.

(2) That, subsequent to the acceptance of its bid, the plaintiff, without its knowledge and consent, changed the specifications of the main contract, which called for a *Page 684 brick veneer outer surface of the house, to a stucco surface and that this change relieved it from any obligation to comply with the guarantee contained in the specifications, respecting the heating system, and

(3) That, if liability exists on its part, the quantum of damages is excessive.

Examination of the record discloses the following facts which are not open to serious dispute: During the latter part of 1940, plaintiff, being desirous of building a home, employed an architect, Mr. Edward F. Sporl, Sr., to prepare plans and specifications and let out a contract for the work. Mr. Sporl accepted this employment, undertook to draw the necessary plans and specifications and to receive bids in order to ascertain the cost of the residence. On October 1, 1940, he received a bid from Holzer Sheet Metal Works in which it quoted the price of $441 for the installation of a warm air heating system, supplying a heater manufactured by the American Furnace Company. This bid was not accepted until some time after February 5, 1941, when plaintiff entered into a building contract with the defendant, Gund, wherein the latter agreed to construct a residence for plaintiff for the sum of $9380. The specifications attached to and made part of this building contract provided for the installation of a re-circulating warm air control heating system and the furnishing of one No. 220-A Lo-Boy "Quaker" oil burning furnace, or equal. It was further provided in said specifications that "The above system is to be guaranteed to keep the building at 70° F. dry bulb temperature when the outside temperature is 30° F. dry bulb temperature".

Upon the acceptance of its bid, Holzer Sheet Metal Works undertook to install the heating system set forth in its offer. The record is indefinite as to the date in 1941 when the heating system was installed but the vast preponderance of testimony shows that the heating work was performed at a time when the building was practically completed. After the completion of the residence, performance under the contract was accepted by plaintiff and the defendant, Gund, received final payment of the balance due him on October 29, 1941. Shortly after plaintiff took occupancy of the house, it was discovered that the heating system did not bring the temperature up to the guarantee set forth in the specifications. Thereafter, he made numerous complaints to Holzer Sheet Metal Works that the house was inadequately heated during the cold weather; that it took from five to six hours for the upstairs portion of the premises to become comfortably warm and that the living room temperature did not at any time reach the required 70° as stipulated for in the guarantee. Holzer Sheet Metal Works responded to these complaints and, on at least two or three occasions during the winter of 1942, sent mechanics to plaintiff's home to make necessary corrections in the heating system. None of the attempted repairs and changes made by the sub-contractor was successful and, in July of 1942, Mr. R.J. Holzer, as President of sub-contractor company, wrote a letter to plaintiff in which he stated that, having been notified by plaintiff of the defects in the heating system and that plaintiff proposed to file a claim against the contractor and his surety because of these defects, the Holzer Company, as sub-contractor, recognized its obligation in the premises and that it agreed to put the heating system in working order by October 15, 1942. The letter further states that the Holzer Company "agree to balance the heating system, and guarantee to you that it will keep the rooms to be heated at the temperature guaranteed in the original contract, viz. to keep these rooms at 70° F. dry bulb temperature when the outside temperature is 30° F. dry bulb temperature." In conformity with its promise as set forth in this letter, the Holzer Company made further changes and repairs to the heating system. However, none of this additional work remedied the defective condition. Under these circumstances, plaintiff, feeling that he could not obtain satisfaction for his damages without the aid of the courts (and justifiably so), filed the present action. It further appears that, even after the suit was filed, plaintiff, in an effort to give the defendants every opportunity to rectify the defective heating system, made an agreement with them to withhold action in the case and give the Holzer Company another chance to comply with the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H. O'CONNOR, INC. v. JR Autenreith, Inc.
343 So. 2d 1090 (Louisiana Court of Appeal, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
19 So. 2d 682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schultz-v-gund-lactapp-1944.