Guy F. Atkinson Co. v. Commissioner

82 T.C. No. 24, 82 T.C. 275, 1984 U.S. Tax Ct. LEXIS 105
CourtUnited States Tax Court
DecidedFebruary 16, 1984
DocketDocket No. 8750-81
StatusPublished
Cited by10 cases

This text of 82 T.C. No. 24 (Guy F. Atkinson Co. v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guy F. Atkinson Co. v. Commissioner, 82 T.C. No. 24, 82 T.C. 275, 1984 U.S. Tax Ct. LEXIS 105 (tax 1984).

Opinion

Sterret, Judge:

By notice of deficiency dated March 5,1981, respondent determined deficiencies in petitioners’ Federal income taxes as follows:

TYE Dec. 31— Deficiency
1972.$758,074
1973. 15,368
1974 . 5,290
1975.3,414,988
4,193,720

After concessions, the issues for decision are whether the proper year for reporting losses from the construction of a water tunnel where the contractor elected the completed contract method of accounting was 1975 or an earlier year and, if so, whether certain losses were allowable in the year of completion. The other issue for decision is whether one of the petitioners was a Western Hemisphere Trade Corporation in 1975.

Some of the facts have been stipulated and are so found. The stipulation of facts, together with the exhibits attached thereto, is incorporated herein by this reference..

The petitioners are the Guy F. Atkinson Co. of California (hereinafter GFA Co.), a California corporation, and subsidiary corporations which joined in the filing of consolidated returns for the calendar years 1972 through 1975. GFA Co.’s principal place of business was in South San Francisco, Calif., at the time the petition was filed. GFA Co. and its subsidiaries filed consolidated U.S. Corporation Income Tax Returns (Forms 1120) for the calendar years 1972 through 1975 with the Internal Revenue Service Center, Fresno, Calif.

I. Losses From the Water Tunnel Project

FINDINGS OF FACT

During the years at issue, the Guy F. Atkinson Co. (hereinafter Atkinson), a Nevada corporation, one of GFA Co.’s wholly owned subsidiaries, owned the Walsh Construction Co. (hereinafter Walsh), as a subsidiary. On December 31, 1970, Walsh merged into Atkinson, becoming a division of Atkinson for the remaining years at issue.

Walsh was the sponsoring and managing partner of the Water Tunnel Contractors (hereinafter WTC), a joint venture organized to construct a water tunnel (hereinafter the tunnel project) for the New York City (hereinafter city) water supply system. Walsh’s interest in the profits, losses, and capital of WTC as of December 18, 1969, was 30 percent.

WTC filed U.S. Partnership Income Tax Returns for the calendar years 1970 through 1975 with the Director, Internal Revenue Service Center, Holtsville, N.Y., and the Director, Internal Revenue Service Center, Fresno, Calif.

During the years at issue, the Board of Water Supply of the City of New York (hereinafter the board) was a city agency responsible for developing the city’s sources of water. The final authority respecting the use, development, and improvement of city land rested with the Board of Estimate (hereinafter BOE). Before the city could undertake capital projects, the BOE had to approve the standards, scope, and final designs of such projects.

On January 15, 1970, the board awarded three contracts (520, 521, 522) to WTC as low bidder for the construction of the first stage of a water tunnel. WTC treated these contracts and the formal change orders thereto as parts of a single contract for financial accounting and tax reporting purposes.

These contracts required the excavation and construction of about 13.7 miles of concrete-lined pressure tunnel, 25 access shafts, 3 large underground caverns (valve chambers), and related work. The contracts contained lump-sum items and unit price items. The lump-sum items included those items such as the construction of certain shafts for which WTC bid a fixed amount. The unit price items were those for which WTC bid a certain price per unit of material installed or work performed such as per pound of structural steel installed. WTC’s bid was thus a summation of prices for many items. For the three contracts, the bid totaled $228,605,810, less a discount of 2.63 percent if WTC received all three contracts, or $222,593,477.20.

Before receiving bids, the board issued documents to prospective bidders which contained estimates of the quantities of unit price items which the tunnel required. The documents indicated, however, that the bidders bore the obligation of substantiating these estimates and of bidding accordingly. Furthermore, the documents warned that the city would not pay an amount in addition to the total bid in the event the board underestimated the quantity of any item. The final contract incorporated the estimates of and amounts bid for each item. Under the terms of the contract, structural steel support was a separate unit price item, and the board estimated that the tunnel would require a total of 700,000 pounds of steel.

On February 6, 1970, the board gave WTC notice to start constructing the tunnel, and WTC began working on the tunnel that month. WTC immediately experienced significant delays and incurred expenses in excess of payments provided for in the contract.

The parties disputed the questions of whether WTC or the city was responsible for these delays and whether the city should bear the additional expense that WTC incurred in constructing the tunnel. Eventually, WTC installed structural steel in an amount far in excess of the estimate of 700,000 pounds, and incurred costs far in excess of the amount the city was willing to pay. In point of fact, by December 6,1974, WTC had installed 18,543,182 pounds of structural steel, and of this amount, the board refused to approve or pay for 3,408,572 pounds.

WTC informed the board that its projected costs in building the tunnel exceeded its projected revenues under the contract, and WTC and the board entered two agreements modifying the contract on November 8,1973, and July 22, 1974. Under these agreements, the board agreed to release a total of $7,200,000 of the retained percentages, which were amounts that the city had withheld from the progress payments as per the contract in order to assure WTC’s performance, and to advance an additional $3 million to WTC. In addition, WTC conveyed title to and liens in its construction plant, equipment, and facilities which were located or used at the tunnel construction sites to the city as security for the performance of the contract.

On November 9, 1974, the board and WTC agreed to a proposed supplemental agreement concerning the tunnel project, which the BOE never approved. Since the BOE did pot approve the supplemental agreement at its December 5,1974, meeting, WTC suspended all tunneling, excavation, and support operations, but continued to provide pumping and guard services at the construction sites. As a result of an interim agreement dated March 10,1975, between WTC and the board, WTC agreed to resume work on the tunnel for 4 months. The interim agreement provided the scope of the work WTC would complete in this period, and the city agreed, inter alia, to pay WTC the costs incurred for work performed during this period. The agreement preserved the existing rights of both WTC and the city. WTC agreed to suspend prosecution of its legal action until 20 days after the expiration of the interim agreement, and the board agreed not to declare WTC in default during the terms of the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re DeGour
478 B.R. 1 (C.D. California, 2012)
Perry v. Comm'r
2012 T.C. Memo. 237 (U.S. Tax Court, 2012)
In Re Sweitzer
332 B.R. 614 (C.D. California, 2005)
Hamilton Industries, Inc. v. Commissioner
97 T.C. No. 9 (U.S. Tax Court, 1991)
Schouten v. Commissioner
1991 T.C. Memo. 155 (U.S. Tax Court, 1991)
Matter of Faber
78 B.R. 934 (S.D. Iowa, 1987)
Ledvina v. Commissioner
1984 T.C. Memo. 462 (U.S. Tax Court, 1984)
Guy F. Atkinson Co. v. Commissioner
82 T.C. No. 24 (U.S. Tax Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
82 T.C. No. 24, 82 T.C. 275, 1984 U.S. Tax Ct. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guy-f-atkinson-co-v-commissioner-tax-1984.