EHRET-DAY CO. v. COMMISSIONER

2 T.C. 25, 1943 U.S. Tax Ct. LEXIS 148
CourtUnited States Tax Court
DecidedJune 8, 1943
DocketDocket No. 109528
StatusPublished
Cited by7 cases

This text of 2 T.C. 25 (EHRET-DAY CO. v. COMMISSIONER) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EHRET-DAY CO. v. COMMISSIONER, 2 T.C. 25, 1943 U.S. Tax Ct. LEXIS 148 (tax 1943).

Opinion

OPINION.

Tyson, Judge:

The first question presented is whether the income from the two construction contracts described in the findings of fact should be taxed as part of the petitioner’s income for the year 1938. Article 42-4 of Regulations 101, promulgated under the Revenue Act of 1938, permits the reporting of income from long term contracts “for the taxable year in which the contract is finally completed and accepted if the taxpayer elects as a consistent practice so to treat such income, provided such method clearly reflects the net income.” The provisions of that article, which have been in force without change since the enactment of the Revenue Act of 1921, are set forth in the margin.1 The respondent determined that the contracts were “completed and accepted” in 1938, and he included the profit in the petitioner’s income for that year. The amount of the profit realized from each contract has been stipulated; and, although the North End Hotel contract covered a period of about three months, the respondent does not question the petitioner’s right to report the income from that contract under the provisions of the regulations. See L. A. Wells Construction Co., 46 B. T. A. 302.

The petitioner opposes the inclusion of the income from the contracts in its income for 1938 on the grounds that the contract for the store and office building (hereinafter referred to as the Fredericks contract) was neither completed nor accepted until 1939, and that the North End Hotel contract was not accepted until 1939, its theory being that, under the cited regulations, the inclusion of the profit in income is conditioned upon both completion and acceptance and that where completion occurs in one year and acceptance occurs in a later year, the reporting of the income must be deferred to the year of acceptance.

On the question of the time of the completion of the Fredericks contract there is dispute and we shall first consider this question, since if, as the petitioner contends, that contract was not completed within the meaning of the regulations until 1939, that fact alone is sufficient to preclude the inclusion of the profit therefrom in petitioner’s income for 1938. National Contracting Co., 25 B. T. A. 407; affd., 69 Fed. (2d) 252, and C. F. Martin, 34 B. T. A. 111. With respect to the Fredericks contract the evidence shows that the building had been completed prior to the close of 1938, but that because of certain minor defects in the workmanship, payment of the balance of $846.44 of the total contract price for construction was withheld for the purpose of adjustment with regard to such defects. Fredericks, the only witness called to testify concerning the condition of the building, stated that the matter of the defects was “ironed out” to his satisfaction in January or February of 1939. There is no evidence whatever of the amount of labor or material, if any, used in correcting the defects or of the cost thereof; nor is there any evidence as to how the matter of the defects was “ironed out.”

The regulations provide for the reporting of the gross income in the taxable year in which the contract is “finally completed.” The word “completed,” according to its definition in' Webster’s New International Dictionary, has the following meanings:

Filled up; with no part, item, or element lacking; free from deficiency; entire; perfect; consummate.
Brought to an end or to a final or intended condition; concluded; completed; as, the edifice is complete.
To bring to a state of entirety or perfection; to fulfill; finish; as to complete a task.

As these meanings embrace the element of finality, the use in the regulations of the word “finally” immediately preceding the word “completed” is redundant in that such use does not enlarge the meaning of that' word, unless it is üsed for the purpose of distinguishing the cases falling within paragraph (b) of the regulations from those cases involving contracts which are partially completed and are covered by the preceding paragraph (a). This being so, we can eliminate consideration of the word “finally” as applied to the facts of this case. In so far as the term “completed” applies to contracts for the construction of buildings, we do not think the regulations were intended to require a completion within the ordinary meaning of the word as defined above any more than it was so intended by the courts in establishing the rule hereinafter quoted. With regard to building contracts, the courts have modified the rule requiring an absolute completion and strict performance of a contract before the right to payment thereon can be enforced. The rule is thus stated in 17 C. J. S., § 509, pp. 1087-1089:

The hardship of the rule requiring strict performance in order to permit recovery on a contract generally, when applied to a contractor who has unde-signedly violated his contract, and the inequitable advantage that it gives to an owner who receives and retains the benefit of the builder’s labor and materials have led to its qualification; and it is generally held that, where the compensation is due only on the performance of the contract, a literal and strict performance is not required, and if the builder, acting in good faith and intending and attempting to perform his contract, does so, he may recover the contract price, notwithstanding slight and trivial defects or deviations in performance, for which compensation may be made, in all its material and substantial particulars, by an allowance to the owner; but the owner is entitled to an allowance for the damages he may suffer by reason of the failure to perform strictly, such as the cost or expense of putting the structure or work in the condition called for by the contract; * * *

The rule is recognized in New Jersey where the contract in question was made and performed. Bozarth v. Dudley, 44 N. J. L. 304; Feeney v. Bardsley, 66 N. J. L. 239; 49 Atl. 443; White Door Bed Co. v. United States Mortgage & Title Guaranty Co. of New Jersey, 146 Atl. 216 (N. J.); Globe Home Improvement Co. v. Michnisky, 120 N. J. L. 233; 199 Atl. 393. In the Feeney case the court approved an instruction given the jury by the lower court which was as follows: “If the contractor has substantially performed his contract, even though he has failed to do so in some minor particulars, he is entitled to recover the contract price, less what will be a fair allowance to the owner to make good the defects in the performance of the contract.”

The facts in the present case clearly show that during the year 1938 the petitioner was, under the above rule of law, entitled to recover the unpaid portion of the contract price of the Fredericks building, subject to such allowance or set-off as might be shown to be proper for the repair of the minor defects complained of. There is nothing in the record showing, or tending to show, that the defects involved were occasioned by lack of good faith or lack of intention or attempt to perform its contract by petitioner so as to preclude application of the quoted rule. In our opinion, the regulations do not contemplate that a building contract which has been completed in all important particulars, except for minor defects, as was the Fredericks contract, shall be regarded as being uncompleted until such time as the minor defects may actually be corrected or adjustment made therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ball, Ball & Brosamer, Inc. v. Commissioner
964 F.2d 890 (Ninth Circuit, 1992)
Ball v. Commissioner Internal Revenue Service
964 F.2d 890 (Ninth Circuit, 1992)
Guy F. Atkinson Co. v. Commissioner
82 T.C. No. 24 (U.S. Tax Court, 1984)
F. D. Rich Co. v. Commissioner
1977 T.C. Memo. 125 (U.S. Tax Court, 1977)
EHRET-DAY CO. v. COMMISSIONER
2 T.C. 25 (U.S. Tax Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
2 T.C. 25, 1943 U.S. Tax Ct. LEXIS 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ehret-day-co-v-commissioner-tax-1943.