Gunnell v. Arizona Public Service Co.

18 P.3d 176, 199 Ariz. 382, 342 Ariz. Adv. Rep. 43, 2001 Ariz. App. LEXIS 49
CourtCourt of Appeals of Arizona
DecidedMarch 8, 2001
Docket1 CA-CV 99-0510
StatusPublished
Cited by2 cases

This text of 18 P.3d 176 (Gunnell v. Arizona Public Service Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gunnell v. Arizona Public Service Co., 18 P.3d 176, 199 Ariz. 382, 342 Ariz. Adv. Rep. 43, 2001 Ariz. App. LEXIS 49 (Ark. Ct. App. 2001).

Opinions

OPINION

GARBARINO, Judge.

¶ 1 Stanley and Jennifer Gunnell appeal the trial court’s grant of summary judgment in favor of Arizona Public Service Company (APS). The trial court ruled that, pursuant to the Underground Facilities Act, Ariz.Rev. Stat. Ann. (A.R.S.) §§ 40-360.21 to 40-360.32 (1996 & Supp.1999), the Gunnells are liable for damage to APS’s underground facility, APS is entitled to indemnity for damages it must pay to James Knox, and the Gunnells must pay APS’s attorneys’ fees incurred as a result of APS’s defense of this action. For the following reasons, we affirm the trial court’s judgment.

FACTS AND PROCEDURAL HISTORY

¶ 2 On an appeal from an order granting summary judgment, we view the facts in a light most favorable to the appellant. Pioneer Annuity Life Ins. Co. v. Rich, 179 Ariz. 462, 464, 880 P.2d 682, 684 (App.1994).

¶ 3 The Gunnells own an excavating business in Cottonwood, Arizona, known as Gunnell Construction. Mr. Gunnell has worked in the excavation trade for more than twenty years. In July 1995, the Gunnells contracted to do the excavation work for the installation of a sewer line crossing Mingus Avenue in Cottonwood. Before beginning the excavation work, Mr. Gunnell met with the Cottonwood City Engineer to determine the location of utility easements. He also called the local Blue Stake Center to notify local utilities that he would be excavating in the area so that they could physically mark the location of their underground facilities. APS did not promptly mark its facilities in the area, and Mr. Gunnell called the Blue Stake Center three additional times specifically to request that APS come to the site and properly mark its facilities.

¶ 4 After APS’s last visit to the site, Mr. Gunnell believed that APS’s blue staking was complete and he began excavating the site. While excavating the site, Mr. Gunnell encountered an unmarked, unidentified galvanized steel pipe in the path of his trench. Because Mr. Gunnell had never before encountered an electric line encased by steel piping, he believed the pipe to be a water line. He therefore contacted both local water companies in the Cottonwood area. Both water companies denied ownership of the line. Based on this information and his years of experience with abandoned lines in the Cottonwood area, Mr. Gunnell concluded that the lines were abandoned, and he proceeded with the excavation. Mr. Gunnell’s co-worker, Jim Knox, cut into the pipe and an explosion occurred, seriously and permanently injuring both Mr. Gunnell and Mr. Knox.

¶ 5 Mr. Gunnell informed APS that he had cut into an unmarked, unidentified electric line. APS responded that if the line was encased in a steel pipe, it could not possibly have belonged to APS. APS later admitted that the electric line was theirs and that the employee in charge of blue staking had “just missed it.”

¶ 6 The Gunnells sued APS, alleging that APS negligently installed the electric line, failed to warn of the line’s location, and inadequately blue-staked the area, causing injuries to Mr. Gunnell. Mr. Knox also sued APS in a separate lawsuit. APS filed an answer denying liability, and APS later amended its answer to assert a counterclaim alleging that the Gunnells were liable for damage to the APS electric line and that the Gunnells were required to indemnify APS for [384]*384all expenses and damages incurred in defense of the lawsuit filed by Mr. Knox. APS also sought an award of costs and attorneys’ fees.

¶ 7 APS moved for summary judgment on all counts of the complaint and counterclaim. The trial court held a hearing in April 1999, and in a signed minute entry dated May 28, 1999, the court ruled as follows:

When ... Gunnell came across the unmarked, unidentified steel pipe, he was required to notify either the owner of the underground facility or an organization designated by the owner. This, [he] failed to do. He contacted two water companies who disclaimed any ownership. However, he failed to re-contact the Blue Stake Center and also failed to contact APS. It is Plaintiffs failure to contact the Blue Stake Center after he encountered the unmarked, unidentified pipe which necessitates this result, and the failure of APS to have originally identified the pipe is not relevant under A.R.S. § 40-360.23B.

After considering APS’s request for costs and attorneys’ fees and the Gunnells’ objection to the form of judgment presented by APS, the trial court entered a formal order granting judgment in favor of APS and awarding APS its costs and attorneys’ fees. The Gunnells filed a timely notice of appeal.

ISSUES
1. Did Mr. Gunnell violate the Underground Facilities Act?
2. Does the Underground Facilities Act allow application of comparative negligence principles?

DISCUSSION

¶ 8 In reviewing an order granting summary judgment, “we determine de novo whether there are any genuine issues of material fact and whether the trial court erred in its application of the law.” Gonzalez v. Satrustegui, 178 Ariz. 92, 97, 870 P.2d 1188, 1193 (App.1993). We also review de novo the trial court’s construction of statutes. Schabel v. Deer Valley Unified Sch. Dist. No. 97, 186 Ariz. 161, 163, 920 P.2d 41, 43 (App.1996).

¶ 9 Arizona Revised Statutes Annotated section 40-360.22 (Supp.1999) provides in relevant part as follows:

A. A person shall not make or begin any excavation in any public street, alley, right-of-way dedicated to the public use or utility easement ... without first determining whether underground facilities will be encountered, and if so where they are located from each and every public utility, municipal corporation or other person having the right to bury such underground facilities....
B.....Upon receipt of inquiry or notice from the excavator, the owner of the facility shall respond as promptly as practical, but in no event later than two working days, by marking such facility with stakes, paint or in some customary manner. No person shall begin excavating before the location and marking are complete or the excavator is notified that marking is unnecessary.
I. The owner of an underground facility shall notify the excavator whether the facility is active or abandoned. For an underground facility abandoned after December 31, 1988 ... the owner of the facility may not advise ... the excavator that a facility or portion of a facility is abandoned unless the owner has verified ... that the facility or portion is actually abandoned and not merely inactive. For all other abandoned or apparently abandoned underground facilities, each one-call notification center shall establish a method of providing personnel from a facility owner qualified to safely inspect and verify that the facility is abandoned or active and a method for reimbursing the verifying facility owner for the costs incurred.... For all purposes under this article, a[n]
... excavator or other person subject to this article may not ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gunnell v. Arizona Public Service Co.
46 P.3d 399 (Arizona Supreme Court, 2002)
Gunnell v. Arizona Public Service Co.
18 P.3d 176 (Court of Appeals of Arizona, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
18 P.3d 176, 199 Ariz. 382, 342 Ariz. Adv. Rep. 43, 2001 Ariz. App. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gunnell-v-arizona-public-service-co-arizctapp-2001.