Guardsman Elevator Co. v. United States

50 Fed. Cl. 577, 2001 U.S. Claims LEXIS 197, 2001 WL 1301402
CourtUnited States Court of Federal Claims
DecidedOctober 22, 2001
DocketNo. 00-716C
StatusPublished
Cited by7 cases

This text of 50 Fed. Cl. 577 (Guardsman Elevator Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guardsman Elevator Co. v. United States, 50 Fed. Cl. 577, 2001 U.S. Claims LEXIS 197, 2001 WL 1301402 (uscfc 2001).

Opinion

ORDER

MILLER, Judge.

This case is before the court on defendant’s motion to dismiss or, in the alternative, for summary judgment. A contractor, allegedly owed compensation for services rendered to a housing project, is pursuing a claim for breach of contract against the United States. The predicate contract arose when a court-appointed receiver was directed to evaluate and pay pre-receivership accounts payable at its discretion. Subse[579]*579quently, the United States Department of Housing and Urban Development (“HUD”) assumed control of the project and appointed the receiver to manage the project, entering into a stipulation with the other parties that incorporated the receiver’s preexisting responsibilities. Argument is deemed unnecessary.

FACTS

The following facts are not disputed. Guardsman Elevator Co., Inc. (“plaintiff”), has serviced elevators at a housing project owned by the Medgar Evers Houses Associates (“Medgar Evers”) located in Brooklyn, New York since 1988. The project received federal housing assistance program subsidies pursuant to both a regulatory agreement and housing assistance payments agreements to which Medgar Evers and HUD were parties. HUD also held a first mortgage on the project. Plaintiff performed these services pursuant to a contract with BPC Management Corporation, an agent for Medgar Evers.

In 1997 the project’s tenants sued Medgar Evers, HUD and others associated with the project under the Racketeer Influenced and Corrupt Organizations Act (“RICO”), 18 U.S.C. §§ 1961-68 (1994), alleging improper removal of project funds and under New York state law alleging failure to properly maintain the project. Pursuant to the parties’ stipulation, the United States District Court for the Eastern District of New York placed the project under receivership on June 17, 1997, and appointed Jeffery Gold-stein, President, ARCO Management Corporation (“ARCO”)1 the receiver pendente lite (the “Receivership Order”). The RICO case was later dismissed. Medgar Evers Houses Tenants Ass’n v. Medgar Evers Houses Assoc., L.P., 25 F.Supp.2d 116, 124 (E.D.N.Y.1998), aff'd sub nom Abbott v. Medgar Evers Houses Assoc. L.P., 201 F.3d 430 (2d Cir.1999) (unpublished table decision), cert. denied, 529 U.S. 1130, 120 S.Ct. 2005, 146 L.Ed.2d 956 (2000).2

The Receivership Order authorized ARCO to order materials, labor, and services necessary to remedy the uninhabitable conditions enumerated in the complaint. It directed ARCO to give first priority for payment to remedial and maintenance work.3

As to existing accounts, paragraph 15 of the Receivership Order directed:

The Receiver shall evaluate all current accounts payable, and shall determine in his discretion, and subject to the discharge of his responsibilities under this order, whether and in what order any such outstanding claims shall be paid.

Per Paragraph 4(a), ARCO was to pay these obligations from project revenues:

The source of revenues for all expenditures authorized by this receivership shall be limited to project revenues and the reserve for replacement fund. Project revenues include tenant rents, the HUD Section 8 payment, and any income produced by the operations of the project. HUD’s consent to the appointment of a receiver does not operate in any way as a release from the constraints placed upon the use of the general insurance fund as proscribed by Congress in 207(k) of the National Housing Act. Accordingly, the receiver shall not request from HUD the release of any moneys other than project funds.

(Emphasis added.)

Plaintiff subsequently forwarded to ARCO 103 unpaid invoices totaling $79,704.79. At the same time, ARCO authorized and approved plaintiffs continued rendering of services. On August 7, 1997, the court entered a Stipulation and Order (the “HUD Stipulation”) dissolving the receivership and transferring possession of the project to HUD. [580]*580ARCO remained as HUD’s managing agent, and ARCO’s duties and responsibilities remained unchanged from its duties as receiver, subject now to modification by HUD. The HUD Stipulation expressly incorporated the terms of the Receivership Order.4 The court also directed ARCO to determine which accounts payable it would pay and which accounts payable it would not pay, subject to subsequent investigation and verification, and to report its findings to HUD and the property owner.

On September 8, 1997, ARCO issued a report of “Pre-Receivership Payables for Medgar Evers.” It identifies plaintiff with the figure $58,362.31 and the notation “Elevator contractor — Evidence of all this work was completed.” In a December 4, 1997 report, ARCO informed the court that, because project revenues were inadequate to pay invoices identified as actual during a certified financial audit, it “assume[d] the partners will have to sit down with HUD to determine how to best deal with this shortfall.” Plaintiff alleges — an allegation that defendant does not challenge on this motion— that although other contractors not identified as pre-receivership payables were paid, plaintiff was not. See Compl. filed Nov. 27, 2000,1114.

Plaintiff now sues the United States for breach of contract and for recovery in quantum meruit, alleging that as a third-party beneficiary of the HUD Stipulation, ARCO’s failure to remit payment on the invoices is attributable to HUD. Defendant moves under RCFC 12(b)(1) to dismiss the claims for lack of jurisdiction under RCFC 12(b)(4) to dismiss plaintiff’s breach claim for failure to state a claim upon which relief can be granted or under RCFC 56 for a grant of summary judgment.

DISCUSSION

1. Subject matter jurisdiction

It is well-settled doctrine that a complaint will not be dismissed for lack of subject matter jurisdiction “unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 40 L.Ed.2d 90 (1974) (quoting Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)). Therefore, when the facts, as alleged in the complaint, reveal “any possible basis on which the non-movant might prevail, the motion must be denied.” W.R. Cooper Gen. Contractor, Inc. v. United States, 843 F.2d 1362, 1364 (Fed.Cir.1988) (citing Scheuer, 416 U.S. at 236, 94 S.Ct. 1683).

The Tucker Act, 28 U.S.C. § 1491(a)(1) (1994 & Supp. V 1999), confers the Court of Federal Claims with jurisdiction over any claim against the United States founded upon an express or implied contract. The court’s Tucker Act jurisdiction thus extends only to plaintiffs in privity of contract with the Government. Erickson Air Crane Co. v. United States, 731 F.2d 810

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Global Freight Systems Co. W.L.L. v. United States
130 Fed. Cl. 780 (Federal Claims, 2017)
Kawa v. United States
86 Fed. Cl. 575 (Federal Claims, 2009)
Klamath Irrigation District v. United States
67 Fed. Cl. 504 (Federal Claims, 2005)
JGB Enterprises, Inc. v. United States
63 Fed. Cl. 319 (Federal Claims, 2004)
Emerald International Corp. v. United States
54 Fed. Cl. 674 (Federal Claims, 2002)
Hunt v. United States
52 Fed. Cl. 810 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
50 Fed. Cl. 577, 2001 U.S. Claims LEXIS 197, 2001 WL 1301402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guardsman-elevator-co-v-united-states-uscfc-2001.