Grynberg v. Bar S Services, Inc.

527 F. App'x 736
CourtCourt of Appeals for the Tenth Circuit
DecidedJune 11, 2013
Docket12-8055, 12-8056
StatusUnpublished
Cited by15 cases

This text of 527 F. App'x 736 (Grynberg v. Bar S Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grynberg v. Bar S Services, Inc., 527 F. App'x 736 (10th Cir. 2013).

Opinion

ORDER AND JUDGMENT *

PAUL KELLY, JR., Circuit Judge.

Jack J. Grynberg appeals from a jury verdict entered in favor of Bar S Services, Inc. The jury determined that Mr. Gryn-berg had breached two separate contracts with Bar S related to the transportation of an oil and gas drilling rig and awarded Bar S damages on both of the contracts. Bar S cross-appeals from the district court’s denial of pre-judgment interest on a portion of its damages award. Exercising jurisdiction pursuant to 28 U.S.C. § 1291, we affirm.

I. Factual and Procedural Background

On November 23, 2010, Mr. Grynberg contracted with Bar S to move a drilling rig from a site in Wyoming to a site in *738 North Dakota. As part of the terms of the contract, Mr. Grynberg pre-paid $242,000 directly to Bar S, and put the remaining $242,000 into an escrow account.

After the parties entered into the contract, Bar S learned that the North Dakota site was not ready for the rig to be set up there. Bar S also learned that the rig needed to be moved from the Pinedale, Wyoming site before the North Dakota site would be ready. As a result, Bar S was unable to complete the move as contemplated in the original contract at that time. Because Mr. Grynberg needed to have the rig moved off of its current location by a certain deadline, Bar S agreed to move the rig from the Pinedale site to a site in Farson, Wyoming, where Bar S stacked out the rig for storage.

In 2011, Mr. Grynberg contracted with another company to move the rig from Wyoming to North Dakota and sought the return of the funds pre-paid to Bar S and into escrow. Bar S refused to return the pre-paid funds or release the escrow funds.

Mr. Grynberg then filed a complaint against Bar S for breach of contract, breach of the covenant of good faith and fair dealing, unjust enrichment, and conversion. Bar S filed a counterclaim against Mr. Grynberg for breach of the November 23, 2010 contract (the contract for the rig move from Pinedale, Wyoming to Williston, North Dakota), and breach of a unilateral contract (the contract for the rig move to Farson, Wyoming and the stack out at that location). Bar S also brought alternative equitable claims for quantum meruit and unjust enrichment for the Farson move.

Bar S moved for summary judgment on all the claims in Mr. Grynberg’s complaint and on its first counterclaim for breach of contract. The district court denied the motions on all of the claims, except for one. The district court concluded that Bar S was entitled to summary judgment on Mr. Grynberg’s unjust enrichment claim because there was an express contract between the parties.

The remaining claims were tried to a jury. The jury found in favor of Bar S and against Mr. Grynberg on all of his claims. The jury also found in favor of Bar S and against Mr. Grynberg on Bar S’s counterclaim that Mr. Grynberg had breached the November 23, 2010 contract. The jury further found that there was a separate, express contract for the Farson move and that Mr. Grynberg had breached that contract. The jury awarded damages in favor of Bar S on both contracts. The district court entered judgment in favor of Bar S.

Bar S filed a motion to alter or amend the judgment, arguing that it should be awarded additional damages in the form of prejudgment interest on the damages for the Farson move. Mr. Grynberg filed a motion for judgment as a matter of law notwithstanding the verdict and a motion for a new trial. The district court denied Bar S’s request for prejudgment interest and denied both of Mr. Grynberg’s motions. This appeal and cross-appeal followed.

II. Mr. Grynberg’s Appeal

A. Validity of the November 23, 2010 contract

In his complaint, Mr. Grynberg alleged that he contracted with Bar S to move an oil rig from Wyoming to North Dakota and that Bar S did not perform the work under the terms of the contract. In response to Bar S’s counterclaim, he admitted in his answer that the parties had entered into a contract on or about November 23, 2010 to move an oil rig from Pinedale, Wyoming to Williston, North Dakota (a copy of the contract that he signed on November 23, *739 2010 was also attached to the counterclaim complaint).

After proceeding on the basis that the November 23, 2010 contract was a valid contract for the first year of the litigation, Mr. Grynberg sought to amend his complaint at the summary judgment stage to drop his claim for breach of contract because Bar S had not signed the contract. The district court denied the motion to amend, explaining:

In this case, Grynberg failed to provide any reason why he was unaware that Bar S had not signed the contract. Grynberg brought this case as a breach of contract case and the parties conducted discovery based on the November 23, 2010 Contract. It was not until after Bar S filed its motions for summary judgment that Grynberg sought to amend its Complaint to withdraw its claim for breach of contract.
The parties in this case all believed that the November 23, 2010 Contract was in place and governed the parties’ actions in this case. The corresponding Escrow Agreement was signed based on the Contract. There is no reason for the Court to allow Grynberg to change its theory of the case at this late date.

Aplt.App., Vol. Ill at 451-52. Mr. Gryn-berg did not appeal from the denial of his motion to amend. Likewise, Mr. Gryn-berg never sought leave to amend his answer to the counterclaim complaint.

“Judicial admissions are formal admissions ... which have the effect of withdrawing a fact from issue and dispensing wholly with the need for proof of the fact.” Guidry v. Sheet Metal Workers Int’l Ass’n, 10 F.3d 700, 716 (10th Cir.1993) (internal quotation marks omitted). The judicial admissions in Mr. Grynberg’s complaint and answer to the counterclaim complaint remain binding on him. “[Ajdmissions in the pleadings ... are in the nature of judicial admissions binding upon the parties, unless withdrawn or amended.” See Missouri Housing Dev. Comm’n v. Brice, 919 F.2d 1306, 1314 (8th Cir.1990) (internal quotation marks omitted).

In response to summary judgment, Mr. Grynberg tried to create a factual dispute about the validity of the contract by arguing that Bar S had not signed the contract and had only signed the accompanying escrow agreement; that the bid Bar S submitted required both parties to sign the contract for it to be valid; and that Bar S indicated in an email after November 23 that there were outstanding issues that needed to be resolved before it could finalize the contract. Mr. Grynberg’s attempt to disavow his earlier judicial admissions about the validity of the contract with seemingly contrary evidence at summary judgment does not create a disputed issue of fact. See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
527 F. App'x 736, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grynberg-v-bar-s-services-inc-ca10-2013.