Groner v. On-Site Grading

CourtCourt of Appeals of Tennessee
DecidedApril 28, 2000
DocketE1999-00219-COA-R3-CV
StatusPublished

This text of Groner v. On-Site Grading (Groner v. On-Site Grading) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groner v. On-Site Grading, (Tenn. Ct. App. 2000).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE

CARROLL D. GRONER v. ON-SITE GRADING, INC.

Direct Appeal from the Chancery Court for Hamilton County No. 98-0314 Howell N. Peoples, Chancellor

No. E1999-00219-COA-R3-CV - Decided - April 28, 2000

This case involves a construction contract. When the plaintiff-owner decided that the project had not been completed in a timely fashion, he terminated the contract and sued the defendant-contractor for breach of contract. The defendant counterclaimed for wrongful termination of the contract. Following a bench trial, the Chancellor found for the defendant as to both claims and awarded damages on the counterclaim. Plaintiff appeals, arguing that the trial court erred in finding that the defendant did not breach the contract and in calculating the award of damages. As modified, we affirm the judgment of the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed, as Modified; Case Remanded

SUSANO, J., delivered the opinion of the court, in which FRANKS, and SWINEY , JJ., joined.

Arvin H. Reingold, Chattanooga, Tennessee, for the appellant Carroll D. Groner.

Don L. Smith, Nashville, Tennessee, for the appellee On-Site Grading, Inc.

OPINION

The plaintiff, Carroll D. Groner (“Developer”), entered into a contract with the defendant, On-Site Grading, Inc. (“Contractor”), for the construction of a roadway and sanitary sewer system on property being developed by the plaintiff. When the Developer decided that the project had not been completed on time, he terminated the contract and sued Contractor for breach of contract. Contractor counterclaimed for wrongful termination of the contract. After a bench trial, the Chancellor found in favor of the Contractor on both the claim and the counterclaim and awarded Contractor damages. Developer appeals, raising essentially two issues: (1) whether the trial court erred in finding that the Contractor did not breach the contract; and (2) whether the trial court erred in calculating damages. I. Facts

The parties entered into a contract on June 13, 1997. Developer prepared the contract. It was signed by Developer and Carl Mashburn, the president of the defendant corporation. Developer was aware that Contractor was not at that time a Tennessee-licensed contractor. Under the terms of the contract, Developer was to pay Contractor $176,775 for the latter’s work, and Contractor was to perform these services in accordance with the City of Chattanooga’s regulations and pursuant to plans developed by Betts Engineering Associates, Inc. (“Betts”). When the contract was executed, the Betts plans indicated that the sewer lines were to be four to five feet deep. Because no “survey” was performed, the contract included a provision that “[a]ny rock encountered, which can’t be moved by mechanical means, will be charged at $45 per cubic yard.” The contract also included a provision reciting that “[a]ny major changes in grading or drainage will be charged extra.” Because Developer wanted the project completed by the fall of 1997 so he could be prepared for the spring lot-buying season, the contract provided that Contractor was to complete the project “within ninety (90) consecutive calendar days after the date of starting.” Developer was to make progress payments to Contractor every two weeks.

The project experienced numerous delays. One of these delays occurred when the City -- declining to approve the plans developed by Betts -- mandated that the sewer be constructed nine to eleven feet deep rather than four to five feet deep as the parties had originally contemplated. Two or three days after commencing work on the sewer in mid-August, Contractor encountered rock. Because of the change in the sewer depth, Contractor had to remove substantially more rock than it had originally anticipated. The new sewer depth, which necessitated the blasting and removal of the unanticipated rock, delayed the project as much as two months.

In addition to the delay caused by the increased sewer depth, the project experienced several other delays. Poor weather between September and December, 1997, delayed the project two to three weeks. Developer’s delay in procuring a compaction test delayed the project approximately three weeks. Work that needed to be performed by utility companies before Contractor could continue its portion of the project caused a delay of approximately two weeks. Contractor at no time asked for a time extension. After the 90-day completion date passed, Developer continued to allow Contractor to work and encouraged it to finish.

Developer made progress payments to Contractor approximately every two weeks from July 7, 1997 to October 13, 1997. On October 24, 1997, Contractor sent a bill to Developer. This bill shows, among other things, the following:

Original Contract $176,775.00 Additions on Sewer 21,047.00 Rock blasting/removal 32,036.40 Total Revised Contract $229,858.40 Less: Progress payments 188,336.40 Balance $ 41,522.00

-2- Contractor’s secretary, Linda Mashburn (“Ms. Mashburn”), testified at trial that this bill did not reflect the extra expense incurred by Contractor for the additional rock blasting and removal necessitated by the increase in sewer depth. Developer, however, was under the impression that he only owed Contractor a total of $37,672 -- the $34,022 left under the original contract and $3,650 for storm drain extras.

Developer’s next progress payment of $7,500 was made November 13, 1997, a month after the previous progress payment. In December, 1997, Developer learned that Contractor had neglected to pay some suppliers and that these suppliers had placed liens against the property.

On December 12, 1997, Contractor sent a letter to Developer seeking payment of “$34,022.40 under contract and $ 3,650.00 in change orders for a total of $37,672.40.” Ms. Mashburn testified that this letter was not a final statement of what Developer owed Contractor and did not include the extra cost of rock blasting and removal. Mr. Mashburn stated in the aforesaid letter that he would return to the site when Developer paid $9,650. Developer replied that he would only issue payment after certain items were completed.

Contractor was at the site most of the week of December 15, 1997, attempting to finish the few remaining items. By Friday of that week, Developer still had not paid Contractor the amount Contractor had requested in its letter of December 12, 1997.

Developer and Mashburn met on December 22, 1997. At this meeting, Mashburn informed Developer that Developer not only owed the $37,672 left on the original contract but also owed Contractor for extra rock blasting and removal. Developer then terminated the contract. Contractor’s witness testified that it could have completed the project for $9,600.

When Developer terminated the contract, he had paid Contractor a total of $195,836.40. He had withheld payment of $37,672 -- an amount he considered to be the balance remaining -- because Contractor had not finished the project. Contractor, on the other hand, considered the balance remaining to be $112,506. The difference between the two figures arises out of a disagreement between the parties over an alleged engineering error and an amount for rock removal that Contractor did not consider part of the original contract.

Another point of contention at trial concerned the price at which the rock removal was to be compensated. The contract provides that Developer is to pay Contractor for the removal of rock at a cost of $45 per cubic yard. The testimony is in conflict, however, as to whether this portion of the contract was modified so as to reduce the payment for rock removal to $31.72 per linear foot. Developer testified that the agreement had been so modified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shepherd v. Perkins Builders
968 S.W.2d 832 (Court of Appeals of Tennessee, 1997)
Massengale v. Massengale
915 S.W.2d 818 (Court of Appeals of Tennessee, 1995)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Bowman v. Bowman
836 S.W.2d 563 (Court of Appeals of Tennessee, 1991)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Presley v. Bennett
860 S.W.2d 857 (Tennessee Supreme Court, 1993)
Wilson v. Page
325 S.W.2d 294 (Court of Appeals of Tennessee, 1958)
Zack Cheek Builders, Inc. v. McLeod
597 S.W.2d 888 (Tennessee Supreme Court, 1980)
Wright v. City of Knoxville
898 S.W.2d 177 (Tennessee Supreme Court, 1995)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)
Commerce Street Co. v. Goodyear Tire & Rubber Co.
215 S.W.2d 4 (Court of Appeals of Tennessee, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
Groner v. On-Site Grading, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groner-v-on-site-grading-tennctapp-2000.