Greenway Equipment, Inc. v. Johnson

2020 Ark. App. 336, 602 S.W.3d 142
CourtCourt of Appeals of Arkansas
DecidedJune 3, 2020
StatusPublished
Cited by4 cases

This text of 2020 Ark. App. 336 (Greenway Equipment, Inc. v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenway Equipment, Inc. v. Johnson, 2020 Ark. App. 336, 602 S.W.3d 142 (Ark. Ct. App. 2020).

Opinion

Cite as 2020 Ark. App. 336 Reason: I attest to the accuracy and integrity of ARKANSAS COURT OF APPEALS this document Date: 2021-06-17 11:41:34 DIVISION II Foxit PhantomPDF No. CV-19-644 Version: 9.7.5 Opinion Delivered: June 3, 2020

GREENWAY EQUIPMENT, INC., APPEAL FROM THE CRITTENDEN SUCCESSOR IN INTEREST TO COUNTY CIRCUIT COURT BARTON AG CENTER, INC., AN [NO. 18CV-12-55] ARKANSAS CORPORATION APPELLANT/CROSS-APPELLEE HONORABLE RICHARD LUSBY, V. JUDGE

BOYCE JOHNSON AFFIRMED ON DIRECT APPEAL; APPELLEE/CROSS-APPELLANT AFFIRMED ON CROSS-APPEAL

PHILLIP T. WHITEAKER, Judge

The appellant, Greenway Equipment, Inc., is a farm-equipment dealer. The appellee,

Boyce Johnson, is a Crittenden County farmer. Johnson filed suit against Greenway in

Crittenden County Circuit Court over the sale of a used tractor. Following a bench trial,

the circuit court found that Greenway had breached an express warranty and entered a

judgment against Greenway and in favor of Johnson. Both parties filed a notice of appeal

from the judgment. We affirm on both direct and cross-appeal. I. Facts and Procedural History

In December 2008, Johnson and Barton AG Center, Inc., 1 by and through its

employee, Gene Ward, began discussions and negotiations over the purchase of a tractor.2

Johnson expressed an interest in purchasing a used, low-engine-hour3 tractor. Ward advised

Johnson that Barton would be taking delivery of several low-hour tractors in early 2009.

Johnson advised Ward several times during their negotiations that he was only interested in

low-hour tractors, and each time Ward reiterated that the trade-in tractors would have

around 500 hours on them. The exact number of engine hours was unknown at the time

because the tractors were not currently on the dealership lot.4

During the negotiations, Ward advised Johnson that Barton would be receiving a

low-hours 2008 John Deere 8330 tractor that had the ability to operate an air seeder and a

no-till drill. Johnson was particularly interested in the John Deere because of those features

and its low hours. On December 30, Johnson agreed to buy the tractor for $142,500 and

placed a $28,500 deposit on it. Ward created a customer purchase-order form for the John

Deere. The form listed the specifications but did not indicate the number of engine hours.

1 Barton was subsequently purchased by Appellant Greenway Equipment, Inc. 2 These discussions occurred on three separate occasions over the course of a week, and the substance of these interactions are combined unless the timing is relevant to the issues at hand. 3 Instead of an odometer tracking mileage on a motor vehicle, tractors utilize an hour meter to indicate the extent of use. 4 Typically, farmers keep their trade-in tractors until their new tractors arrive; therefore, the trade-in tractors are not generally on the lot for inspection.

2 Johnson once again asked Ward about the hours on the tractor, and Ward specified that the

tractor would have 500–550 hours on it. Johnson then wrote “500–600 hours” on the copy

of the purchase order provided to him by Ward to ensure there was “no misunderstanding.”

Ward did not correct him.

In February 2009, Barton informed Johnson that the tractor had been received at the

dealership. When Johnson inquired as to the actual number of hours on the tractor, he was

informed that the tractor had 886 hours on it. Johnson refused to take possession of the

tractor because the number of hours was significantly more than he expected. Barton and

Johnson endeavored to settle the dispute but were unable to do so.

After settlement negotiations failed, Johnson attempted to find another tractor within

his specifications to either buy or rent for the 2009 crop season. He was unsuccessful in

purchasing another tractor that met his specifications. This forced him to change his intended

method of preparing and planting his land, resulting in approximately 75 acres being left

unplanted. Johnson was eventually able to rent a tractor from a local farmer but had to wait

until this tractor became available. This delayed planting and resulted in a reduced crop yield

for the 230 acres planted during the 2009 crop season.

In February 2012, Johnson filed suit against Greenway, the successor in interest to

Barton, alleging breach of contract and breach of an express warranty. Johnson sought

damages for lost profits on both the 75 unplanted acres and the diminished yield on the

remaining 230 acres. He further sought damages for his expenses in connection with the

tractor rental, for pre-irrigation and chemical expenses, for tractor repair, and for

prejudgment interest. Greenway answered, denying the allegations and alleged that if a breach

3 had occurred, Johnson had failed to properly mitigate his damages. Greenway also responded

that it was entitled to a credit against any damages award that Johnson might receive.5

The parties appeared at a bench trial in February 2019. After hearing all the evidence,

the circuit court found that Ward’s representations to Johnson created an express warranty

and that the tractor delivered did not conform to that warranty. The court then awarded a

judgment to Johnson in the amount of $96,600 representing the lost profits on the 230 acres

of reduced yield. The court denied all other requests for damages from Johnson and denied

Greenway’s request for credit for the income tax savings Johnson received from depreciating

the tractor. From this judgment, both parties appeal.

II. Analysis—Direct Appeal

Greenway raises five points on appeal: (1) the circuit court erred in finding that Ward’s

statements created an express warranty with regard to the hours on the tractor; (2) the circuit

court erred in finding that Johnson mitigated his damages; (3) the circuit court erred in

awarding damages that were based on speculation and conjecture; (4) the circuit court erred

in its refusal to reduce the damages award by Johnson’s tax savings; and (5) the circuit court

erred by refusing to admitting a prior inconsistent statement by Johnson.

Our standard of reviewing a judgment entered by a circuit court after a bench trial is

well established. We do not reverse such a judgment unless we determine that the circuit

court erred as a matter of law or we decide that its findings were clearly against the

5 Johnson depreciated the purchase price of the John Deere tractor on his 2008 tax return, and Greenway contends that the income tax savings Johnson received should be credited to them.

4 preponderance of the evidence. Ark. R. Civ. P. 52(a) (2019); Santifer v. Ark. Pulpwood Co., 66

Ark. App. 145, 991 S.W.2d 130 (1999).

A. Express Warranties

Greenway first argues that the circuit court erred in finding that Ward’s alleged

representations created an express warranty regarding the number of hours logged on the

tractor. The existence of an express warranty presents a mixed question of law and fact. See

Little Rock Sch. Dist. of Pulaski Cty. v. Celotex Corp., 264 Ark. 757, 765, 574 S.W.2d 669, 673

(1978), on reh’g sub nom. Little Rock Sch. Dist. of Pulaski Cty. v. Matson, Inc., 264 Ark. 757, 576

S.W.2d 709 (1979) (noting that if the parties involved have assumed conflicting postures

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montie Hobson v. George W. Hobson
2025 Ark. App. 311 (Court of Appeals of Arkansas, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ark. App. 336, 602 S.W.3d 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenway-equipment-inc-v-johnson-arkctapp-2020.