Greenfield Builders & Erectors, Inc. v. Fellure

443 N.E.2d 87, 1982 Ind. App. LEXIS 1511
CourtIndiana Court of Appeals
DecidedDecember 14, 1982
Docket1-981A262
StatusPublished
Cited by5 cases

This text of 443 N.E.2d 87 (Greenfield Builders & Erectors, Inc. v. Fellure) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenfield Builders & Erectors, Inc. v. Fellure, 443 N.E.2d 87, 1982 Ind. App. LEXIS 1511 (Ind. Ct. App. 1982).

Opinion

NEAL, Judge.

STATEMENT OF THE CASE

Cross-claimant-appellant Greenfield Builders and Erectors, Inc. (Contractor) appeals a judgment entered in the Hancock Circuit Court in a trial without a jury in a construction contract action wherein the court found an express written agreement binding between the Contractor and cross-defendants-appellees Edward A. Fellure and Richard A. Syphers (Owners). 1

We affirm.

STATEMENT OF THE FACTS

On December 30, 1976, the Owners acquired 5.37 acres in Hancock County, Indiana for the construction of a new commercial building for their company, Industrial Products, Inc. (IPI). At that time and throughout 1976 and 1977, the Owners were also officers, directors and the only shareholders of IPI. In August, 1976, one Raymond R. Baxter (Baxter), President of appellant Greenfield Builders, met with the Owners and orally agreed to construct a commercial building on their property for $275,000. However, in late December, 1976, *89 Baxter informed the Owners that he could not construct a building for that price and so the parties orally agreed to the increased price of $350,000.

On January 14, 1977, Baxter, acting on behalf of the Contractor, ordered component parts for a fourteen foot high building and retained Gregory Gammons, an architect, for $3,500. Gammons provided plans and specifications from time to time as requested by the Contractor; however, neither of the Owners was ever asked to provide plans or specifications.

After construction began, the Contractor and Owners orally agreed to a further increase in the cost of construction to $366,-000, the additional $16,000 cost was for construction of a concrete pad to be used for future expansion. Then, in April, 1977, the Contractor requested a partial payment of the agreed sum in the amount of $95,000. Before making this payment, Syphers requested the Contractor to prepare a written agreement which would confirm the oral contract. A building contract was prepared by the Contractor, signed by Baxter and presented to the Owners on May 2,1977. It provided for construction of a building for the sum of $350,000, and an expansion pad for $16,000, for an aggregate amount of $366,000. The contract further provided that neither the Contractor nor any other person or entity would place any mechanic’s or materialmen liens against any real estate of the Owners.

The Owners accepted the writing by tendering a check for $95,000 to the Contractor on May 4, 1977. Subsequently, additional payments were made to the Contractor in the total amount of $335,000. Each payment was by check plainly marked “S.A.F.E. Richard A. Syphers, Edward A. Fellure.” During construction, the Owners requested changes and additions to the original plans which added $40,303.59 to the original contract price. Then, on October 14, 1977, the parties met at Baxter’s house to discuss the extra costs. After discussing only one or two items, Baxter advised the Owners, “[b]y god there will be no nit picking, you pay me $421,000 or we go to arbitration.” Baxter also tacked on an additional charge of $20,000, bringing the total amount he demanded to $441,000. Later the same day, the Owners offered to pay $400,000.

On October 17, 1977, the Contractor stopped working and instructed his employees and the subcontractors not to return to the construction site. No further work would be performed, the Contractor advised the Owners, until they agreed to pay the additional sum, which they refused.

Following a trial, the court entered special findings on April 8, 1981, which in pertinent part provided that 1) the actions of the parties together with the acceptance by the Contractor of the Owners’ checks demonstrate that the parties intended to be bound by the provisions of the written agreement; 2) the Owners should receive a $41,435.65 credit toward the original contract price of $366,000 in satisfaction of various subcontractors’ mechanic’s liens judgments which they paid; 3) the Owners should receive a credit for $16,071.94 which they expended to correct deficient work by the Contractor; 4) the Owners should receive a $55,986.71 credit for money they expended to complete the construction; and 5) there is no evidence of the Contractor’s having timely and properly filed notice of an intention to hold a lien on the Owners’ property.

The trial court thereafter adjudged that 1) the Contractor was entitled to recover $62,243.59 from the Owners for changes and additions they requested after the original contract; and 2) the Owners were entitled to $113,494.30 from the Contractor for costs paid by the Owners to correct deficiencies and to complete performance of the building.

ISSUES

The Contractor presents five issues for review which we restate as follows:

I. Whether the trial court erred in finding that a written contract existed between the Contractor and Owners, which agreement included a no-lien provision;
*90 II.Whether the Owners breached the contract and thereby excused the Contractor from further performance;
III. Whether the trial court erred in finding that there was no evidence to show a valid filing of a notice to hold a mechanic’s lien;
IV. Whether there is sufficient evidence to sustain the trial court’s findings as to costs and additions in the construction; and
V.Whether the trial court erred in finding that the Owners expended $16,071.94 to correct deficient work performed by the Contractor.

DISCUSSION AND DECISION

Issue I. Contract

a. Offeree

The Contractor argues that the trial court erroneously found some blank forms Baxter gave the Owners as evidence of a written agreement between the parties. However, in the event this writing represents an offer, the offeree is IPI, not the Owners, Fellure and Syphers, who are not the designated parties to the contract. The Contractor further asserts that aside from the payment of $95,000 by the Owners upon receipt of the signed agreement by Baxter, no notice of acceptance was made by IPI, the named party on the contract. The Contractor cites Gates v. Petri, (1957) 127 Ind. App. 670, 143 N.E.2d 293, for the proposition that an offer can be accepted only by the offeree, IPI, and any manifestation of acceptance by the Owners personally is no notice of acceptance of the contract by IPI.

We first note that the trial court made special findings and conclusions in this cause. In reviewing the trial court’s findings of fact, the Court of Appeals neither weighs the evidence nor determines the credibility of the witnesses; findings of fact will be disturbed only if the record discloses that there were neither facts nor inferences on which to base the findings. Indiana Tri-City Plaza Bowl, Inc. v. Estate of Glueck, (1981) Ind.App., 422 N.E.2d 670. In other words, this court will disturb the trial court’s findings of fact only when such are clearly erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayberry Café, Inc. v. Glenmark Construction Co.
879 N.E.2d 1162 (Indiana Court of Appeals, 2008)
Woodworth v. Estate of Yunker
673 N.E.2d 825 (Indiana Court of Appeals, 1996)
Gibson-Lewis Corp. v. Northern Indiana Public Service Co.
524 N.E.2d 1316 (Indiana Court of Appeals, 1988)
Smith v. Union State Bank
452 N.E.2d 1059 (Indiana Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
443 N.E.2d 87, 1982 Ind. App. LEXIS 1511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenfield-builders-erectors-inc-v-fellure-indctapp-1982.