Green v. Pendergraft

179 So. 2d 831, 253 Miss. 891, 1965 Miss. LEXIS 1066
CourtMississippi Supreme Court
DecidedNovember 8, 1965
Docket43654
StatusPublished
Cited by10 cases

This text of 179 So. 2d 831 (Green v. Pendergraft) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green v. Pendergraft, 179 So. 2d 831, 253 Miss. 891, 1965 Miss. LEXIS 1066 (Mich. 1965).

Opinion

Brady, Tom P., J.

This is an appeal from a suit brought by the appellee against appellants in the Circuit Court of Warren County, Mississippi, for labor and materials furnished by the appellee in remodeling a house owned by the appellants in the city of Vicksburg, Mississippi. The appellee sued for the amount of $11,888.86, together with a lien-against the property for said amount. The appellants denied the indebtedness and filed a cross-bill for the sum of $11,931.50. The jury returned a verdict in favor of ap *894 pellee in the sum of $10,500. Judgment was entered in favor of appellee for that amount, together with a lien on the property of appellants. Prom this judgment appellants have prosecuted this appeal. The record discloses the following pertinent facts:

Appellants sought the services of appellee, whom they had known and who had been in business for many years in Vicksburg, to assist them in planning the remodeling of an old house which the appellant, Benton H. Green, had inherited from his father. Several conferences were held between appellants and appellee with reference to the changes and work which the appellants desired. The appellee wrote a letter to appellants on July 21, 1962, setting forth generally the basis upon which he would undertake the work in accordance with their desires. The letter indicated specifically that the appellee would undertake the work on a cost-plus basis, as the appellee was unwilling to perform the work on a contract basis because it could not be determined with any degree of exactness the cost of the proposed work since the appellants did not know at that time ultimately what they wanted to have done. Appellee’s letter submitted a rough estimate of the cost of the proposed work, which amounted to the sum of $16,717. After further discussions, it was mutually agreed that certain items would be deleted as the appellants desired to keep the cost within $14,000. The appellee made a note of the reduction, “Cut to $14,000,” on the estimate which he had submitted.

The record shows, and the appellee admits, that during the early discussions of the proposed work appellants did express a desire to keep the work within the $14,000 cost limit but appellee asserts that as the work progressed and as additional items were added at the request, of the appellants, the $14,000 figure was disregarded and was not further considered. Appellants admit that the plans were changed and, after the work had begun, the following additions were made: A second *895 bathroom, a bay window in the family room, a den, a barbeque pit, a chimney, kitchen flooring, and a garage. The garage was included in the original estimate, was then deleted, but was finally included in the work.

In addition, the record discloses that certain work was done on the brick front porch which had not been included in the original estimate. Appellants testified that these additions were made at their request and that they were fully aware that all this work was being done, and both appellants agreed that Mrs. Green was on the job practically every day, in some instances supervising and criticizing the work as it progressed. Mrs. Green stated that she watched the job closely and kept account of the number of loads of concrete that went into the garage floor, all of the lumber and roofing that went into the garage, and the payroll of some of appellee’s workmen at various times. Appellants’ contention that they were not aware of what was taking place and the probability that the cost of the work would exceed the $14,000 figure is not established by the record.

The appellee, his witnesses, and some of his workmen testified that the presence of Mrs. Green on the job so much of the time, her endeavors to direct the men in the performance of their work, and her close supervision thereof, constituted a harassment of them to such a degree that finally after about six months, on May 9, 1963, the workmen walked off the job and the appellee quit. On May 28, 1963, at the request and insistence of appellants, the appellee returned and resumed work on the house.

The record discloses that during the time the work was progressing statements were made approximately every thirty days by the appellee to the appellants showing the indebtedness due the appellee. These amounts were promptly paid. The appellee submitted monthly statements for four consecutive months, from December, 1962, through March, 1963. The amounts paid by the appellants totaled a little more than $9,000. The monthly *896 statement for April was not paid, and no statement was submitted for the month of May. On June 16, 1963, the appellee rendered a statement to the appellants for the sum of $8,733.79, and on August 2, 1963, he rendered another statement for the sum of $389.79. The record discloses that when, except for a few items, the house was substantially completed, the work of appellee was finally stopped on July 10, 1963, at the request of appellants, which they admit. Thereafter appellee did not have an opportunity to finish the work which he had undertaken.

Subsequent to his discharge, appellee brought suit for the unpaid sum of $11,888.86, covering all the materials he had purchased and the services which he had expended in remodeling appellants’ house. It is the contention of the appellants that the appellee had agreed to perform the work for a sum not in excess of $14,000. The appellants also contend that appellee’s estimate was grossly incorrect, misleading, and negligently made and that the appellee’s charges for his work were grossly excessive. Appellants further assert that appellee’s work was done negligently, incompetently, and demonstrated poor workmanship. In support of these contentions the appellants introduced Mr. William Ward Easley, III, a registered architect, who inspected appellants’ house and the work done by appellee, sometime after appellee had performed his last work there. Mr. Easley testified in minute detail with reference to all of the work which had been performed by the appellee and specifically noted many detailed items which, in his opinion, evidenced poor workmanship, improper construction, or defective materials which had been performed or utilized by the appellee in his remodeling of the house.

The record discloses appellee obtained the services of other persons to finish the remodeling of the house, some of which in the original estimate the appellee was not required to complete. Errors in construction, in selection of materials, in the proper treatment of ma *897 terials, in the remodeling of the house and the construction of the garage and porch were all noted by-Mr. Easley, who made an exhaustive presentation to the jury of the defects which he claimed to have found. The jury returned a verdict for $10,500 in favor of the appellee, and from this verdict this appeal is prosecuted.

Numerous errors are assigned by the appellant, but only three assignments are considered or urged in appellants’ brief. These errors are: (1) The court should have declared a mistrial in the case; (2) the verdict does not correspond with and is against the evidence given at the trial; and (3) the verdict of the jury does not correspond with the law of the case and is excessive in amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DC General Contractors, Inc. v. Slay Steel, Inc.
109 So. 3d 577 (Court of Appeals of Mississippi, 2013)
Toyota Motor Corp. v. McLaurin
642 So. 2d 351 (Mississippi Supreme Court, 1994)
Singing River Mall Company v. Mark Fields, Inc.
599 So. 2d 938 (Mississippi Supreme Court, 1992)
Eastline Corp. v. Marion Apartments, Ltd.
524 So. 2d 582 (Mississippi Supreme Court, 1988)
Samples v. Hall of Mississippi, Inc.
673 F. Supp. 1413 (N.D. Mississippi, 1987)
Slay v. Illinois Cent. Gulf R. Co.
511 So. 2d 875 (Mississippi Supreme Court, 1987)
Troy Mining Corp. v. Itmann Coal Co.
346 S.E.2d 749 (West Virginia Supreme Court, 1986)
Gentry ex rel. Gentry v. Ferrill
288 So. 2d 18 (Mississippi Supreme Court, 1974)
Mooney v. Lawley
214 So. 2d 679 (Mississippi Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
179 So. 2d 831, 253 Miss. 891, 1965 Miss. LEXIS 1066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-v-pendergraft-miss-1965.