DC General Contractors, Inc. v. Slay Steel, Inc.

109 So. 3d 577, 2013 WL 427380, 2013 Miss. App. LEXIS 50
CourtCourt of Appeals of Mississippi
DecidedFebruary 5, 2013
DocketNo. 2011-CA-00827-COA
StatusPublished
Cited by3 cases

This text of 109 So. 3d 577 (DC General Contractors, Inc. v. Slay Steel, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DC General Contractors, Inc. v. Slay Steel, Inc., 109 So. 3d 577, 2013 WL 427380, 2013 Miss. App. LEXIS 50 (Mich. Ct. App. 2013).

Opinions

ISHEE, J.,

for the Court:

¶ 1. DC General Contractors Inc. contracted with Slay Steel Inc. for the fabrication of steel for a construction project that was ultimately abandoned. Slay Steel filed a breach-of-contraet suit seeking to recover $165,000 for its losses on materials purchased for the project and lost profits. A jury trial was held. The jury found in favor of Slay Steel and awarded $41,500 in damages.

¶2. DC General appeals, asserting the parties agreed to a contract modification that released DC General from liability. Slay Steel cross-appeals requesting an ad-ditur. It asserts the jury’s verdict of $41,500 was an impermissible compromise verdict. We affirm on both the appeal and cross-appeal.

FACTS AND PROCEDURAL HISTORY

¶ 3. DC General, a general contractor, was hired to oversee the construction of a Big Buck Sports retail store in Hatties-burg, Mississippi. On January 15, 2008, DC General contracted with Slay Steel for the fabrication of structural steel for the store. Slay Steel agreed to cut and fabricate the steel in preparation for construction. The purchase order was for $936,830. Big Buck Sports’ owners had [580]*580trouble financing the store, and the construction was delayed. However, Slay Steel had already begun purchasing materials, as the price quoted in the purchase order was based on the then-current market price of steel.

¶ 4. On May 13, 2008, when no progress had been made by Big Buck Sports, Slay Steel invoiced DC General $289,819.90 for materials Slay Steel had purchased and stored in anticipation of construction starting. DC General forwarded the invoice to Big Buck Sports’ owners with an attached letter stating: “We need to pay for these materials as soon as possible.” Big Buck Sports’ owners replied that they did not want to commit funds to hold the inventory, and the invoice went unpaid. Through subsequent letters exchanged by the parties, Slay Steel was given permission to “utilize this material on other projects as needed,” since it was unclear when the project would start. However, Slay Steel proposed that the contract price would need to be renegotiated if this was done. DC General responded, “we will evaluate steel costs to replace the steel you use and adjust our pricing at that point.” Slay Steel used or sold the materials as it was able. Ultimately, Big Buck Sports failed to obtain financing and cancelled its contract with DC General. DC General paid Slay Steel $60,000 for shop drawings, but this was the only payment Slay Steel received. This amount is separate from the $289,819.90 requested for materials.

¶ 5. Slay Steel sought compensation from DC General for its losses. DC General refused. On January 14, 2010, Slay Steel filed a breach-of-contract suit in the Lauderdale County Circuit Court. A trial was held, consisting of testimony by Greg Slay, vice president of Slay Steel, and Dorian Shoemake, owner of DC General.

¶ 6. At trial, Slay Steel argued DC General breached the contract by failing to specify a delivery date for the fabricated steel in a timely manner. DC General moved for a directed verdict at the end of Slay Steel’s ease-in-chief and again at the close of all evidence. In its motions, DC General argued that it was not liable to Slay Steel for breach of contract because the subsequent letters exchanged by the parties served to modify the contract upon the decision by Big Buck Sports’ owners not to proceed with construction of the store. The motions were denied. The jury returned a verdict in favor of Slay Steel for $41,500. DC General moved for an additur, a judgment notwithstanding the verdict, or, in the alternative, a new trial. All three motions were denied. DC General now appeals arguing the trial court erred in denying its motion for a directed verdict. Slay Steel cross-appeals arguing the trial court erred in denying its motion for an additur or, in the alternative, a new trial on damages.

STANDARD OF REVIEW

¶ 7. The denial of a motion for a directed verdict or JNOV is reviewed de novo. White v. Stewman, 932 So.2d 27, 32 (¶ 10) (Miss.2006). The criteria for review are as follows:

This Court will consider the evidence in the light most favorable to the appellee, giving that party the benefit of all favorable inferenee[s] that may be reasonably drawn from the evidence. If the facts so considered point so overwhelmingly in favor of the appellant that reasonable [jurors] could not have arrived at a contrary verdict, we are required to reverse and render. On the other hand[,] if there is substantial evidence in support of the verdict, that is, evidence of such quality and weight that reasonable and fair minded jurors in the exercise of impartial judgment might have reached different conclusions, affirmance is required. [581]*581The above standards of review, however, are predicated on the fact that the trial judge applied the correct law.

Solanki v. Ervin, 21 So.3d 552, 557 (¶ 10) (Miss.2009) (quoting Ala. Great S. R.R. v. Lee, 826 So.2d 1232, 1235-36 (¶ 12), 826 So.2d 1232 (Miss.2002)). In other words, we must consider “whether the evidence, as applied to the elements of a party’s case, is either so indisputable, or so deficient, that the necessity of a trier of fact has been obviated.” White, 932 So.2d at 32 (¶ 11).

¶ 8. The denial of an additur is reviewed for abuse of discretion. Thompson v. Nguyen, 86 So.3d 232, 237 (¶ 18) (Miss.2012).

DISCUSSION

I. DENIAL OF MOTION FOR A DIRECTED VERDICT

¶ 9. DC General argues it was entitled to a directed verdict because the two letters exchanged by the parties modified the contract such that it was not liable for Slay Steel’s losses once the project was abandoned by Big Buck Sports’ owners.

¶ 10. “It is well established that contracts may be modified by a subsequent agreement between the parties.” Heritage Bldg. Prop., LLC, v. Prime Income Asset Mgmt., Inc., 43 So.3d 1138, 1143 (¶ 10) (Miss.Ct.App.2009) (citing Kelso v. McGowan, 604 So.2d 726, 731 (Miss.1992)). “For a subsequent agreement to modify an existing contract, the later agreement must, itself, meet the requirements for a valid contract.” Singing River Mall Co. v. Mark Fields, Inc., 599 So.2d 938, 947 (Miss.1992). A valid contract requires an offer and acceptance. Heritage Bldg. Prop., 43 So.3d at 1143 (¶ 10). “Failure to communicate acceptance of an offer is fatal to [the] creation of a valid contract.” Anderton v. Bus. Aircraft, Inc., 650 So.2d 473, 476 (Miss.1995) (citing R.C. Constr. Co., Inc. v. Nat’l Office Sys., Inc., 622 So.2d 1253, 1255 (Miss.1993)). An agreement modifying a contract does not need consideration to be binding. Miss.Code Ann. § 75-2-209(1) (Rev.2002).

¶ 11. The contract that is the subject of this action is the January 15, 2008 purchase order for the fabrication of steel. The purchase order states that Slay Steel will “effect complete delivery [of the fabricated steel] to the job site by TBD with partial deliveries as required by job progress .... ”

¶ 12. On June 25, 2008, when no delivery date had been determined, Slay Steel sent DC General’s manager, Ken Taylor, the following letter:

Dear Ken,
As you know, I received a purchase order on Big [B]uck on January 15, 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
109 So. 3d 577, 2013 WL 427380, 2013 Miss. App. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dc-general-contractors-inc-v-slay-steel-inc-missctapp-2013.