Great Northern Insurance v. Architectural Environments, Inc.

514 F. Supp. 2d 139, 2007 U.S. Dist. LEXIS 71867
CourtDistrict Court, D. Massachusetts
DecidedSeptember 14, 2007
DocketCivil Action 05-12356-NMG
StatusPublished
Cited by5 cases

This text of 514 F. Supp. 2d 139 (Great Northern Insurance v. Architectural Environments, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great Northern Insurance v. Architectural Environments, Inc., 514 F. Supp. 2d 139, 2007 U.S. Dist. LEXIS 71867 (D. Mass. 2007).

Opinion

MEMORANDUM & ORDER

GORTON, District Judge.

The underlying case involves allegations of negligence and breach of warranties resulting from a building fire on April 26, 2005. The plaintiff, Great Northern Insurance Co. (“Great Northern”), insured the building and brings this action as the sub-rogee of the insured party, Transkaryotic Therapies, Inc. (“TKT”). The plaintiff alleges that the fire originated on the roof and was able to ignite and spread rapidly as a result of the presence of certain insulation and weatherproofing materials located in the roof-top duct work. The particu *141 lar insulation and weatherproofing was Alumaguard, the use of which was allegedly in violation of the Massachusetts State Building Code.

The named defendants are various entities involved with the design and construction of renovations to the building: 1) AHA Consulting Engineers, Inc. (“AHA”), which contracted with TKT to provide mechanical and electrical engineering services, 2) Architectural Environments, Inc. (“AEI”), the construction manager, 3) United HVAC Co., Inc. (“United HVAC”), AEI’s subcontractor for the installation of the HVAC systems, 4) United Insulation Specialties, Inc. (“United Insulation”), supplier and installer of the insulation and weatherproofing material, 5) Polyguard Products, Inc. (“Polyguard”), manufacturer of the insulation and weatherproofing material sold to United Insulation and 6) General Insulation Co. (“General Insulation”), the alleged distributor of the insulation and weatherproofing material.

The first four defendants filed separate motions for summary judgment, seeking dismissal of all claims and cross-claims brought against them. All of the defendants agree that their respective cross-claims against each other should be dismissed insofar as the plaintiffs direct claims against them are dismissed. The Court referred those motions to United States Magistrate Judge Judith Dein and on August 28, 2007, she issued a Report and Recommendation (“R & R”). After reviewing the R & R and the objections thereto filed by the several parties, the Court will accept and adopt the R & R after briefly addressing those objections.

I. Dismissal of Claims Against AHA

The Magistrate Judge recommends that the motion for summary judgment of defendant AHA be allowed, in part, and denied, in part. Specifically, she recommends that, pursuant to the statute of repose, the claims of negligence and breach of implied warranties, but not the claim for breach of express warranties, should be dismissed. Plaintiff Great Northern objects to the proposed ruling and contends that the Magistrate Judge erroneously concluded that the Complaint was not filed within the six-year statute of repose period.

AHA has moved for summary judgment on all claims on the grounds that the suit is barred by the relevant statute of repose. That provision provides, in part:

Actions of tort for damages arising out of any deficiency or neglect in the design, planning, construction or general administration of an improvement to real property ... shall be commenced only within three years next after the cause of action accrues; provided, however, that in no event shall such actions be commenced more than six years after the earlier of the dates of: (1) the opening of the improvement to use; or (2) substantial completion of the improvement and the taking of possession for occupancy by the owner.

Mass. Gen. Laws ch. 260, § 2B (emphasis added). In her R & R, the Magistrate Judge determines and concludes that: 1) Great Northern’s claims for negligence and breach of implied warranties qualify as tort claims within the ambit of the statute of repose, 2) the improvements on the building were open to use in August, 1999, which is, albeit by only three months, more than six years prior to the November, 2005 filing of this Complaint, and 3) the statute of repose bars the negligence and implied warranties claims and, therefore, summary judgment should be allowed,

The central issue is when the statute of repose began to run. The statute provides that it runs from the earlier of: *142 1) “the opening of the improvement to use” or 2) “[the] date of substantial completion of the improvement and the taking of possession for occupancy by the owner”. Mass. Gen. Laws ch. 260, § 2B. The Magistrate Judge properly concludes that, in this case, the certificate of occupancy, which grants the owner the right to occupy the premises, determines the date upon which the improvement was open to use, as well as the date it was occupied. See Aldrich v. ADD, Inc., 437 Mass. 213, 221-222, 770 N.E.2d 447 (2002). In this case, the temporary and permanent certificates of occupancy were issued, in August and December of 1999, respectively. The Magistrate Judge concludes that the premises were open to use under the temporary certificate of occupancy and, thus, the August, 1999 date is the operative date. Great Northern disagrees. The distinction between the two certifícate dates is meaningful because the Complaint was filed within the permissible six-year period if the December date is operative.

In her R & R, the Magistrate Judge specifically addresses the question of whether the “temporary” certificate of occupancy establishes the date on which the building was open to use:

[w]hile there conceivably may be situations which would preclude a “temporary” [certificate of occupancy] from being the date an improvement is open to use, in the instant case the [temporary [certificate of occupancy] expressly authorized the exact same occupancy as the [p]ermanent [certificate of occupancy]. There were no limitations on the use TKT could make of the Building.

After a thorough review of the case law and the plaintiffs arguments, the Magistrate Judge found that the mere fact that a certificate of occupancy is “temporary” does not negate the fact that it was open for use. This Court agrees. Having found that the improvements were open to use in August, 1999, the Magistrate Judge properly did not reach the issue of when construction was substantially completed.

With respect to express warranties, she concludes, again correctly, that: 1) the statute of repose is inapplicable and 2) questions of material fact preclude the entry of summary judgment. Specifically, there is a genuine issue of material fact as to whether AHA was required to and/or did approve the use of the insulation. Neither party has filed an objection to those conclusions and the Court concurs with the Magistrate Judge’s recommendation to deny the motion for summary judgment with respect to the claim of express warranties.

II. Dismissal of Claims Against AEI, United HYAC and United Insulation

The Magistrate Judge provides two separate recommendations with respect to the summary judgment motions of defendants AEI, United HVAC and United Insulation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
514 F. Supp. 2d 139, 2007 U.S. Dist. LEXIS 71867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-northern-insurance-v-architectural-environments-inc-mad-2007.