Great American Insurance Company v. Hinkle Contracting Corporation

497 F. App'x 348
CourtCourt of Appeals for the Fourth Circuit
DecidedNovember 28, 2012
Docket12-1014
StatusUnpublished
Cited by5 cases

This text of 497 F. App'x 348 (Great American Insurance Company v. Hinkle Contracting Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great American Insurance Company v. Hinkle Contracting Corporation, 497 F. App'x 348 (4th Cir. 2012).

Opinion

Vacated and remanded by unpublished opinion. Judge KEENAN wrote the opinion, in which Judge KING and Judge THACKER joined.

Unpublished opinions are not binding precedent in this circuit.

BARBARA MILANO KEENAN, Circuit Judge:

This appeal concerns the scope of an arbitration clause contained in a written agreement between a general contractor and subcontractor (the subcontract), which was incorporated without limitation in a performance bond issued by a surety guaranteeing the subcontractor’s obligations. After the subcontractor defaulted, the surety filed the present declaratory judgment action against the general contractor seeking to avoid the surety’s obligations under the performance bond. The general contractor responded by seeking a dismissal or stay of the declaratory judgment proceedings pending arbitration of the parties’ dispute.

The district court determined that the surety’s claims were not arbitrable, holding that the parties intended to exclude claims brought by the surety under the terms of the performance bond. The district court therefore denied the general contractor’s motion for stay or dismissal of the proceedings pending arbitration. We reverse the district court’s decision based on the broad scope of the arbitration clause, which manifested the parties’ intent that all claims “arising from or relating to” the subcontract be subject to arbitration.

I.

In November 2009, the West Virginia Department of Transportation (WVDOT) hired Hinkle Contracting Corporation, LLC (Hinkle) as the general contractor for construction of a portion of a highway in Mingo County. Hinkle entered into a subcontract with Chapman-Martin Excavation and Grading, Inc. (CME or the subcontractor) to perform the grading and drain work for the highway project.

As required by the subcontract, CME obtained both a performance bond and a payment bond. Great American Insurance Company (Great American or the surety) issued those bonds, naming CME as principal and Hinkle as obligee. The performance bond, the only bond at issue in the present case, stated that Hinkle and CME had entered into the subcontract, and that the “subcontract is by reference made a part hereof.” The performance bond also stated that if CME defaulted on its obligations under the subcontract, Great American was required to remedy CME’s default either by providing for completion of CME’s work or by compensating Hinkle financially for the reasonable costs of completing that work. Finally, the performance bond stated that “[a]ny suit under this bond must be instituted” within two years from the due date of the final payment under the subcontract.

After obtaining the required bonds, CME began its work on the highway project. In September 2010, Hinkle notified *350 CME that it was in default for failing to complete certain work. Hinkle and CME entered into negotiations to cure the default and ultimately executed a “change order” to the subcontract, which modified CME’s contractual obligations. The change order established new deadlines for the completion of various phases of CME’s work, and included provisions for an award of liquidated damages to Hinkle in the event that CME defaulted on its obligations under the change order.

Several months later, Hinkle again declared CME in default, citing CME’s failure to complete its work as required by the subcontract and the change order. In March 2011, Hinkle notified Great American that CME was in default and demanded payment from Great American under the terms of the performance bond.

Great American filed a complaint in the district court against Hinkle seeking a declaratory judgment that Great American was not liable under the performance bond, primarily because the change order materially altered “the financial obligations under the [subcontract in the event of default by CME.” Great American alleged that the terms in the change order were not “within the reasonable contemplation of Great American” when it issued the performance bond.

In an amended complaint, Great American raised an additional claim. In that claim, Great American alleged that Hinkle breached the terms of its contract with WVDOT, which was incorporated into the subcontract, by failing to pay CME for work performed under the subcontract. Great American accordingly sought an order requiring Hinkle to provide an accounting of payments received from WVDOT and to deposit with the district court funds owed to CME.

Hinkle filed a motion to dismiss or stay the proceedings pending arbitration, pursuant to Hinkle’s notice and demand for arbitration issued in July 2011. Hinkle asserted that because the performance bond incorporated the subcontract in its entirety, including the provisions granting Hinkle an exclusive right to demand arbitration, Great American was obliged to submit its claims to arbitration.

The language at issue in the subcontract is contained in Section 16, which is entitled “Dispute Resolution.” Included in this section is a provision stating that “[a]ll claims, disputes, controversies and matters in question (hereinafter ‘Claims’) arising out of, or relating to, this [subcontract] or the breach thereof ... shall be resolved by mediation followed by arbitration or litigation at [Hinkle’s] sole option.”

The district court denied Hinkle’s motion to dismiss or stay the proceedings pending arbitration. The court concluded that although the arbitration clause states that it applies to all claims arising out of or relating to the subcontract, other language in the subcontract demonstrates the parties’ intent to limit the scope of arbitrable disputes. In support of its conclusion, the court relied on Section 16.2(e), which details dispute resolution procedures. That provision states, in relevant part:

If a disputed Claim remains unresolved after negotiation and mediation, [Hin-kle] shall have the exclusive option either to have the dispute decided by a court or by arbitration.... [Hinkle], Subcontractor and Subcontractor’s surety agree that the disputed Claim shall be resolved in the appropriate forum selected by [Hinkle] at its sole discretion. If Subcontractor or its surety first commences a court action with respect to a dispute which [Hinkle] desires to have determined by an arbitration proceeding, or if Subcontractor or its surety first commences an arbitration proceeding which [Hinkle] desires *351 to have determined by a court, [Hinkle] shall commence the arbitration proceeding or court action ... within thirty (30) calendar days after receiving service of Subcontractor’s complaint or arbitration demand. If, at any time ... [Hinkle] becomes involved in litigation or arbitration with another party or parties involving questions of fact or law common to the dispute between [Hinkle] and Subcontractor to the extent that (a) in Subcontractor’s absence, complete relief cannot be accorded among those already parties, or (b) disposition of such other action may as a practical matter, impair or impede [Hinkle’s] or Subcontractor’s ability to fully prevent its incurring multiple or otherwise inconsistent obligations, then Subcontractor and its surety

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
497 F. App'x 348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-american-insurance-company-v-hinkle-contracting-corporation-ca4-2012.