Grasso Paving, Inc. v. Ascot Dev. Corp., No. Cv 95 0146827 (Apr. 16, 1997)

1997 Conn. Super. Ct. 3844
CourtConnecticut Superior Court
DecidedApril 16, 1997
DocketNo. CV 95 0146827
StatusUnpublished

This text of 1997 Conn. Super. Ct. 3844 (Grasso Paving, Inc. v. Ascot Dev. Corp., No. Cv 95 0146827 (Apr. 16, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grasso Paving, Inc. v. Ascot Dev. Corp., No. Cv 95 0146827 (Apr. 16, 1997), 1997 Conn. Super. Ct. 3844 (Colo. Ct. App. 1997).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION CT Page 3845 This case involves the foreclosure of a mechanic's lien and presents the issue of whether an alleged accord and satisfaction occurred. The plaintiff, Grasso Paving, Inc., is an excavating and paving contractor. In its complaint, the plaintiff alleges that it had a contract with the named defendant, Ascot Development Corp. (Ascot), the general contractor, to provide services and material to premises on Sunset Road, Stamford, owned by the co-defendants, Leandro Rizzuto, Jr., the principal officer of Ascot, and his wife, Denise Ann Rizzuto. The plaintiff also alleges that it began work on March 29, 1995, finished on April 7, 1995, and recorded a certificate of mechanic's lien on the Stamford land records on June 22, 1995, in the amount of $5,117.96. The plaintiff seeks a foreclosure of its mechanic's lien1 and related relief. The defendants filed an answer denying the material allegations of the complaint and three special defenses: (1) that the plaintiff was paid in full; (2) that the amount owed the plaintiff was in dispute, and on June 8, 1995, the defendants sent a check to the plaintiff for $5,000, which was accepted by the plaintiff in full settlement of the amount due the plaintiff, viz., an accord and satisfaction; and (3) that they did not owe any money to the plaintiff.

This case was referred to Attorney Jules Lang, an attorney trial referee, in accordance with General Statutes § 52-434 (a) and Practice Book § 428 et seq. The referee conducted a trial and then submitted a report finding the following facts: (1) the plaintiff and the defendants signed an agreement dated March 24, 1995, for excavating and drainage work, to be billed on a cost plus basis, but with a maximum of $5,000; (2) the plaintiff claimed that the scope of the work had been increased at the request of the defendants, and sent a final bill to the defendants, dated April 20, 1995, in the amount of $14,209, which invoice also referred to an additional amount to be charged for paving a certain apron on the roadway; (3) the defendants sent a check for $5,000 on April 20, 1995, and a second check on June 8, 1995, for an additional $5,000, for a total of $10,000 received by the plaintiff; (4) the second check for $5,000 was accompanied by a letter from the defendants indicating that the amount sent represented payment in full2; (5) thereafter the plaintiff completed the paving, and on June 7, 1995, sent the defendants a separate bill for $908.86; (6) the plaintiff endorsed, deposited and cashed the check for $5,000 sent by the defendants on June 8, CT Page 3846 1995; and (7) when accepting the check, the plaintiff's lawyer wrote on June 12, 1995, that the defendants still owed his client the balance due on the original invoice of $14,209, as well as for the paving.3

The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) by cashing the defendants' June 8, 1995 check for $5,000, the plaintiff entered into a binding accord based on mutual assent; (2) the plaintiff had not complied with the accord because it attempted to charge the defendants for the paving of the apron by charging an extra $908; (3) even if an accord and satisfaction had not been reached, because of a lack of a meeting of the minds, the plaintiff would still not be entitled to recover any money because the original written contract with a cap of $5,000 would still be operative, and the plaintiff would have been paid in full; and (4) both parties breached the accord because the plaintiff attempted to charge for the paving, and the defendants did not pay the balance of $760 that they owed to the plaintiff. The referee recommended that judgment enter in favor of the defendants, discharging the lien filed by the plaintiff.

The plaintiff, pursuant to Practice Book § 438, moved to correct the referee's report. The plaintiff sought the addition of the following corrections to the report: (1) the parties had mutually agreed upon a new contract price calling for an additional payment of $5,760, and the plaintiff was therefore owed $760, because the defendants only sent a partial payment of $5,000 to the plaintiff on June 8, 1995; (2) the June 8, 1995 check did not bear any endorsement that it constituted payment in full; and (3) there was no meeting of the minds and, therefore, no accord and satisfaction, because the plaintiff did not accept the $5,000 check of June 8, 1995, with the understanding that it constituted a valid accord.

In response to the motion to correct filed by the plaintiff, the attorney trial referee declined to change his recommendation. The referee noted specifically that: (1) by cashing the check for $5,000 sent on June 8, 1995, the plaintiff entered into a valid and binding accord and satisfaction based on mutual assent; (2) the plaintiff breached the accord by attempting to collect separately for the paving, when that work had been included in the check sent to the plaintiff by the defendants, but also that the defendants breached the accord by not paying the balance of $760; and (3) alternatively, there was no meeting of the minds CT Page 3847 and therefore the original agreement and contract cap of $5,000 were operative.

The plaintiff did not file any exceptions to the report as authorized by Practice Book § 439. The plaintiff did, however, file objections to the report pursuant to Practice Book § 440. In these objections, the plaintiff contends that: (1) there was no accord and satisfaction because there was no meeting of the minds; and (2) even if there had been an accord and satisfaction, it was for $5,760, not $5,000, and therefore the defendants owe the plaintiff $760.

As to this court's scope of review of an attorney trial referee's report regarding the facts of a given case, the Supreme Court reiterated in Elgar v. Elgar, 238 Conn. 839, 848-49,679 A.2d 937 (1996), that "[a] reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court . . . or the Superior Court reviewing the findings of . . . attorney trial referees. See Practice Book § 443 . . . . The factual findings of a [trial referee] on any issue are reversible only if they are clearly erroneous . . . . . [A reviewing court] cannot retry the facts or pass upon the credibility of the witnesses . . . . . A finding of fact is clearly erroneous when there is no evidence in the record to support it . . . or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed." (Citations omitted; internal quotation marks omitted.) See also Romano v. Derby, 42 Conn. App. 624, 626,681 A.2d 387 (1996) ("The trial court, as the reviewing authority, may render whatever judgment appropriately follows, as a matter of law, from the facts found by the attorney trial referee.")

Thus, according to Elgar v. Elgar, supra, 238 Conn. 845, this court has two tasks to perform in reviewing an attorney trial referee's report.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dills v. Town of Enfield
557 A.2d 517 (Supreme Court of Connecticut, 1989)
Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership
674 A.2d 1313 (Supreme Court of Connecticut, 1996)
Elgar v. Elgar
679 A.2d 937 (Supreme Court of Connecticut, 1996)
Blessings Corp. v. Carolton Chronic & Convalescent Hospital, Inc.
508 A.2d 829 (Connecticut Appellate Court, 1986)
State Bank v. New Dimension Homes of Connecticut, Inc.
661 A.2d 119 (Connecticut Appellate Court, 1995)
Romano v. City of Derby
681 A.2d 387 (Connecticut Appellate Court, 1996)
Iroquois Gas Transmission System v. Mileski
682 A.2d 140 (Connecticut Appellate Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Conn. Super. Ct. 3844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grasso-paving-inc-v-ascot-dev-corp-no-cv-95-0146827-apr-16-1997-connsuperct-1997.