Graham Contracting, Inc. v. Flagler County

444 So. 2d 971, 1983 Fla. App. LEXIS 25170
CourtDistrict Court of Appeal of Florida
DecidedDecember 15, 1983
Docket83-1256
StatusPublished
Cited by17 cases

This text of 444 So. 2d 971 (Graham Contracting, Inc. v. Flagler County) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graham Contracting, Inc. v. Flagler County, 444 So. 2d 971, 1983 Fla. App. LEXIS 25170 (Fla. Ct. App. 1983).

Opinion

444 So.2d 971 (1983)

GRAHAM CONTRACTING, INC., a Florida Corporation, Petitioner,
v.
FLAGLER COUNTY, Respondent.

No. 83-1256.

District Court of Appeal of Florida, Fifth District.

December 15, 1983.
Rehearing Denied February 9, 1984.

Ernest H. Eubanks of Pitts, Eubanks & Ross, P.A., Orlando, for petitioner.

Noah C. McKinnon, Jr., Bunnell, and Cynthia S. Tunnicliff of Carlton, Fields, Ward, Emmanuel, Smith & Cutler, P.A., Tallahassee, for respondent.

COWART, Judge.

This case involves a contractual right to have disputes arising out of the contract resolved by arbitration and whether that right has been impliedly waived under the circumstances.

Petitioner, Graham Contracting, contracted with Flagler County to build an addition to the Flagler County Courthouse. The contract required arbitration of "all claims, disputes and other matters in question between the parties ... arising out of or relating to this agreement or the breach thereof." The contract also required that a demand for arbitration be made "within a reasonable time after the claim, dispute or other matter in question has arisen."

Graham Contracting commenced work in May of 1982. On June 22, 1982, while pilings were being installed to support the addition to the courthouse, the foundation of the existing courthouse shifted, damaging the old courthouse. Flagler County instructed Graham Contracting to cease work until further notice. On December 22, 1982, Flagler County served a complaint on Graham Contracting. On January 11, 1983, Graham Contracting served a motion to dismiss the complaint for failure to state a cause of action. On March 31, 1983, a meeting between Graham Contracting and Flagler County was held to discuss completion of construction. Graham Contracting was advised that Flagler County would request completion of construction. On April 13, 1983, Graham Contracting submitted documentation of additional costs that it would incur due to the delay in construction caused by the county instructing Graham Contracting to cease work in June of 1982. Flagler County refused to pay these additional costs and Graham Contracting served a demand for arbitration pursuant to the contract. On April 29, *972 1983, Graham Contracting filed a motion in the trial court to compel arbitration. On May 16, 1983, a hearing was held on Graham Contracting's motion to compel arbitration and on its earlier filed motion to dismiss for failure to state a cause of action. The trial court dismissed Flagler County's first complaint but denied Graham Contracting's motion to compel arbitration. Graham Contracting then filed this petition for writ of certiorari.[1] We grant the petition.

In the instant case, the contract required that the demand for arbitration be made "within a reasonable time after the claim, dispute or other matter in question has arisen." The trial court found that a dispute became apparent on June 22, 1982, when the foundation of the old courthouse shifted and Graham Contracting was told to cease work until further notice. The court then found that Graham Contracting's demand for arbitration made ten months later was not made within a reasonable period of time, relying on Lyons v. Krathen, 368 So.2d 906 (Fla. 3d DCA 1979), cert. den., 378 So.2d 346 (Fla. 1979), and Bickerstaff v. Frazier, 232 So.2d 190 (Fla. 1st DCA 1970), cert. dismissed, 238 So.2d 110 (Fla. 1970). In Lyons v. Krathen a written demand was made on a contractor to correct certain defects. The contractor waited nine months after the demand before filing a motion to compel arbitration. In Bickerstaff v. Frazier, the owners were put on notice of a dispute as to the amount due the contractor for final payment under the contract when the contractor served and recorded his claim of lien for labor and materials furnished under the construction contract. The court held the owners waived their right to arbitrate by waiting until four months later to demand arbitration. By contrast, in the instant case no claim was made, and no dispute arose, on June 22, 1982, when Graham Contracting was told to cease work until further notice. The contract does not require the demand for arbitration be made merely because it has become apparent that there is a potential dispute between the parties. The dispute between the parties first crystallized on December 22, 1982, when Flagler County served its complaint on Graham Contracting. While Graham Contracting's initial demand for arbitration was not filed until April 13, 1983, nearly four months later, we do not believe that four months is, as a matter of law, an unreasonable delay. We note that the third and fourth district courts of appeal have adopted the view that the issue of whether a demand for arbitration is timely according to the meaning of the contract is a question to be decided in arbitration. See Federated Department Stores, Inc. v. Pavarini Construction Company, Inc., 425 So.2d 1212 (Fla. 4th DCA 1983); Rinker Portland Cement Corp. v. Seidel, 414 So.2d 629 (Fla. 3d DCA 1982). We believe that a waiver of the right to arbitrate should not be implied from mere inaction unless the delay has given the party seeking arbitration an undue advantage or has resulted in prejudice to another. See Carcich v. Rederi A/B Nordie, 389 F.2d 692 (2d Cir.1968).

Respondent also contends that Graham Contracting waived its right to arbitration by filing its motion to dismiss Flagler County's complaint for failure to state a cause of action. In R.W. Roberts Construction Company v. Masters and Company, 403 So.2d 1114 (Fla. 5th DCA 1981), this court held that a defendant had waived its right to arbitrate by filing a motion to dismiss and to transfer the cause of action based on a contractual venue clause.

Petitioner's motion to dismiss and transfer the action is a contention that the proceeding is in the court of the wrong county, not that it doesn't belong in court at all. This position seems totally inconsistent with petitioner's later assertion that no court was the proper forum, because arbitration was appropriate.
Id. at 1115.

*973 See also, King v. Thompson and McKinnon, Auchinschloss, Kohlmeyer, Inc., 352 So.2d 1235 (Fla. 4th DCA 1977) (arbitration waived by filing answer and cross-claim, arbitration issue not raised until interrogatories were served); Gettles v. Commercial Bank at Winter Park, 276 So.2d 837 (Fla. 4th DCA 1973) (arbitration waived where plaintiff filed suit, defendant counter sued, plaintiff filed motion to dismiss counterclaim and one week later plaintiff filed demand for arbitration); Ojus Industries, Inc. v. Mann, 221 So.2d 780 (Fla. 3d DCA 1969); Mike Bradford and Company, Inc. v. Gulf States Steel Company, Inc., 184 So.2d 911 (Fla. 3d DCA 1966) (right to arbitrate waived where steel company, with full knowledge of its rights, answered complaint without raising issue of arbitration, counterclaimed upon the same contract, allowed cause to proceed for five and one-half months and allowed jury to be empanelled before demanding arbitration). In none of the above cases has it been held that the filing of a motion to dismiss for failure to state a cause of action, without more, constituted a waiver of the right to arbitrate.[2] The failure of a complaint to allege occurrence of a condition precedent of arbitration could be argued as the reason a complaint fails to state a cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Truly Nolen of America, Inc. v. King Cole Condominium Association, Inc.
143 So. 3d 1015 (District Court of Appeal of Florida, 2014)
Houchins v. King Motor Co.
906 So. 2d 325 (District Court of Appeal of Florida, 2005)
City of Crystal River v. United Brotherhood of Carpenters
884 So. 2d 440 (District Court of Appeal of Florida, 2004)
Morrell v. Wayne Frier Manufactured Home Center
834 So. 2d 395 (District Court of Appeal of Florida, 2003)
Hirschfeld v. Crescent Heights, X, Inc.
707 So. 2d 955 (District Court of Appeal of Florida, 1998)
Duckworth v. Plant
697 So. 2d 1257 (District Court of Appeal of Florida, 1997)
Beverly Hills v. George Wimpey of Fla., Inc.
661 So. 2d 969 (District Court of Appeal of Florida, 1995)
Hardin Intern., Inc. v. Firepak, Inc.
567 So. 2d 1019 (District Court of Appeal of Florida, 1990)
Rohlfing v. Tomorrow Realty & Auction Co., Inc.
528 So. 2d 463 (District Court of Appeal of Florida, 1988)
Finn v. Prudential-Bache Securities, Inc.
523 So. 2d 617 (District Court of Appeal of Florida, 1988)
Weiss v. Ins. Co. of State of Pa.
497 So. 2d 285 (District Court of Appeal of Florida, 1986)
Wieneke v. Raymond, James & Assoc.
495 So. 2d 869 (District Court of Appeal of Florida, 1986)
School Board of Orange County v. Southeast Roofing & Sheet Metal, Inc.
489 So. 2d 886 (District Court of Appeal of Florida, 1986)
PRUDENTIAL-BACHE SECURITIES v. Pauler
488 So. 2d 894 (District Court of Appeal of Florida, 1986)
Old Dominion Ins. v. DEPENDABLE REINS.
472 So. 2d 1365 (District Court of Appeal of Florida, 1985)
Graham Contracting, Inc. v. Flagler County
458 So. 2d 418 (District Court of Appeal of Florida, 1984)
MERRILL LYNCH, PIERCE v. Melamed
453 So. 2d 858 (District Court of Appeal of Florida, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
444 So. 2d 971, 1983 Fla. App. LEXIS 25170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graham-contracting-inc-v-flagler-county-fladistctapp-1983.