Graef Construction Incorported v. LS Black Constructors-Loeffel Construction JV

District Court, D. Arizona·Decided September 14, 2022·No. 2:20-cv-01585·Unknown

Opinion

WO

Graef Construction Incorporated, No. CV-20-01585-PHX-JJT

Plaintiff, ORDER

v.

LS Black-Loeffel Civil Constructors JV LP, et al., Defendants. At issue is Defendants LS Black-Loeffel Contractors JV (the “JV”), LS Black Contractors, Inc. (“LS BLACK”), Loeffel Engstrand Corporation d/b/a Loeffel Construction (“LOEFFEL”), and Federal Insurance Company’s (“FIC”) (hereinafter referred to collectively as “Defendant”) Motion to Confirm Arbitration Award (Doc. 37), to which Plaintiff Graef Construction Incorporated (“Graef”) filed a Response and Cross- Motion/Petition to Vacate Arbitration Award (Doc. 50). Defendant filed a Reply in Support of its Motion to Confirm Arbitration Award (Doc. 56) and a Response to Plaintiff’s Cross- Motion (Doc. 58), to which Plaintiff replied (Doc. 59). Plaintiff also filed a Request/Motion for Scheduling Conference Pursuant to Rule 16(b) (Doc. 52), to which Defendant responded (Doc. 53), and Plaintiff replied (Doc. 54). The Court finds these matters suitable for resolution without oral argument. See LRCiv 7.2(f). For the reasons set forth below, the Court confirms the arbitration award, and denies as moot Plaintiff’s Request for Scheduling Conference. This case arises out of a contract dispute. Defendant was the prime contractor on a design/build contract with the U.S. Army Corps of Engineers (“USACE”) for a new Army Reserve training center (the “Project”) near Luke Air Force Base. (Doc. 56 at 2.) Plaintiff was awarded the subcontract for the grading, earthwork, and utilities for the Project. (Doc. 56 at 2.) Defendant contends that despite the fact that a sewage lift station was specified in “every iteration” of the design documents provided to Plaintiff, Plaintiff claimed that the lift station was not included in the subcontract, and demanded a change order to increase the price of the contract before it would perform the work. (Doc. 56 at 2.) Plaintiff contends that the sewage lift station was not buildable as designed, so a change order was required for the work on the lift station to commence. (Doc. 59 at 2-3.) Defendant refused to give Plaintiff a change order, so Plaintiff stopped all work, left the site, and refused to return to the project. (Doc. 56 at 2.) Plaintiff maintains that it “did not stop all work,” but was “prevented from continuing” work. (Doc. 59 at 3.) In August 2020, Plaintiff brought suit in this Court alleging that it was not paid for the work it performed, and seeking damages in the amount of $563,985.79 plus interest, attorneys’ fees, and costs. (See generally Doc. 1, Compl., amended at Doc. 11, First Amended Complaint (“FAC”).) In November 2020, the parties stipulated to stay the litigation pending arbitration. (Doc. 18.) The parties participated in arbitration through the American Arbitration Association (“AAA”) to resolve the dispute. (Doc. 50 at 2.) In arbitration, Defendant sought compensation for the cost of completing Plaintiff’s unfinished work and fixing defects in the work Plaintiff had completed. (Doc. 56 at 3.) Plaintiff counterclaimed to recover the remaining balance on its contract, including for work not performed and unearned profits. (Doc. 56 at 3.) In his final award (“Award”), issued January 27, 2022, Arbitrator Mark Zukowski (“Arbitrator Zukowski”) issued a decision in favor of Defendant and rejected all of Plaintiff’s claims. (See Doc. 50, Ex. 4.) In February 2022, Defendants filed a Motion to Confirm Arbitration Award (Doc. 37), but Plaintiff argues that the Award should be vacated pursuant to 9 U.S.C. § 10 and legal precedent. (Doc. 50 at 2.) Federal court review of arbitration awards is limited, and courts are permitted to conduct only a “restricted review” of arbitral decisions. See, e.g., Rostad & Rostad Corp. v. Investment Mgmt. & Research Inc., 923 F.2d 694, 697 (9th Cir. 1991) (citation omitted). The Ninth Circuit has consistently held that sections 10 and 11 of the Federal Arbitration Act (“FAA”) provide the exclusive means by which an arbitration award may be vacated or modified. Biller v. Toyota Motor Corp., 668 F.3d 655, 664 (9th Cir. 2012). A district court may vacate an arbitration award only: (1) where the award was procured by corruption, fraud or undue means; (2) where there was evidence of partiality or corruption on the part of the arbitrators; (3) where the arbitrators were guilty of misbehavior by which the rights of any party have been prejudiced; or (4) where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made. 9 U.S.C. § 10(a)(1)-(4). Plaintiff asks the Court to vacate the arbitration award under section 10 of the FAA. Relying on the Sixth Circuit’s standard for vacatur of an arbitration award, Plaintiff alleges that Arbitrator Zukowski’s conclusion conflicts with the express terms of the Federal Prompt Payment Act (“FPPA”) language in the parties’ contract and payment certification, imposes additional requirements, and is not rationally supported or derived from the agreement. (Doc. 50 at 12.) See Beacon Journal Pub. Co. v. Akron News. Guild, 114 F.3d 596, 600 (6th Cir. 1997). In response, Defendant begins by noting that the Ninth Circuit’s standard for overturning an arbitrator’s decision is “extremely high.” (Doc. 56 at 4-5.) Courts applying section 10 of the FAA have found that an arbitration “award may not be vacated even where there is a clearly erroneous finding of fact.” Bosack v. Soward, 586 F.3d 1096, 1106 (9th Cir. 2009) (citation omitted). Rather, arbitrators exceed their powers under the FAA when “the award is completely irrational, or exhibits a manifest disregard of law.” Biller, 668 F.3d at 665. Because this Court is located in the Ninth Circuit, not the Sixth Circuit, the Court applies Ninth Circuit law in its analysis of Plaintiff’s argument. Plaintiff’s first main argument is somewhat grounded in Ninth Circuit precedent. In short, the crux of Plaintiff’s argument is that Arbitrator Zukowski “recognized the applicable federal law . . . and then ignored it entirely.” (Doc. 50 at 6.) To support its argument that Arbitrator Zukowski ignored the applicable law, Plaintiff contends that he recognized that the elements of the FPPA regarding timely payment applied, and acknowledged that Defendant’s payments to Plaintiff were late pursuant to the FPPA’s time frame. (Doc. 50 at 6-7, Ex. 4.) Plaintiff also takes issue with Arbitrator Zukowski’s finding that Plaintiff’s material breach took place prior to the payments being due. (Docs. 50 at 7; 59 at 6.) Plaintiff explains that Arbitrator Zukowski’s finding is “completely irrational” and exhibits a manifest disregard for the law because the late-paid pay applications were for May and June, and Defendant did not allege a breach by Plaintiff until mid-August, nor was a Notice of Default sent to Plaintiff notifying it of any breach until September 11, 2019. (Doc. 50 at 7, 10, Ex. 7.) Plaintiff also alleges that, pursuant to the contract between the parties, pay applications were required to be submitted monthly, and Arbitrator Zukowski failed to acknowledge the monthly billing requirement. (Doc. 59 at 5-6.) Further, Plaintiff claims that Arbitrator Zukowski failed to “define the [material] breach or state the date of occurrence.” (Doc. 50 at 9.) According to Plaintiff, the evidence presented clearly showed that Defendant was withholding payment—and thus in material breach of the parties’ contract—prior to Plaintiff’s termination. (Doc. 50 at 11.) Defendant maintains that Arbitrator Zukowski’s award was neither irrational nor i

Free access — add to your briefcase to read the full text and ask questions with AI

Graef Construction Incorported v. LS Black Constructors-Loeffel Construction JV, (D. Ariz. 2022).

Graef Construction Incorported v. LS Black Constructors-Loeffel Construction JV (Graef Construction Incorported v. LS Black Constructors-Loeffel Construction JV) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lagstein v. CERTAIN UNDERWRITERS, LLOYD'S, LONDON
607 F.3d 634 (Ninth Circuit, 2010)
See More Light Investments v. Morgan Stanley Dw Inc.
415 F. App'x 1 (Ninth Circuit, 2011)
Biller v. Toyota Motor Corp.
668 F.3d 655 (Ninth Circuit, 2012)
Foundation Development Corp. v. Loehmann's, Inc.
788 P.2d 1189 (Arizona Supreme Court, 1990)
In Re Bosack v. Soward
586 F.3d 1096 (Ninth Circuit, 2009)
Penn Allegheny Coal Co. v. Williams
114 F.3d 22 (Third Circuit, 1997)
Murphy Farrell Development, LLLP v. Sourant
272 P.3d 355 (Court of Appeals of Arizona, 2012)