Good v. Johnson

38 Colo. 440
CourtSupreme Court of Colorado
DecidedSeptember 15, 1906
DocketNo. 4948
StatusPublished
Cited by15 cases

This text of 38 Colo. 440 (Good v. Johnson) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Good v. Johnson, 38 Colo. 440 (Colo. 1906).

Opinion

Mr. Justice Campbell

delivered'the opinion of the court:

Action for damages for personal injuries. The Denver and Northwestern Pacific Railroad Company contracted with The Colorado and Utah Construction Company for the building of the former’s roadbed. The construction company let a contract for grading a part of the road covered by its contract to George S. Good & Co., and the latter, in turn, sublet a portion of their work to Swanson, Johnson & Co. The plaintiff, Gust Johnson, was employed by Charles Swanson, a member of the firm of Swanson, Johnson & Co., as a common laborer. Johnson, another member of the firm who was acting- at the time as its foreman, ordered plaintiff to do some work in a tunnel which was then being driven, in complying with which plaintiff was injured, as he says, through the foreman’s negligence.

Plaintiff seeks to hold Good & Co. responsible therefor, first, because Johnson was their servant and foreman — the relation of Swanson, Johnson & Co. to Good & Co-, being, as it is said, not that of independent contractors, but merely that of servants, in the sense that the master is responsible for their negligence; second, if the true relation between Good & Co. and Swanson, Johnson & Co. is not that of master and servant, nevertheless because of certain conduct of Good & Co. they are estopped now to deny that such was the relation. From the judgment which the plaintiff recovered against Good & Co., they have appealed.

[443]*443The trial court committed grave and prejudicial error, necessitating a reversal, in its instructions to the jury with respect to the relation between defendants and Swanson, Johnson & Co. Therefore, questions argued by counsel relating to the negligence of defendants and contributory negligence of the plaintiff are eliminated from the discussion.

1. The contract, and the only contract, between Good & Co. and Swanson, Johnson & Co. is in writing. Therein the former are called contractors, the latter subcontractors, and, for convenience, they will be so designated in the opinion. There is not a particle of evidence which tends to show bad faith on the part of any of the parties to the contract in entering into it. The work done by the subcontractors was done under the written agreement, and not otherwise. There is no evidence that the contractors assumed to exercise, or, in fact, exercised, any control whatever over the subcontractors other than, or different from, that which any owner or principal contractor retains over the one who does work under an agreement that leaves him entirely free as to the manner or mode in which that work shall be done, though requiring it to be done according to plans and specifications agreed on beforehand.

The contract being in writing, the relation which it created between the parties thereto is exclusively within the province of the court to determine, and should not have been submitted to the jury. In instruction No. 5, the court told the jury, if they believed that the contract between the parties was made in good faith, and that plaintiff was employed by Swanson, Johnson & Co. as subcontractors, then the defendants would not be liable. The court should not have submitted to the jury the question of good faith. That element was not involved in the case, for there was no evidence whatever tending to show bad faith. [444]*444In this particular the court should have instructed the jury that the contract, on its face, inasmuch as it was unquestionably executed by the parties in good faith, did not, considered in connection with the surrounding circumstances, constitute Swanson, Johnson & Co>. servants of the contractors.

The Colorado and Utah Construction Company was the original or first contractor to which was let all, or a large part, of the construction work for the railroad company. It is fair to assume that the entire work of grading and preparing the roadbed for rails was to be done in accordance with plans and specifications of the railroad company itself, to which those actually doing the work must conform. And it is only fair to say, what sufficiently appears from, the record, that, in the written agreement between Good & Co. and Swanson, Johnson & Co., the various provisions which plaintiff here relies on as constituting the relation between them one of agency, or that of master and servant, are substantially the same which are found in the contract that defines the relation of the construction company and Good & Co., and were put in these various construction contracts to secure the general result which the railroad company sought to accomplish, viz., to have a satisfactory roadbed. In the light of these considerations, and from, the language of these particular clauses, interpreted in the light of the entire contract including the plans and specifications which are a part thereof, let us proceed to an examination of these provisions of the contract which plaintiff says give rise to the relation of master and servant between the contractors and the subcontractors. The clauses are 3, 5, 9, 10, 15, 16-|, 21 and 26.

The 3rd clause says that the work is to be performed under the direction and supervision of the engineer of the construction company, who is given [445]*445power to condemn and reject any or all work or material which does not conform to the agreement, and defective work and material is to he remedied by the subcontractors at their cost and expense to the satisfaction of the engineer.

The 5th clause authorizes this engineer to discharge any employee of the subcontractors whenever, in his opinion, the interests of the construction company or the contractors demand the same.

The 9th clause authorizes the engineer, if he thinks the work is not progressing rapidly enough to secure its completion within the time limited by the contract, to notify the subcontractors to increase the force sufficiently to comply therewith, and, if the subcontractors fail within a certain time to comply with this ■ notice, such failure shall he considered as a breach and forfeiture of the agreement, and the contractors may declare the contract forfeited and enter upon and take possession of the work, and re-let it, or perform the work themselves.

The 10th clause is that the contractor may reduce the force engaged upon the work, or suspend it for any length of time, or may discontinue the work and cancel the contract by paying the subcontractor all that is coming to him up to the time of suspension.

The 15th clause gives the engineer power to direct the application of forces to any portion of the work which, in his judgment, requires it.

Clause 16J requires the contractor to furnish the subcontractors, free of charge, all tools and track and blacksmith outfit, and keep the same in repair.

The 21st clause requires the subcontractor to save harmless the contractor from all damages that may he caused to third persons during the prosecution of the work.

The 26th gives the option to the contractors, in order to protect themselves against liens, to pay di[446]*446rectly to the laborers or other persons employed by the subcontractors the wages which they have earned, and to charge such payments against the contractors as so much paid on the contract.

In our judgment, neither of these clauses, nor all combined, have the effect which the plaintiff contends for them, as a review of some of the. leading authorities will disclose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowser v. State Industrial Accident Commission
185 P.2d 891 (Oregon Supreme Court, 1947)
Moore & Chicago Mill & Lumber Co. v. Phillips
120 S.W.2d 722 (Supreme Court of Arkansas, 1938)
Prouty Lumber & Box Co. v. McGuirk
68 P.2d 473 (Oregon Supreme Court, 1937)
Pribulo v. Chiarelli
157 A. 420 (Supreme Court of Connecticut, 1931)
North Chesapeake Beach Land & Improvement Co. v. Cochran
144 A. 505 (Court of Appeals of Maryland, 1929)
Medford Lumber Co. v. Industrial Commission
221 N.W. 390 (Wisconsin Supreme Court, 1928)
Helzer v. Wax
272 P. 556 (Oregon Supreme Court, 1928)
Kaw Boiler Works v. Frymyer
1924 OK 469 (Supreme Court of Oklahoma, 1924)
Swansea Lease, Inc. v. Molloy
183 P. 740 (Arizona Supreme Court, 1919)
Western Colorado Power Co. v. Gibson Lumber & Coal Co.
176 P. 318 (Supreme Court of Colorado, 1918)
Scales v. First State Bank
172 P. 499 (Oregon Supreme Court, 1918)
Zeitlow v. Smock
117 N.E. 665 (Indiana Court of Appeals, 1917)
De Sandro v. Missoula Light & Water Co.
136 P. 711 (Montana Supreme Court, 1913)
Bokoshe Smokeless Coal Co. v. Morehead
1912 OK 329 (Supreme Court of Oklahoma, 1912)
Larsen v. Home Telephone Co.
129 N.W. 894 (Michigan Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
38 Colo. 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/good-v-johnson-colo-1906.