Callan v. Bull

45 P. 1017, 113 Cal. 593, 1896 Cal. LEXIS 830
CourtCalifornia Supreme Court
DecidedAugust 3, 1896
DocketS. F. No. 68
StatusPublished
Cited by61 cases

This text of 45 P. 1017 (Callan v. Bull) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Callan v. Bull, 45 P. 1017, 113 Cal. 593, 1896 Cal. LEXIS 830 (Cal. 1896).

Opinion

Harrison, J.

The plaintiff brought this action to recover damages for an injury sustained by him while in the employ of the defendant. The defendant in December, 1892, had entered into a contract with Major W. H. Heuer, of the corps of engineers, acting on behalf of the United States, for constructing a breakwater or jetty on each side of the entrance to Humboldt Bay, and in April, 1893, had hired the plaintiff as a laborer to work on the jetty. In constructing the jetty, trestle-work was built out from the shore, on which was laid a double railroad track on which to carry rock and other material with which the jetty was to be formed. This trestlework was constructed of bents of piling sixteen feet apart, each bent consisting of four piles upon which a cap was fastened, and across these caps were laid stringers, upon which were placed the rails on which the cars were to run. Brush mattress work was constructed about the trestlework and sunk to the bottom of the sea, and on this brush work was deposited rock, thus forming a rip-rap embankment to constitute the jetty. The mode of laying the brush mattress was as follows: After some of the bents had been placed in position and the track laid thereon, a grillage of poles the width of the jetty, and varying in length from one to four bents, was laid beneath the bents, and bundles of brush placed thereon in alternate layers to the thickness of nearly four feet, on the top of which was laid another grillage of poles, and after these grillages had been secured the whole was dropped to the bottom and the rock afterward dumped thereon. During the construction of a mat it was suspended at each end by sling-poles hung from the bents, and on these sling-poles were laid the poles forming the bottom grillage of the mattress. After the north jetty had been built for the distance of [596]*596about a quarter of a mile from the shore) the defendant commenced to construct a spur on the outer side for its protection, and, for this purpose, placed a bent consisting of two piles and a cap, parallel to the main jetty, and about sixteen feet therefrom. These piles were driven sixteen feet apart, and on them was placed a cap thirty-two feet long. The defendant was directed to construct a mattress at this point twenty-four feet wide, measured in a direction parallel to the trestle, and as long from " the trestle as it was-practicable to make it from a single bent, the inner edge of the mattress being twelve feet inside of the spur-bent. For the purpose of sustaining this mat during its construction, two sling-poles about forty feet long were slung about eight feet under the cap and outside of the piles, the inner ends running in and resting upon the rock of the jetty already built and rued to the caps of the main trestle, and the outer ends suspended from the projecting ends' of the cap on the spur-bent. Two stringers thirty-two feet in length were also laid across the cap of the spur-bent, one end of which was fastened to the end of the caps of the main trestle, and the other projected out over the spur-cap and sixteen feet beyond it. The northernmost of these stringers was placed with its center eighteen inches outside of the center of the pile, and to these stringers the sling poles were also suspended by steel cables at a point near their outer end. On August 12th, the next day after these stringers had been placed in position, . the plaintiff, with other laborers,-was engaged in laying the mat with the bundles of brush, and, after a few loads of brush had been placed thereon, the cap broke near its northern end, and a portion of that end of the cap fell upon the mat and struck the plaintiff, seriously injuring him. The jury rendered a verdict in favor of the plaintiff, and from the judgment entered thereon, and from an order denying a new trial, the defendant has appealed.

There was conflicting evidence upon the character of the timber, and also upon the amount of weight which [597]*597it bore, as well as the support which a sound stick of its size would bear; but, in view of the verdict of the jury, we must assume that the evidence showed that the weight of the mattress at the time it fell was too great for the sustaining force of the cap, either from its in^ herent defect or from the manner in which it was supported, and that there was negligence, either in the (Construction of the bent or in the mode in which the stringers were placed.

The contract of the appellant contained the following provision: “ The work is to be executed under the supervision of the engineer officer in charge, or his agent, who will prescribe the order in which the materials are to be placed, and who will give the lines and levels to be used. No material, of any description, will be placed in the works without his knowledge and instructions at the time, and any materials so placed will not be paid for. The contractor must keep upon the work at all times responsible agents, who shall have full authority to carry out the instructions of the agent of the United States. The contractor shall remove from the work, at the request of the engineer officer in charge, any person who is not acceptable to the agents of the United States”; and also a provision that “all material, supervision, and labor furnished by the contractor will be subject to the approval of the engineer officer in charge.” From these provisions, it is contended by the appellant that he was acting under the directions of the officers of the United States, and was but the agent or servant of the United States in the performance of the contract; that by the terms of the contract the United States reserved such control over the construction of the jetty as to deprive him of the power to select the mode of construction, or the laborers whom he would employ, and that, consequently,he is not liable for any injury resulting from following the directions of these officers, or for any fault or negligence in the manner of doing the work; and, further, that if there was any negligence in the performance of the work, which resulted in the in[598]*598jury sustained by the plaintiff, it was the negligence of the fellow-servants of the plaintiff, for which he cannot be held responsible. On the other hand, the plaintiff contends that the defendant was bound to furnish |o him a safe place in which to work, and safe appliances with which to, do his work, and that he could not divest himself of this responsibility by intrusting to others, whether they be fellow-servants or not, the care of providing such appliances and place of work.

The master’s liability for the negligence of his servant rests upon his right to select the servant and to control his work, but, when this selection and control rests in another, he is freed from such liability. The same principles govern the liability of a contractor for an injury resulting from the use of defective materials in his work. He can be held liable only when he has the right of selecting the materials. If he is to perform the contract with only such materials as may have been previously selected and furnished by his employer, he cannot be held liable for any defect in such materials. These principles are, however, subject to the rule that this right of selection and control is to be determined by the terms of the contract of employment, and that, unless by the contract this right is reserved to the employer, the contractor will be presumed to have the right of selection and control of all whom he employs. It is not enough that while performing the contract he may ask for and act upon the advice of his employer, or listen to his suggestions as to the mode of doing the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandoval v. Qualcomm Incorporated
California Supreme Court, 2021
Pylon, Inc. v. Olympic Insurance Co.
271 Cal. App. 2d 643 (California Court of Appeal, 1969)
Estate of Rowley
257 Cal. App. 2d 324 (California Court of Appeal, 1967)
Safeway Stores, Inc. v. Massachusetts Bonding & Insurance
202 Cal. App. 2d 99 (California Court of Appeal, 1962)
Bedford v. Bechtel Corp.
342 P.2d 495 (California Court of Appeal, 1959)
Johns v. Ward
339 P.2d 926 (California Court of Appeal, 1959)
McDonald v. Shell Oil Co.
285 P.2d 902 (California Supreme Court, 1955)
Burch v. Valley Motor Lines, Inc.
179 P.2d 47 (California Court of Appeal, 1947)
Day v. Western Loan & Building Co.
108 P.2d 702 (California Court of Appeal, 1940)
Singer Sewing Machine Co. v. Odom
1935 OK 610 (Supreme Court of Oklahoma, 1935)
Pribulo v. Chiarelli
157 A. 420 (Supreme Court of Connecticut, 1931)
Grant v. Nihill
210 P. 914 (Montana Supreme Court, 1922)
Barton v. Studebaker Corp. of America
189 P. 1025 (California Court of Appeal, 1920)
Buckingham v. Commary-Peterson Co.
178 P. 318 (California Court of Appeal, 1918)
Mickel v. Althouse
176 P. 51 (California Court of Appeal, 1918)
E. I. DuPont de Nemours & Co. v. Hipp
96 S.E. 280 (Supreme Court of Virginia, 1918)
Albert v. McKay & Co.
163 P. 666 (California Supreme Court, 1917)
Fahey v. Panama-California Exposition
159 P. 1045 (California Supreme Court, 1916)
Fonts v. Southern Pacific Co.
159 P. 215 (California Court of Appeal, 1916)
Zelavin v. Tonopah Belmont Development Co.
149 P. 188 (Nevada Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
45 P. 1017, 113 Cal. 593, 1896 Cal. LEXIS 830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/callan-v-bull-cal-1896.