[26]*26Per Curiam.
Petitioner’s husband, Frank J. Gondeck, was killed as a result of a jeep accident on San Salvador Island outside a defense base at which he was employed. The accident took place in the evening as Gondeck and four others were returning from a nearby town. The Deputy Commissioner of the Bureau of Employees’ Compensation, United States Department of Labor, awarded death benefits to petitioner in accordance with the terms of the Longshoremen’s and Harbor Workers’ Compensation Act, 44 Stat. 1424, as amended, 33 U. S. C. § 901 et seq. (1958 ed.), as extended by the Defense Base Act, 55 Stat. 622, as amended, 42 U. S. C. § 1651 et seq. (1958 ed.). In support of the award, the Deputy Commissioner found, among other things, that, although Gondeck had completed his day’s work, he was subject to call for emergencies while off duty and was returning from reasonable recreation when the accident occurred. The District Court set aside the Deputy Commissioner’s order, and the Court of Appeals for the Fifth Circuit affirmed. United States v. Pan American World Airways, Inc., 299 F. 2d 74. The Court of Appeals acknowledged that Gondeck was subject to call, id., at 75, but found no benefit to the employer in Gondeck’s trip, and “no evidence that furnishes a link by which the activity in which Gondeck was engaged was related to his employment.” Id., at 77.
On June 11, 1962, we denied certiorari. 370 U. S. 918. On October 8, 1962, we denied a petition for rehearing. 371 U. S. 856. We are now apprised, however, of “intervening circumstances of substantial . . . effect,”
In O’Keeffe we made clear that the determinations of the Deputy Commissioner are subject only to limited judicial review, and we reaffirmed the Brown-Pacific-Maxon holding that the Deputy Commissioner need not find a causal relation between the nature of the victim’s employment and the accident, nor that the victim was engaged in activity of benefit to the employer at the time of his injury or death. No more is required than that the obligations or conditions of employment create the “zone of special danger” out of which the injury or death arose. Since the Court of Appeals for the Fifth Circuit misinterpreted the Brown-Pacific-Maxon standard in this case, and since, of those eligible for compensation from the accident, this petitioner stands alone in not receiving it, “the interests of justice would make unfair the strict application of our rules.” United States v. Ohio Power Co., supra, at 99.
[28]*28We therefore grant the motion for leave to file the petition for rehearing, grant the petition for rehearing, vacate the order denying certiorari, grant the petition for certio-rari, and reverse the judgment of the Court of Appeals.
It is so ordered.
Mr. Justice Fortas took no part in the consideration or decision of this case.
Mr. Justice Clark,
joining in the judgment.
I fully agree with my Brother Harlan “that litigation must at some point come to an end” and “that this decision holds seeds of mischief for the future orderly administration of justice . . . .” But with Cahill v. New York, N. H. & H. R. Co., 351 U. S. 183 (1956), on our books, no other conclusion can be reached.
Up until Cahill I thought that successive petitions for rehearing would not be received by the Court under its Rule 58 (4).1 This rule took the place of the old “end of Term” rule of Bronson v. Schulten, 104 U. S. 410, 415 (1882), abolished by the Congress in 1948, 28 U. S. C. § 452 (1958 ed.). Indeed, I doubted that the Court had the power to grant a successive petition for rehearing under a factual situation, as here, where a petition for certiorari had been denied over three years ago, 370 U. S. 918 (1962); a petition for rehearing had been denied, 371 U. S. 856 (1962); the mandate had issued more than three years before; and where petitioner had, about the same date, cancelled her appeal bond and been discharged of all liability thereunder. In Cahill, however, the Court through the device of a “motion to recall and amend the judgment” permitted a successive peti[29]*29tion not only to be received but granted, despite the fact that the judgment thereby reopened had been previously paid.2 This paved the way for the grant of a successive petition for rehearing in United States v. Ohio Power Co., 353 U. S. 98 (1957), to make its judgment conform with this Court’s decision that same Term in United States v. Allen-Bradley Co., 352 U. S. 306 (1957), a companion case of Ohio Power in the Court of Claims.
The vice, of course, is the granting of successive petitions for rehearing in violation of Rule 58 (4), which was done for the first time in Cahill. It makes no difference that the rejection of finality be to correct alleged errors of our own or those below. Nor does it matter that the errors be corrected in the same Term, as in Cahill, or four Terms later, as here. In each instance the action violates Rule 58 (4) and that is the basis of my position.
I, too, as my Brother Harlan said in Ohio Power,
Free access — add to your briefcase to read the full text and ask questions with AI
[26]*26Per Curiam.
Petitioner’s husband, Frank J. Gondeck, was killed as a result of a jeep accident on San Salvador Island outside a defense base at which he was employed. The accident took place in the evening as Gondeck and four others were returning from a nearby town. The Deputy Commissioner of the Bureau of Employees’ Compensation, United States Department of Labor, awarded death benefits to petitioner in accordance with the terms of the Longshoremen’s and Harbor Workers’ Compensation Act, 44 Stat. 1424, as amended, 33 U. S. C. § 901 et seq. (1958 ed.), as extended by the Defense Base Act, 55 Stat. 622, as amended, 42 U. S. C. § 1651 et seq. (1958 ed.). In support of the award, the Deputy Commissioner found, among other things, that, although Gondeck had completed his day’s work, he was subject to call for emergencies while off duty and was returning from reasonable recreation when the accident occurred. The District Court set aside the Deputy Commissioner’s order, and the Court of Appeals for the Fifth Circuit affirmed. United States v. Pan American World Airways, Inc., 299 F. 2d 74. The Court of Appeals acknowledged that Gondeck was subject to call, id., at 75, but found no benefit to the employer in Gondeck’s trip, and “no evidence that furnishes a link by which the activity in which Gondeck was engaged was related to his employment.” Id., at 77.
On June 11, 1962, we denied certiorari. 370 U. S. 918. On October 8, 1962, we denied a petition for rehearing. 371 U. S. 856. We are now apprised, however, of “intervening circumstances of substantial . . . effect,”
In O’Keeffe we made clear that the determinations of the Deputy Commissioner are subject only to limited judicial review, and we reaffirmed the Brown-Pacific-Maxon holding that the Deputy Commissioner need not find a causal relation between the nature of the victim’s employment and the accident, nor that the victim was engaged in activity of benefit to the employer at the time of his injury or death. No more is required than that the obligations or conditions of employment create the “zone of special danger” out of which the injury or death arose. Since the Court of Appeals for the Fifth Circuit misinterpreted the Brown-Pacific-Maxon standard in this case, and since, of those eligible for compensation from the accident, this petitioner stands alone in not receiving it, “the interests of justice would make unfair the strict application of our rules.” United States v. Ohio Power Co., supra, at 99.
[28]*28We therefore grant the motion for leave to file the petition for rehearing, grant the petition for rehearing, vacate the order denying certiorari, grant the petition for certio-rari, and reverse the judgment of the Court of Appeals.
It is so ordered.
Mr. Justice Fortas took no part in the consideration or decision of this case.
Mr. Justice Clark,
joining in the judgment.
I fully agree with my Brother Harlan “that litigation must at some point come to an end” and “that this decision holds seeds of mischief for the future orderly administration of justice . . . .” But with Cahill v. New York, N. H. & H. R. Co., 351 U. S. 183 (1956), on our books, no other conclusion can be reached.
Up until Cahill I thought that successive petitions for rehearing would not be received by the Court under its Rule 58 (4).1 This rule took the place of the old “end of Term” rule of Bronson v. Schulten, 104 U. S. 410, 415 (1882), abolished by the Congress in 1948, 28 U. S. C. § 452 (1958 ed.). Indeed, I doubted that the Court had the power to grant a successive petition for rehearing under a factual situation, as here, where a petition for certiorari had been denied over three years ago, 370 U. S. 918 (1962); a petition for rehearing had been denied, 371 U. S. 856 (1962); the mandate had issued more than three years before; and where petitioner had, about the same date, cancelled her appeal bond and been discharged of all liability thereunder. In Cahill, however, the Court through the device of a “motion to recall and amend the judgment” permitted a successive peti[29]*29tion not only to be received but granted, despite the fact that the judgment thereby reopened had been previously paid.2 This paved the way for the grant of a successive petition for rehearing in United States v. Ohio Power Co., 353 U. S. 98 (1957), to make its judgment conform with this Court’s decision that same Term in United States v. Allen-Bradley Co., 352 U. S. 306 (1957), a companion case of Ohio Power in the Court of Claims.
The vice, of course, is the granting of successive petitions for rehearing in violation of Rule 58 (4), which was done for the first time in Cahill. It makes no difference that the rejection of finality be to correct alleged errors of our own or those below. Nor does it matter that the errors be corrected in the same Term, as in Cahill, or four Terms later, as here. In each instance the action violates Rule 58 (4) and that is the basis of my position.
I, too, as my Brother Harlan said in Ohio Power, “can think of nothing more unsettling to lawyers and litigants, and more disturbing to their confidence in the evenhand-edness of the Court’s processes, than to be left in . . . uncertainty ... as to when their cases may be considered finally closed in this Court.” At p. Ill (dissenting opinion). However, Cahill opened up this practice. It may be that Ohio Power and the present case are more objectionable on their facts, but they merely condone Cahill’s original vice. Until we can gain the vote of the majority to the contrary we are stuck with the practice. The outlook for this appears dim. We can only hope that this rule of “no finality,” which the Court varnishes with the charms of reason, will be sparingly used, or overruled by Congress, as was the “end of Term” rule. I, therefore, join in the judgment of the Court.
U. S. Supreme Ct. Rule 58 (2).