Gold Kist, Inc. v. Carr

886 S.W.2d 425, 1994 WL 484099
CourtCourt of Appeals of Texas
DecidedNovember 23, 1994
Docket11-93-093-CV
StatusPublished
Cited by18 cases

This text of 886 S.W.2d 425 (Gold Kist, Inc. v. Carr) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gold Kist, Inc. v. Carr, 886 S.W.2d 425, 1994 WL 484099 (Tex. Ct. App. 1994).

Opinion

*428 Opinion

McCLOUD, Chief Justice.

Edward C. Carr, Jr., entered into a written agreement with Gold Kist, Inc. to purchase trucks and peanut hauling equipment from Gold Kist. Carr later sued Gold Kist for damages alleging breach of contract, promissory estoppel, and fraud. The central issue in Carr’s suit was whether or not Carr had “exclusive hauling rights.” Trial was to the jury who found that:

(1) Gold Kist agreed that Carr would have exclusive hauling of Gold Kist’ peanut commodities in the State of Texas during the term of the promissory note.
(2) Carr was able to perform in accordance with that agreement.
(3) With the objective of placing Carr in the position he would have been in had the agreement been performed, the damages suffered by Carr for the following peanut hauling seasons were:
1986: $ 20,479.00
1987: $ 89,188.00
1988: $146,089.00
1989: $171,895.00
1990: $114,148.00
1991: $ 29,602.00
(4) Gold Kist knew on September 24,1986, that the representation that Carr would have exclusive rights to haul peanuts was false.
(5) Carr should recover $250,000.00 as exemplary damages for that falsehood.

The trial court made farther findings relating to breach of contract, promissory estoppel, and fraud. The court entered a judgment in favor of Carr awarding him $570,401.00 in actual damages and $250,000.00 in exemplary damages plus prejudgment interest and attorney’s fees. The trial court also granted Gold Kist an offset of $36,568.41 on its counterclaim against Carr for payment on his promissory note.

Gold Kist appeals challenging the judgment on several grounds. Gold Kist contends that Carr’s breach of contract claim is barred by the parol evidence rule and the statute of frauds 1 and that the trial court erred in entering express findings 2 as to Carr’s claim of promissory estoppel. Gold Kist also attacks the jury’s finding of fraud. We sustain these challenges in Gold Kist’ Points of Error Nos. 1, 3, and 5. 3 The judgment of the trial court is reversed and rendered in part and affirmed in part.

Background Facts

The record reflects that, in August of 1986, Walter Dan Holland was the manager of Gold Kist’ peanut shelling plant in Comyn, Texas. Peanuts were transported to the Co-myn plant from statewide “buying points” where farmers sold their peanuts. Some of the buying points were owned by Gold Kist; and others, known as “commissioned buying points,” were independently owned. Holland contacted Carr and offered to sell Carr Gold Kist’ trucks and hauling equipment at the Comyn plant. Holland and Carr began to negotiate the terms of the sale, and both men were aware that any agreement they reached would have to be approved by Gold Kist’ corporate headquarters in Atlanta, Georgia.

They first agreed that Carr would purchase the trucks and equipment and that Carr would have the exclusive right to haul peanuts for Gold Kist in Texas. This agreement was submitted to Michael Stimpert, a vice-president for Gold Kist at the Atlanta corporate headquarters. Some of the commissioned buying points wanted to use their own trucks and equipment to haul the peanuts. Gold Kist did not want to risk losing business from these buying points. Stimpert objected to granting Carr exclusive hauling rights and requested that the final contract be drafted so as to exclude any hauling rights. Holland told Carr that Gold Kist would not grant him the exclusive right to haul all of Gold Kist’ peanuts.

*429 A contract was drafted under which Carr would purchase Gold Kist’ trucks and hauling equipment for $60,000.00 paying $20,000.00 in cash and executing a five-year promissory note for the remaining $40,000.00. The contract stated: ■ “Gold Kist, from time to time, may, but shall be under no obligation to, engage you to haul commodities on its behalf.” Stimpert signed the contract as Gold Kist’ “Group Vice President-Agricommodities.” On September 24, 1986, Carr signed the contract.

Exclusive Hauling Rights

The central issue in Carr’s suit is whether or not Gold Kist granted him the exclusive right to haul its peanuts. Carr testified that, after the original agreement was rejected by Gold Kist’ corporate headquarters, he renegotiated the agreement with Holland. Under this second agreement, Carr testified that he was to have exclusive hauling rights with the exception that, during the first year of operation, he would not haul peanuts from the buying points that had protested. After the first year, those buying points would be “educated and straightened out”; and Carr would then have the exclusive right to haul from those buying points as well. Because Carr’s hauling dining the first year would be reduced under the new agreement, the purchase price of the trucks and equipment was reduced from $100,000.00 to $60,000.00.

When he received the written contract signed by Stimpert, Carr questioned the sentence that stated that Gold Kist had no obligation to use Carr because the sentence did not conform with what he thought was the agreement. Carr asked Holland what it meant. Holland called Ron Clark, the Atlanta-based manager of Gold Kist’ peanut division, who told Holland that he thought Gold Kist did not have to use Carr if his performance did not meet Gold Kist’ expectations. Holland relayed this information to Carr who signed the agreement.

Parol Evidence Rule

The parol evidence rule precludes consideration of extrinsic evidence to contradict, vary, or add to the terms of an unambiguous written agreement absent fraud, accident, or mistake. Kuper v. Schmidt, 161 Tex. 189, 338 S.W.2d 948, 952 (1960); Hubacek v. Ennis State Bank, 159 Tex. 166, 317 S.W.2d 30, 32 (1958). Whether a contract is ambiguous is “a question of law for the court to decide by looking at the contract as a whole in light of the circumstances present when the contract was entered.” Coker v. Coker, 650 S.W.2d 391, 393-94 (Tex.1983). A contract is ambiguous when its meaning is genuinely uncertain and doubtful or when it is reasonably susceptible to more than one meaning. Coker v. Coker, supra. If a contract can be given a certain or definite legal meaning or interpretation, it is not ambiguous; and the court will construe the contract as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in Re Estate of Timothy Glen Chapman
Court of Appeals of Texas, 2017
Miller v. Citimortgage, Inc.
970 F. Supp. 2d 568 (N.D. Texas, 2013)
Hurd v. Bac Home Loans Servicing, LP
880 F. Supp. 2d 747 (N.D. Texas, 2012)
Smith v. Maximum Racing, Inc.
136 S.W.3d 337 (Court of Appeals of Texas, 2004)
Glen Smith v. Maximum Racing, Inc.
Court of Appeals of Texas, 2004
Taub v. Houston Pipeline Co.
75 S.W.3d 606 (Court of Appeals of Texas, 2002)
In Re H.E. Butt Grocery Co.
17 S.W.3d 360 (Court of Appeals of Texas, 2000)
McClure v. Attebury
20 S.W.3d 722 (Court of Appeals of Texas, 1999)
Johnson & Higgins of Texas, Inc. v. Kenneco Energy, Inc.
962 S.W.2d 507 (Texas Supreme Court, 1998)
In re City Metals Co.
181 B.R. 398 (W.D. Missouri, 1995)
Hionis International Enterprises, Inc. v. Tandy Corp.
867 F. Supp. 268 (D. Delaware, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
886 S.W.2d 425, 1994 WL 484099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gold-kist-inc-v-carr-texapp-1994.