Gnagey Gas & Oil Co. v. Pennsylvania Underground Storage Tank Indemnification Fund

82 A.3d 485, 2013 WL 6385303, 2013 Pa. Commw. LEXIS 509
CourtCommonwealth Court of Pennsylvania
DecidedDecember 6, 2013
StatusPublished
Cited by15 cases

This text of 82 A.3d 485 (Gnagey Gas & Oil Co. v. Pennsylvania Underground Storage Tank Indemnification Fund) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gnagey Gas & Oil Co. v. Pennsylvania Underground Storage Tank Indemnification Fund, 82 A.3d 485, 2013 WL 6385303, 2013 Pa. Commw. LEXIS 509 (Pa. Ct. App. 2013).

Opinion

OPINION BY Judge McCULLOUGH.

Gnagey Gas & Oil Co., Inc. (Gnagey) petitions for review of the June 21, 2012 adjudication and order of the Underground Storage Tank Indemnification Board (Board), which adopted the report and recommendation of the Presiding Officer of the Underground Storage Tank Indemnification Fund (Fund) and dismissed Gnagey’s exceptions to the report. The Board upheld the Presiding Officer’s conclusion that Gnagey engaged in fraudulent conduct in concealing material information and in failing to cooperate with the Fund during the removal of underground storage tanks (USTs) on contaminated property owned by Gnagey. Accordingly, the Board concluded that under the Storage Tank and Spill Prevention Act of 1989 (the [489]*489Tank Act)1 and applicable regulations, the Fund is entitled to recoup $319,738.57 it paid to Gnagey for remediation expenses.

This case involves the Fund’s determination that Gnagey was eligible for funds for remediation measures made in connection with the removal of four USTs from Gna-gey’s property and the Fund’s later decision to revoke Gnagey’s eligibility and recoup the funds paid on the grounds that Gnagey fraudulently concealed the existence of eight unregistered and abandoned/orphaned tanks during the clean-up.

I. Facts and Procedural History

The relevant facts and procedural history of this case, as found and detailed in a commendable fashion by the Presiding Officer, are as follows:

Gnagey purchased the Cranberry Township site of the subject claim in 1995 from Gulf Oil.... When Gnagey purchased the property, five [USTs] were registered for the site. The four registered gasoline tanks were located in one tankfield on the southern edge of the property while the location of a 500 gallon registered waste oil tank was unknown.
In addition to the registered tanks, the site contained eight additional abandoned and unregistered USTs. Four of the unregistered tanks were just southwest of the dispenser islands near the center of the property, and the other four were north of the dispensers. The tanks were of the type used in the 1950s and 1960s, and all had been taken out of service sometime before 1970.
In connection with Gnagey’s purchase of the property, a site assessment was performed in 1995 to identify potential contamination on the site. Twenty-four borings were drilled on the site, mostly around the perimeter of the property. Three of the borings revealed contamination in excess of the state regulatory standards in effect at that time. One of the borings containing contamination was between the dispenser islands and the registered tanks where the drill hit a product line. The other two borings showing contamination were near the northernmost unregistered tanks. The environmental contractor dug out the area around the boring which struck a product line, removed a small amount of soil, made a repair to the line and back-filled everything. The area around the other two contaminated borings was not addressed, and the sale to Gnagey was completed.
After purchasing the property from Gulf Oil, Gnagey operated the site as a convenience store and service station until 2007, when Gnagey was in the process of selling the site to a land developer. As part of that sale, a site assessment was conducted for the buyer and the assessment indicated contamination. Because the sale was contingent on the site being free of contamination^ Gnagey engaged United Environmental Group (“UEG”), a firm which performed Gnagey’s environmental work for many years.... In August 2007, UEG on behalf of Gnagey timely reported the release to the Pennsylvania Department of Environmental Protection (“DEP”) and to [the Fund]. At that time, the source of the contamination was listed as being unknown. [The Fund] engaged ICF International (“ICF”) to investigate and administer the claim, and the claim was assigned to Ron Moore. After an initial investigation, [the Fund] through Mr. Moore granted eligibility for the claim on November 1, 2007, with the letter indicating that any corrective action costs [490]*490attributable to contamination found to have been released prior to February 1, 1994 would not be covered by the Fund.
Mr. Moore was notified that the tanks were going to be removed in March 2008.... On March 3, 2008, UEG began excavation, starting on the southern side of the property where the registered tanks were located.
Upon removing the four tanks, UEG encountered contamination in the tank pit and began removing the contaminated soil and water. One of the tanks was cracked, and UEG determined it to be the source of the release even though the tank system had passed tightness testing as recently as 2007. After removing the tanks and excavating soil in the tank pit, UEG began excavating along the product line towards the dispenser islands as that trench also was contaminated. On March 17, 2008, UEG issued an invoice which was paid by the Fund.
UEG initially stockpiled the contaminated soil on the northern side of the property but eventually ran out of room and began hauling the contaminated soil away to an incineration facility. Given the volume of contaminated soil which was being excavated, the Ohio facility was less costly than a Pennsylvania landfill which requires analytic sampling on every hundred tons of soil. As a result, the excavated soil was not available for analysis and samples were not taken or preserved for analysis.
UEG continued to excavate towards the north of the property, ultimately encountering and removing the abandoned unregistered tanks between March 18 and 28, 2008. The abandoned tanks were riddled with holes and were filled with water. UEG removed the contaminated water from the tanks and disposed of it off site. Soil was visibly contaminated under and around the abandoned tanks. Gnagey was notified when UEG encountered the first set of abandoned tanks in the center of the property and again when UEG encountered the second set in the northern portion of the property. Gnagey was informed that there was contamination around the abandoned tanks.
In March and April 2008, UEG invoiced Gnagey rather than [the Fund] for removal of the abandoned tanks and disposal of contaminated water in the tanks. With those invoices, UEG supplied Gnagey with photographs of the abandoned tanks in the ground and after removal. The photographs showed the obvious contamination of the soil under and in the vicinity of the abandoned tanks.
On March 19, 2008, after the first set of abandoned tanks was discovered, Mr. Klesic of UEG telephoned Mr. Moore and informed him that the product line ditches were filtering product into an old pit or former foundation but did not mention the abandoned tanks in the pit. On March 26, 2008, in response to a request for status by Mr. Moore, UEG advised Mr. Moore that 4,000 tons of impacted soil had been removed from the site and that no other remedial activity had occurred other than removal of ponded water. Again, the abandoned tanks and surrounding contamination were not mentioned.
UEG issued invoices on March 28, April 7 and April 15.... The March 28 invoice was accompanied by a narrative and a site map showing the general areas of excavation. The area containing the first set of abandoned tanks encountered was designated as a former excavation [491]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HARTEL v. BEAZER EAST, INC.
W.D. Pennsylvania, 2025
SELTZ v. SWEPI LP
W.D. Pennsylvania, 2024
ZAFTR INC. v. LAWRENCE
E.D. Pennsylvania, 2023
RANALLI v. AMAZON.COM LLC
W.D. Pennsylvania, 2021
BARBOUNIS v. THE MIDDLE EAST FORUM
E.D. Pennsylvania, 2021
Lower Bucks County Joint Municipal Authority v. P. Koszarek
Commonwealth Court of Pennsylvania, 2020
In re Chrysler-Dodge-Jeep Ecodiesel Mktg.
295 F. Supp. 3d 927 (N.D. California, 2018)
In re General Motors LLC Ignition Switch Litigation
257 F. Supp. 3d 372 (S.D. New York, 2017)
Martin v. Ort
Maine Superior, 2016
Norfolk Southern Railway Co. v. Pittsburgh & West Virginia Railroad
153 F. Supp. 3d 778 (W.D. Pennsylvania, 2015)
Oxford Investments, L.P. v. City of Philadelphia
21 F. Supp. 3d 442 (E.D. Pennsylvania, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
82 A.3d 485, 2013 WL 6385303, 2013 Pa. Commw. LEXIS 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gnagey-gas-oil-co-v-pennsylvania-underground-storage-tank-pacommwct-2013.