Global Truck & Equipment Co. v. Palmer MacHine Works, Inc.

628 F. Supp. 641, 42 U.C.C. Rep. Serv. (West) 1250, 1986 U.S. Dist. LEXIS 29524
District Court, N.D. Mississippi·Decided February 7, 1986·No. EC 83 174 GD D·Published·Cited by 10 cases

Opinion

MEMORANDUM OPINION

DAVIDSON, District Judge.

The plaintiff Global Truck & Equipment Co., Inc. (Global) brings this action for damages arising from the sale of alleged defective dump trailers sold by Palmer Machine Works, Inc. (Palmer). The plaintiff seeks recovery under the theories of strict liability in tort, negligent design and breach of express and implied warranties. The defendant asserts that the trailers sold by it were free from defect and the trailer turnovers were the result of the misuse of the product in that the trailers were made for hauling washed rock and gravel only and that a cohesive material containing rock and dirt or clay was hauled instead. Plaintiff Global is a Texas corporation primarily engaged in the business of selling and purchasing trucks, trailers and related equipment. Defendant Palmer is a Mississippi corporation engaged in the manufacture and selling of trailers to be used for the hauling and dumping of various materials. This court has jurisdiction of this matter pursuant to its diversity jurisdiction. 28 U.S.C. section 1332. The court proceeds with its findings of fact and conclusions of law pursuant to rule 52 of the Federal Rules of Civil Procedure.

FINDINGS OF FACT

In late 1980, John Randall, Vice-President and a major stockholder of Global, was contacted by Roberto Lopez of McAllen Motors, at the request of Constructora-Dava, a Mexican contractor, to purchase twenty-five trucks. Lopez stated that the trucks were to be equipped with triaxle frame-type trailers, 30 feet in length, containing a 38 cubic yard capacity, 1 twelve 22 inch tires and having five foot sides. At the time of the sale, Randall of Global and Lopez had been in the business of buying and selling trucks and trailers since 1975 and 1979, respectively. Randall had previously received orders from Lopez for trucks and trailers and, in a desire to continue to please his customers, Randall contacted a number of manufacturers and dealers with which he was familiar but was unable to find a manufacturer who would deliver a triaxle 30 foot trailer by the date that Lopez related that Constructora-Dava needed the trailers. One of the dealers, however, recommended Palmer Machine Works, Inc. and subsequently, Randall telephoned Jason Gallop of Palmer. Randall advised Gallop of the general specifications 2 demanded by the Mexican customer, Constructora-Dava, advised Gallop that the trailers were to be used in Mexico and that they were to be used for hauling washed rock and gravel. An initial order of five trailers instead of the requested twenty-five trailers was made in an attempt to manufacture and deliver the trailers before the expiration of the Mexicans’ import permit. The total purchase price of the five trailers was $81,375.00 or $16,275.00 each. Randall placed the order on November 14, 1980 and a deposit of 15 percent or $12,-206.25 was paid on November 18. Global paid the balance of the purchase price upon *644 receipt of the trailers at Palmer’s facility in Monroe County, Mississippi on November 24, 1980.

After arriving at the site in Mexico, the first trailer was loaded but overturned during the dumping process. The second trailer likewise overturned on its first use. Upon notification of these occurrences, Lawrence R. Palmer, president of the defendant, met with Lopez in McAllen, Texas and from there they traveled to the site in Mexico to supervise and observe the dumping of a third Palmer trailer. Palmer instructed the Mexicans to utilize the same loading and dumping procedures as were implemented with regard to the first two Palmer trailers. The Mexicans proceeded to wet the material with water from hoses at the site and loaded the trailers utilizing loaders. The Palmer trailers in a normal dumping procedure dump at five different levels or stages. At the end of stages 1 and 2, Palmer ordered the dumping process temporarily haulted while he took measurements of the spring deflection underneath the trailer as well as other measurements. Palmer testified that at the first and second stages, about one-third of the load discharged per stage. After taking these measurements, Palmer ordered the trailer raised to the third stage and again stopped. Palmer testified that, at this stage, approximately another ten to fifteen feet of material had discharged, or about 80% of the total load, leaving five to six feet of material in the trailer bed. Lopez and Palmer agree that while Palmer was underneath the trailer, more of the material in the trailer suddenly discharged, causing the trailer to tip to the left, then to the right whereupon the trailer proceeded to fall to the ground.

Free access — add to your briefcase to read the full text and ask questions with AI

Global Truck & Equipment Co. v. Palmer MacHine Works, Inc., 628 F. Supp. 641, 42 U.C.C. Rep. Serv. (West) 1250, 1986 U.S. Dist. LEXIS 29524 (N.D. Miss. 1986).

628 F. Supp. 641 (Global Truck & Equipment Co. v. Palmer MacHine Works, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Compaq Computer Corp. v. Lapray
135 S.W.3d 657 (Texas Supreme Court, 2004)
Torres v. Northwest Engineering Co.
949 P.2d 1004 (Hawaii Intermediate Court of Appeals, 1998)
Maroone Chevrolet, Inc. v. Nordstrom
587 So. 2d 514 (District Court of Appeal of Florida, 1991)
Futch v. James River-Norwalk, Inc.
722 F. Supp. 1395 (S.D. Mississippi, 1989)