Glenn Thurman, Inc. v. Moore Construction, Inc.

942 S.W.2d 768, 1997 Tex. App. LEXIS 1608, 1997 WL 148800
CourtCourt of Appeals of Texas
DecidedMarch 31, 1997
Docket12-95-00254-CV
StatusPublished
Cited by27 cases

This text of 942 S.W.2d 768 (Glenn Thurman, Inc. v. Moore Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glenn Thurman, Inc. v. Moore Construction, Inc., 942 S.W.2d 768, 1997 Tex. App. LEXIS 1608, 1997 WL 148800 (Tex. Ct. App. 1997).

Opinion

HOLCOMB, Justice.

Glenn Thurman, Inc. (“GTI”), Appellant, appeals the trial court’s judgment in favor of Moore Construction, Inc. (“Moore”), Appel-lee, on GTI’s breach of contract counterclaim. Appellant generally alleges that the trial court erred in submitting jury questions which “tainted” the jury in regards to its counterclaim, in not finding for GTI on several issues as a matter of law, in failing to grant GTI’s Judgment Non Obstante Vere-dicto (“JNOV”), in failing to submit certain jury questions and instructions, and in sub *770 mitting a jury question based upon common law contract theory rather than the Uniform Commercial Code (“U.C.C.”). We reverse the judgment of the trial court and remand for a new trial.

Moore and GTI entered into a contract whereby GTI would sell hot mix asphaltic concrete and prime coat to Moore, who was constructing a parking lot for Walmart in Gun Barrel City. After Moore completed the parking lot, Walmart informed the construction company that the asphalt was not within Walmart’s specifications. The record shows that Moore wrote to GTI and requested a “correction of the defective pavement.” When GTI did not respond, Moore wrote another letter stating that it was going to repair the parking lot and seek damages from GTI for the repairs. Moore replaced approximately one-third of the asphalt, and did not pay GTI for any of the asphaltic concrete, the prime coat, or freight delivery. Moore proceeded to sue GTI for breach of contract and violation of the Deceptive Trade Practices Act (“DTPA”). GTI countersued for payment under the contract and for quantum meruit. During the jury trial, the parties entered into a stipulation that if either party appealed, it would base its appeal only upon the charge, the verdict, or the judgment as it related to the verdict. The jury found for Moore on both its breach of contract and DTPA causes of action, but Moore elected to move for judgment on the DTPA violation. On GTI’s counterclaim, the jury found that Moore breached its contract by failing to pay GTI, but that GTI’s prior breach excused Moore’s breach. The jury failed to find for GTI on its quantum meruit theory.

Before reviewing GTI’s points of error in detail, we must ascertain if the parties’ stipulation bars any or all of them from consideration by this Court. GTI complains of charge error in points one, two, four, five and six. Its points of error three, seven and eight aver that the trial court committed error in failing to find various elements as a matter of law. Its ninth point of error asserts that the trial court committed error by awarding Moore a windfall recovery contrary to the law, and in failing to grant GTI’s JNOV Motion and Motion for New Trial on this issue. And point ten claims that the trial court erred in failing to award GTI attorneys’ fees, as found by the jury. The stipulation, as stated in the record, is as follows:

Further, both parties agree that if either party elects to appeal, that the appeals would not be related to issues concerning sufficiency of the weight of the evidence or anything that has transpired during trial, or no evidence points. The issues would be related to the jury charge and the verdict, and that would be the limit of both parties’ right to an appeal, if any.
And ... to make sure this is a complete agreement, ... if we have the right to appeal the charge and verdict, we also need the right to appeal the Court’s judgment on the verdict ... as it relates only to the charge and the verdict.'

A stipulation constitutes a contract between the parties, and between the parties and the court. First National Bank v. Kinabrew, 589 S.W.2d 137, 142 (Tex.Civ.App.—Tyler 1979, writ ref'd n.r.e). A stipulation may fix, limit, or modify the issues in a case. Id. Specifically, parties may enter into a binding stipulation that limits the issues on appeal. See Missouri Pacific Railroad Co. v. Whittenburg & Alston, 424 S.W.2d 427, 428 (Tex.1968). Such a stipulation will foreclose the appellate court from going behind the agreement in examining issues beyond those stipulated by the parties. See id.; see also Ruiz v. Conoco, Inc., 868 S.W.2d 752, 754 (Tex.1993).

We overrule GTI’s points three, seven and eight because they are based on evidentiary matters specifically barred by the parties’ stipulation. Point nine fails to complain of the jury charge or the verdict and judgment on the charge; therefore, it also contravenes the stipulation, and we overrule it as well.

In its first two points of error, GTI alleges that two of Moore’s breach of contract jury questions “tainted” the jury’s answers to GTI’s questions on its counterclaims. Although GTI objected to these questions before the charge was submitted to *771 the jury, it did not specifically complain that they would “taint” the remaining questions. Objections to the charge must be specific. The objection must clearly identify the error and explain the grounds for the complaint. Tex.R.Civ.P. 274; Castleberry v. Branscum, 721 S.W.2d 270, 276 (Tex.1986). If the objection does not meet both requirements, it will not preserve error. Id. Because GTI was not specific and did not clearly explain its grounds, it failed to preserve error. We overrule points one and two.

GTI’s point of error four complains that the trial court committed error in submitting Question No. 10, as well as the related instruction to the jury which GTI alleges misstated the law and was improperly worded. GTI further alleges that the court erred in entering judgment on the jury’s finding on Question No. 10 and in failing to grant GTI’s JNOV Motion on Question No. 10. Question Nos. 9 and 10, along with the jury’s answers, read as follows:

QUESTION NO. 9:
Did Moore fail to comply with the terms of the Contract?
ANSWER: Yes
QUESTION NO. 10:
Was Moore’s failure to comply excused?
ANSWER: Yes
You are instructed that failure to comply by Moore is excused by Thurman’s previous failure to comply with a material obligation of the Contract.
You are further instructed that Thurman failed to comply with a material obligation of its Contract if:
(a) the materials were not reasonably uniform in quality; or
(b) the materials were not at all times up to standard.

GTI asserts that the jury question on “excuse” was reversible error because it reflects a common law contract defense, rather than a U.C.C. defense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luig v. North Bay Enterprises, Inc.
55 F. Supp. 3d 942 (N.D. Texas, 2014)
Omni USA, Inc. v. Parker-Hannifin Corp.
964 F. Supp. 2d 805 (S.D. Texas, 2013)
TC/American Monorail, Inc. v. Custom Conveyor Corp.
822 N.W.2d 812 (Court of Appeals of Minnesota, 2012)
Bro-Tech Corp. v. Purity Water Co. of San Antonio, Inc.
681 F. Supp. 2d 791 (W.D. Texas, 2010)
Justin Davis v. State
Court of Appeals of Texas, 2007
TRIDENT STEEL CORPORATION v. Wiser Oil Co.
223 S.W.3d 520 (Court of Appeals of Texas, 2006)
Jay v. Nesco Acceptance Corp. (In Re Jay)
308 B.R. 251 (N.D. Texas, 2003)
Coburn Supply Company Inc. v. Kohler Co.
342 F.3d 372 (Fifth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
942 S.W.2d 768, 1997 Tex. App. LEXIS 1608, 1997 WL 148800, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glenn-thurman-inc-v-moore-construction-inc-texapp-1997.