Glassell, Taylor & Robinson v. John W. Harris Associates, Inc.

26 So. 2d 1, 209 La. 957, 1946 La. LEXIS 748
CourtSupreme Court of Louisiana
DecidedMarch 18, 1946
DocketNo. 37828.
StatusPublished
Cited by25 cases

This text of 26 So. 2d 1 (Glassell, Taylor & Robinson v. John W. Harris Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glassell, Taylor & Robinson v. John W. Harris Associates, Inc., 26 So. 2d 1, 209 La. 957, 1946 La. LEXIS 748 (La. 1946).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 959 [EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 960 [EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 961 The plaintiff is appealing from the judgment of the district court dismissing, on exceptions of no cause and no right of action, its suit against the general contractor, the owner with whom the contract was entered into, and the present owners of the premises, to recover from them in solido the balance allegedly due for services rendered and material and labor furnished in the construction of a complete housing project, in accordance with its contract with the said contractor, as well as for recognition *Page 963 and enforcement of its lien and privilege on the premises.

While the allegations contained in the petition are somewhat lengthy and involved, its well-pleaded facts, which, according to the well-settled jurisprudence of this state, must be accepted as true in disposing of exceptions of no cause and no right of action, are substantially that the plaintiff, Glassell, Taylor Robinson, a partnership, allegedly furnished services, material, and labor preparatory to and in the construction of a complete housing project under three separate contracts with the general contractor, i. e., one of May 28, 1943, for the clearing, grubbing, excavation, and grading of parks, house sites, rights-of-way for streets and utilities, a temporary railroad spur and siding, and the construction of two culverts; another of June 5, 1943, for the construction of a temporary railroad spur and siding; and the third of July 2, 1943, for the complete installation of a water distributing and sewerage collection system as well as the construction of roads, streets, and drainage therefor, said general contractor being John W. Harris Associates, Inc., of Louisiana, a Delaware corporation, engaged under contract to construct this complete building or housing project for the Cities Service Refining Corporation, also a Delaware corporation, on certain lands then owned by the latter and located in the Parish of Calcasieu, the exact date and contents of such contract being unknown to *Page 964 the plaintiff since it was not of record; that the contracts of May 28 and July 2 were substantially similar as to form, each providing that payment was to be made according to the "unit" prices specified in the contract every two weeks, as the work was completed and accepted, the payments being limited to 90% of the contract price, the remaining 10% thereof being retained until the work was completed and accepted by the contractor's architectural engineer, while the contract of June 5 was paid after completion for the flat price of $12,250 for the completed job, a balance remaining due thereon in the amount of $287.88; that the work on the first two contracts was timely completed and while the work on the contract of July 2 was promptly begun, it was not completed within the number of working days stipulated in the contract for the reason that obstacle after obstacle was interposed by the contractor to the orderly, economical, and expeditious prosecution of the construction, the contract being finally cancelled and the plaintiff ousted by the general contractor on February 28, 1944, without just cause, the general contractor then being in default, having repeatedly refused to pay certain amounts due for work completed and having failed to furnish plans as specified in the contracts; that in the meanwhile, on November 10, 1943, the Cities Service Refining Corporation transferred title to the entire housing project to the general contractor, who, in turn, on December 21, 1943, sold the same to the defendants *Page 965 Maplewood Housing Corporation and Second Maplewood Housing Corporation. Plaintiff further alleged that on February 23, 1944, it filed and recorded in the mortgage records of Calcasieu Parish, in accordance with the provisions of Act 298 of 1926, as amended (by Acts 323 of 1938 and 79 of 1944), a lien in the amount of $309,359.66, and that a copy of this lien was properly and legally served on John W. Harris Associates, Inc., of Louisiana and on the Cities Service Refining Corporation; that on March 22, 1944, there was also filed in accordance with the provisions of this act in the mortgage records of Calcasieu Parish a lien in the sum of $383,317.39, and that a copy of this said lien was properly and legally served on John W. Harris Associates, Inc., of Louisiana, Cities Service Refining Corporation, Maplewood Housing Corporation, and Second Maplewood Housing Corporation.

The plaintiff abandoned its main demand, that is, that these documents, being potestative in character, are null and void as contracts, and in its first alternative demand prayed for the dissolution and rescinding of the contracts because of breaches and defaults on the part of the general contractor and that it recover from the defendants in solido, in quantum meruit, the sum of $383,317.39; in the second alternative, that if the plaintiff is held not to be entitled to have the contracts judicially rescinded and this amount recovered in quantum meruit, then that it be entitled to recover from the *Page 966 defendants in solido the sum (1) of $73,216.52, for work done from December 15, 1943, to March 1, 1944; (2) $22,238.63, for extra work done; (3) $41,962.66, for percentages retained, and (4) the difference between the alleged cost of the work performed by the plaintiff and the prices of the said work as set out in the contracts of May 28, June 5, and July 2, none of which amounts have been paid; and, in the third alternative, these same amounts as damages for the breach of these contracts by the general contractor, in the event they are held to be legal and binding and the plaintiff not entitled to their dissolution or rescission.

The trial judge in construing those portions of Act 298 of 1926 he considered pertinent followed the rule of construction that acts in derogation of common rights must be strictly construed and concluded that under Sections 2 and 12 of this act "a general contractor in order that his lien and privilege may be created and preserved must reduce his contract with the owner towriting and then it must be signed by the parties and then the contract thus executed must be recorded, but where the owner undertakes the work himself, and where there is no contract, or where there is a contract but not recorded, with respect to any labor or material, the laborer or furnisher of material may create and preserve his lien and privilege by executing an affidavit and filing for record such affidavit. This method of creating and preserving the lien and *Page 967 privilege is available only to the laborer or furnisher of material, and is not available to a contractor orsubcontractor, * * * for Section 2 of the Act provides that a contractor must reduce his contract to writing, then the parties must sign the same, and after which the contract must be recorded within the time prescribed by the Act." (Italics ours.)

Then, relying on the decision of the Court of Appeal for the First Circuit in the case of Officer v. Combre, 194 So. 441, as being decisive, he held that John W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Haydel v. Commissioner
1991 T.C. Memo. 507 (U.S. Tax Court, 1991)
Aesco Steel, Inc. v. J.A. Jones Construction Co.
621 F. Supp. 1576 (E.D. Louisiana, 1985)
Ragusa v. Burns
462 So. 2d 658 (Louisiana Court of Appeal, 1984)
Orleans Onyx, Inc. v. Buchanan
428 So. 2d 841 (Louisiana Court of Appeal, 1983)
Tom Black & Associates, Inc. v. Thibaut Construction Co.
420 So. 2d 1150 (Louisiana Court of Appeal, 1982)
South Central Bell Tel. Co. v. Traigle
367 So. 2d 1143 (Supreme Court of Louisiana, 1978)
Express Ready-Mix, Inc. v. Evans
266 So. 2d 257 (Louisiana Court of Appeal, 1972)
Pringle-Associated Mortgage Corporation v. Eanes
226 So. 2d 502 (Supreme Court of Louisiana, 1969)
Capital Bank & T. Co. v. Broussard Paint & Wall. Co.
198 So. 2d 204 (Louisiana Court of Appeal, 1967)
Broadmoor Lumber Co. v. Liberto
162 So. 2d 800 (Louisiana Court of Appeal, 1964)
Martinolich v. Albert
143 So. 2d 745 (Louisiana Court of Appeal, 1962)
Fruge v. Muffoletto
137 So. 2d 336 (Supreme Court of Louisiana, 1962)
Johnson v. Sewerage District No. 2 of Parish of Caddo
120 So. 2d 262 (Supreme Court of Louisiana, 1960)
State v. Orleans Parish School Board
118 So. 2d 471 (Louisiana Court of Appeal, 1960)
Melde Tile Roofing Co. v. Compact Homes, Inc.
92 So. 2d 735 (Louisiana Court of Appeal, 1957)
Schwartz Supply Co. v. Zimmerman
84 So. 2d 438 (Supreme Court of Louisiana, 1955)
Roland v. American Casualty Co.
80 So. 2d 387 (Supreme Court of Louisiana, 1955)
State ex rel. Henry v. 8-Mile Post Plumbing Supplies, Inc.
63 So. 2d 749 (Louisiana Court of Appeal, 1953)
Smith v. Anderson Bros.
104 F. Supp. 117 (W.D. Louisiana, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 2d 1, 209 La. 957, 1946 La. LEXIS 748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glassell-taylor-robinson-v-john-w-harris-associates-inc-la-1946.