GJ Deville Lumber Company, Inc. v. Chatelain

308 So. 2d 428
CourtLouisiana Court of Appeal
DecidedJune 6, 1975
Docket4805
StatusPublished
Cited by12 cases

This text of 308 So. 2d 428 (GJ Deville Lumber Company, Inc. v. Chatelain) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GJ Deville Lumber Company, Inc. v. Chatelain, 308 So. 2d 428 (La. Ct. App. 1975).

Opinion

308 So.2d 428 (1975)

G. J. DEVILLE LUMBER COMPANY, INC., Plaintiff-Appellee,
v.
Ronald Edwin CHATELAIN, Defendant-Appellant.

No. 4805.

Court of Appeal of Louisiana, Third Circuit.

February 12, 1975.
Rehearing Denied March 12, 1975.
Writ Refused June 6, 1975.

*429 Dodd, Hirsch, Barker, Avant & Wall by Kenneth L. Riche, Baton Rouge, for defendant-appellant.

Jack C. Frugé, Sr., Ville Platte, for plaintiff-appellee.

Before HOOD, CULPEPPER and MILLER, JJ.

HOOD, Judge.

G. J. Deville Lumber Company, Inc., instituted this suit to recover the balance of $2,429.91 due under a contract, pursuant to which it constructed a home for defendant, Ronald Edwin Chatelain. Defendant answered alleging generally that there were defects in the construction, that the cost of correcting them should be set-off against the amount claimed, and that plaintiff's suit should be dismissed. Defendant also filed a reconventional demand alleging breach of contract, setting out particularly several omissions or defects in construction, and demanding damages from Deville in the amount of $16,759.00, including $3,000.00 for mental anguish. The trial judge rendered judgment in favor of Deville and against Chatelain for $1,360.91. Chatelain appealed.

The issues presented, stated generally, are whether Chatelain is entitled to credits or set-offs against the amount he owes under the contract, in addition to the set-offs allowed by the trial court, and whether he *430 is entitled to recover damages for breach of contract.

In August, 1971, the parties entered into a contract under the terms of which Deville agreed to construct a home for Chatelain for a price or consideration of about $25,000.00. The construction of the home was completed in January, 1972, at least to the extent that Chatelain was able to move into it, and defendant has lived in the home since that time. Chatelain did not pay the consideration called for in the contract when demand was made upon him because he contended that parts of the house had not been constructed in accordance with the specifications, and that the workmanship was defective in several respects.

Before construction was begun, Chatelain obtained a commitment from Avoyelles Savings and Loan Association for a loan of $21,500.00, which amount was to be used to pay the major part of the construction costs of this house. Some time in January or February, 1972, representatives of that association inspected the house and approved it for completion of the loan. Before the association would disburse the proceeds of the loan, however, it required a "lien waiver" or a "no-lien" certificate from the contractor.

On March 13, 1972, Deville received a letter from the Savings and Loan Association informing it that the association was ready to remit to it the proceeds of the loan, and requesting that Deville advise the association whether that amount "will settle all claims incurred in the construction of said home."

On March 14, immediately after receipt of the above letter, Lionel Deville, president of plaintiff corporation, met with defendant Chatelain at the latter's newly constructed home to discuss their differences. At that meeting Deville and Chatelain agreed that the total contract price due Deville for constructing the home was $23,929.91, and that after the construction was completed and the proceeds of the loan were paid to Deville there would remain a balance of $2,429.91 due by Chatelain on that contract. Both parties also agreed at that time that Chatelain would pay to Deville immediately the sum of $1,429.91, that Deville would perform some specified corrective work on the house, and that Chatelain would pay the remaining balance of $1,000.00 due under the contract when the corrective work agreed upon was performed by Deville.

Pursuant to that agreement, Chatelain issued and delivered to Deville on March 14, 1972, his check for $1,429.91. Deville, in consideration of that payment and pursuant to the agreement, executed the formal "lien waiver" or "no-lien" certificate, which the Savings and Loan Association required, and he also wrote a letter to that association advising that "This will settle all but $1,000.00 which owner has agreed to remit." The lien waiver was delivered to the Savings and Loan Association, and in due course the loan proceeds in the amount of $21,500.00 were paid to Deville and credited to Chatelain's account. Deville also, pursuant to the agreement, promptly sent two carpenters and a painter to the Chatelain home to make the corrections or repairs which he had agreed to make, and those workmen worked five full days in Chatelain's home making those repairs. Deville feels that it corrected all of the defects in the house which it and Chatelain agreed should be made.

After Deville had signed the lien waiver and had incurred some expense in making the corrections which the parties had agreed upon, Chatelain stopped payment on the check for $1,429.91 which he had issued to Deville, and he has refused to pay plaintiff the amount of that check or any part of the $1,000.00 which had been withheld from the agreed contract price. Deville instituted this suit several months later, on September 25, 1972, to recover the $2,429.91 balance due on the contract.

Chatelain, in his amended answer, alleged generally that plaintiff had constructed this building with serious defects *431 and omittances, that the cost of correcting them would exceed the amount sued for by Deville, and that defendant is entitled to a set-off from the amount claimed. In that answer, Chatelain did not particularize any of the defects which he felt existed. In his reconventional demand, however, Chatelain alleged with particularity a number of defects and omittances.

At the trial evidence was offered by Chatelain to show the defects in construction which were alleged, and also to show defects other than those which were particularized in the reconventional demand. Plaintiff objected to any evidence tending to show defects or omittances which had not been alleged in the reconventional demand, basing that objection on the ground that such evidence tended to enlarge the pleadings. The trial judge admitted the evidence subject to the objection, but he eventually ruled that evidence as to defects not specified in the reconventional demand was not admissible. Considering only the evidence which he felt was admissible, the trial judge held that a balance of $2,429.91 was owed to Deville under the contract, but that Chatelain was entitled to credits or set-offs amounting to $1,069.00, and he accordingly rendered judgment in favor of plaintiff Deville for the remaining balance of $1,360.91.

We arrive at substantially the same result as did the trial judge, but we prefer to base our decision on different grounds. In our opinion, Chatelain is estopped from claiming a credit or set-off of more than $1,000.00, that being the amount which was withheld pursuant to the agreement entered into between the parties on March 14, 1972. Plaintiff thus is entitled to recover at least $1,429.91 from Chatelain. Since Deville has not appealed or answered the appeal, however, the award made to it by the trial judge cannot be increased. The judgment of the trial court thus should be affirmed.

We have considered the circumstance that under LSA-C.C.P. art. 1005 a plea or defense of estoppel is a special defense which must be set forth affirmatively in the answer, and that in this case plaintiff Deville has not affirmatively set forth estoppel in any of the pleadings it has filed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller Plastering, Inc. v. Amigo Building Corp.
20 So. 3d 1190 (Louisiana Court of Appeal, 2009)
Brian v. Jock Shop, Inc.
479 So. 2d 398 (Louisiana Court of Appeal, 1985)
Nicholson v. Grisaffe
436 So. 2d 763 (Louisiana Court of Appeal, 1983)
Metropolis, Inc. v. Hanson
434 So. 2d 1207 (Louisiana Court of Appeal, 1983)
Chambers v. PAROCHIAL EMPLOYEES'RETIREMENT SYSTEM
398 So. 2d 102 (Louisiana Court of Appeal, 1981)
Sam Marrs Equipment Co. v. C. & J. Painting & Sandblasting Co.
365 So. 2d 592 (Louisiana Court of Appeal, 1978)
Savoie v. Bills
317 So. 2d 249 (Louisiana Court of Appeal, 1975)
Porter v. Travelers Indemnity Company
313 So. 2d 641 (Louisiana Court of Appeal, 1975)
Verret v. Norwood
311 So. 2d 86 (Louisiana Court of Appeal, 1975)
G. J. Deville Lumber Co. v. Chatelain
313 So. 2d 239 (Supreme Court of Louisiana, 1975)
Humphries v. Puritan Life Insurance Company
311 So. 2d 534 (Louisiana Court of Appeal, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
308 So. 2d 428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gj-deville-lumber-company-inc-v-chatelain-lactapp-1975.