Miller Plastering, Inc. v. Amigo Building Corp.

20 So. 3d 1190, 9 La.App. 3 Cir. 237, 2009 La. App. LEXIS 1710, 2009 WL 3190346
CourtLouisiana Court of Appeal
DecidedOctober 7, 2009
Docket09-237
StatusPublished

This text of 20 So. 3d 1190 (Miller Plastering, Inc. v. Amigo Building Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller Plastering, Inc. v. Amigo Building Corp., 20 So. 3d 1190, 9 La.App. 3 Cir. 237, 2009 La. App. LEXIS 1710, 2009 WL 3190346 (La. Ct. App. 2009).

Opinion

COOKS, Judge.

FACTS

| iMiller Plastering, Inc. (Miller) entered into a written contract with Priola Construction Corporation (Priola) as a subcontractor to perform sheet rock, plastering, and acrylic wall coating work on barrack buildings owned by the U.S. Army Corps of Engineers (Corps) at Fort Polk. The general contractor for the work was Amigo Building Corporation (Amigo). Amigo and Priola had a contractual agreement whereby Priola was responsible for, among other things, the type of plastering and wall finishing work it sub-contracted to Miller. Under the contract between Priola and Amigo, the costs of superintendent labor and quality control management were specifically excluded from Priola’s responsibility. Nevertheless, both Amigo and Priola had employees on-site at all times while work was being performed by Miller, and both participated daily in quality control over the project including quality control over Miller’s work. At no time did any representative of Priola or Amigo, ever in any way, indicate to Miller that any of its work was unacceptable or not in compliance with the Corps of Engineers’ plans and specifications.

Before proceeding with its plaster and acrylic coating work, Miller prepared a sample which was approved by the Corps. After inadvertently covering over that sample, another sample was prepared by Miller and approved by the Corps. Amigo and Priola’s personnel observed the daily progress of Miller’s work and made no indication that the work was unacceptable to the Corps. In fact, at trial, witnesses for both Priola and Amigo testified they believed Miller’s work was in compliance with the Corps’ requirements, matched the approved sample, was not deficient, and did not 12need to be redone.

After Miller fully completed the work on Building No. 2273, the inspector for the Corps rejected Miller’s work and demanded it be redone. The Corps’ inspector threatened if Miller caused trouble over this demand he would make it difficult for Miller to proceed on the remaining work to be done under the main contract between Amigo and the Corps. Miller, believing it was useless to argue with the Corps’ quality control person, proceeded to redo the building in question.

All parties admit that Miller incurred substantial expense to redo the entire building. At no point did either Priola or Amigo object to Miller redoing the building. Apparently, none of these parties ever discussed who would bear the cost of the redo following the Corps’ demand. Amigo, as general contractor, and Priola, as sub-contractor, refused to pay Miller for the cost of redoing the building. Miller filed suit against Priola and Amigo but did not include the Corps in the suit. Neither Priola nor Amigo sought to make the Corps a party to this litigation. This casé previously came to our court on writs following the trial court’s denial of defendants’ Motion For Summary Judgment. Because the jurisdictional amount was below the required limit for jury trial the case was tried before a judge. The trial court ruled in favor of Miller and against Amigo and Priola awarding Miller damages equal to the expenses incurred for materials and labor, under the doctrine of equitable estoppel. Priola and Amigo appealed the decision asserting the trial court erred in applying the doctrine of equitable estoppel and in failing to apportion any amount of fault to the Corps and/or to Miller.

*1192 ANALYSIS

We review the trial court’s decision under the manifest error-clearly wrong [^standard of review. Stobart v. State through DOTD, 617 So.2d 880 (La.1993). In order to set aside the trial court’s findings of fact we must examine the record and determine that there is no reasonable factual basis for the trial court’s findings and that the trial court’s findings are clearly wrong. Id.

We find the record supports the findings of the trial court. Amigo clearly had responsibility for quality control of all work on the project. Both Amigo and Priola had personnel on-site daily observing Miller’s work and were indeed contractually obligated to provide such oversight. Miller was told the sample submitted was acceptable, and Miller proceeded to do its work in accordance with the approved sample. At no time did any employee or representative of Priola or Amigo express any concern to Miller about the quality or appropriateness of Miller’s work, nor did any representative of the Corps express any dissatisfaction with Miller’s work until after the work was completed on Building 2273. Both Priola and Amigo had constant contact with the Corps’ quality control person, Mr. Smith. Miller reasonably relied on Amigo’s and Priola’s silence as approval of his original work. Further, Miller reasonably relied on Amigo’s and Priola’s silence as it undertook to completely redo Building 2273 at the Corps’ insistence. Amigo was contractually bound in its contract with the Corps to give a satisfactory finished product subject to the Corp’s approval. Priola was contractually bound to give Amigo and the Corps a satisfactory product as well. Amigo and Priola’s failure to object to the Corps’ demand or to Miller’s efforts to comply with the Corps’ demand by redoing the work, prevents them from protesting now that the subsequent work was neither authorized nor required. Amigo and Priola direct our attention to article 8 of Miller’s contract, which provides:

|4Warranty. Subcontractor [Miller] warrants its work against all deficiencies and defects in materials and/or workmanship and agrees to satisfy same without cost to Owner [Corps] or Contractor [Priola] for a period of one (1) year from date of Substantial Completion of the Project or per Contract Document, whichever is longer.

The contract also provides in Article 2 that the Subcontractor (Miller) was to perform and complete its work in accordance with Contract Documents and “under the general direction of Contractor (Priola).” Additionally, an addendum to the contract dated November 14, 2001 reads as follows:

With respect to all services performed and to be performed under this agreement/contract by Miller for Priola, the latter is recognized as a statutory employer of Contractor’s employees, including but not limited to the Contractor’s direct employees, immediate employees and statutory employees.

Priola, by express written agreement, was the statutory employer of Miller’s employees performing the work on Building 2273 and provided constant supervision over those employees and the quality of their work as Priola’s contracts with Miller and Amigo required it to provide. Additionally, the president of Priola, Nieki Pri-ola, Jr., testified it was his understanding that Section 8 of the contract with Miller means that Miller would only have to redo his work at no cost if the work was defective or deficient. He further testified Miller’s work was not defective or deficient but simply was not to the Corps’ satisfaction.

Though not urged in its brief, Priola asserted at oral argument that the con *1193 tract between it and Miller required Miller to submit a change order before beginning the redo of building 2273. Article 4 of the noted contract states:

Contractor (Priola), without nullifying Agreement, may direct Subcontractor (Miller) in writing to make changes to Subcontractor’s work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Marshall Legacy Foundation
Louisiana Court of Appeal, 2024

Cite This Page — Counsel Stack

Bluebook (online)
20 So. 3d 1190, 9 La.App. 3 Cir. 237, 2009 La. App. LEXIS 1710, 2009 WL 3190346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-plastering-inc-v-amigo-building-corp-lactapp-2009.