Miller Plastering, Inc. v. Amigo Building Corporation

CourtLouisiana Court of Appeal
DecidedOctober 7, 2009
DocketCA-0009-0237
StatusUnknown

This text of Miller Plastering, Inc. v. Amigo Building Corporation (Miller Plastering, Inc. v. Amigo Building Corporation) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller Plastering, Inc. v. Amigo Building Corporation, (La. Ct. App. 2009).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

09-237

MILLER PLASTERING, INC.

VERSUS

AMIGO BUILDING CORPORATION & PRIOLA CONSTRUCTION CORPORATION

********** APPEAL FROM THE THIRTIETH JUDICIAL DISTRICT COURT PARISH OF VERNON, NO: 70,852 HONORABLE JOHN C. FORD, PRESIDING **********

SYLVIA R. COOKS JUDGE

**********

Court composed of Sylvia R. Cooks, Oswald A. Decuir, and James David Painter, Judges. PAINTER J. CONCURS IN THE RESULT. AFFIRMED.

Thomas P. LeBlanc Loftin, Cain, Gabb & LeBlanc, LLC 113 Dr. Michael Debakey Drive Lake Charles, LA 70601 (337) 310-4300 (337) 310-4400 COUNSEL FOR DEFENDANTS/APPELLANTS

Daniel G. Brenner David L. Roberson Bolen, Parker, Brenner, & Lee, Ltd. P.O. Box 11590 Alexandria, LA 71315-1590 (318) 445-8236 COUNSEL FOR PLAINTIFF/APPELLEE COOKS, Judge.

FACTS

Miller Plastering, Inc. (Miller) entered into a written contract with Priola

Construction Corporation (Priola) as a sub-contractor to perform sheet rock,

plastering, and acrylic wall coating work on barrack buildings owned by the U.S.

Army Corps of Engineers (Corps) at Fort Polk. The general contractor for the work

was Amigo Building Corporation (Amigo). Amigo and Priola had a contractual

agreement whereby Priola was responsible for, among other things, the type of

plastering and wall finishing work it sub-contracted to Miller. Under the contract

between Priola and Amigo, the costs of superintendent labor and quality control

management were specifically excluded from Priola’s responsibility. Nevertheless,

both Amigo and Priola had employees on-site at all times while work was being

performed by Miller, and both participated daily in quality control over the project

including quality control over Miller’s work. At no time did any representative of

Priola or Amigo, ever in any way, indicate to Miller that any of its work was

unacceptable or not in compliance with the Corps of Engineers’ plans and

specifications.

Before proceeding with its plaster and acrylic coating work, Miller prepared

a sample which was approved by the Corps. After inadvertently covering over that

sample, another sample was prepared by Miller and approved by the Corps. Amigo

and Priola’s personnel observed the daily progress of Miller’s work and made no

indication that the work was unacceptable to the Corps. In fact, at trial, witnesses for

both Priola and Amigo testified they believed Miller’s work was in compliance with

the Corps’ requirements, matched the approved sample, was not deficient, and did not

1 need to be redone.

After Miller fully completed the work on Building No. 2273, the inspector

for the Corps rejected Miller’s work and demanded it be redone. The Corps’ inspector

threatened if Miller caused trouble over this demand he would make it difficult for

Miller to proceed on the remaining work to be done under the main contract between

Amigo and the Corps. Miller, believing it was useless to argue with the Corps’ quality

control person, proceeded to redo the building in question.

All parties admit that Miller incurred substantial expense to redo the entire

building. At no point did either Priola or Amigo object to Miller redoing the building.

Apparently, none of these parties ever discussed who would bear the cost of the redo

following the Corps’ demand. Amigo, as general contractor, and Priola, as sub-

contractor, refused to pay Miller for the cost of redoing the building. Miller filed suit

against Priola and Amigo but did not include the Corps in the suit. Neither Priola nor

Amigo sought to make the Corps a party to this litigation. This case previously came

to our court on writs following the trial court’s denial of defendants’ Motion For

Summary Judgment. Because the jurisdictional amount was below the required limit

for jury trial the case was tried before a judge. The trial court ruled in favor of Miller

and against Amigo and Priola awarding Miller damages equal to the expenses

incurred for materials and labor, under the doctrine of equitable estoppel. Priola and

Amigo appealed the decision asserting the trial court erred in applying the doctrine

of equitable estoppel and in failing to apportion any amount of fault to the Corps

and/or to Miller.

ANALYSIS

We review the trial court’s decision under the manifest error-clearly wrong

2 standard of review. Stobart v. State through DOTD, 617 So.2d 880 (La.1993). In

order to set aside the trial court’s findings of fact we must examine the record and

determine that there is no reasonable factual basis for the trial court’s findings and

that the trial court’s findings are clearly wrong. Id.

We find the record supports the findings of the trial court. Amigo clearly

had responsibility for quality control of all work on the project. Both Amigo and

Priola had personnel on-site daily observing Miller’s work and were indeed

contractually obligated to provide such oversight. Miller was told the sample

submitted was acceptable, and Miller proceeded to do its work in accordance with

the approved sample. At no time did any employee or representative of Priola or

Amigo express any concern to Miller about the quality or appropriateness of

Miller’s work, nor did any representative of the Corps express any dissatisfaction

with Miller’s work until after the work was completed on Building 2273. Both

Priola and Amigo had constant contact with the Corps’ quality control person, Mr.

Smith. Miller reasonably relied on Amigo’s and Priola’s silence as approval of his

original work. Further, Miller reasonably relied on Amigo’s and Priola’s silence

as it undertook to completely redo Building 2273 at the Corps’ insistence. Amigo

was contractually bound in its contract with the Corps to give a satisfactory finished

product subject to the Corp’s approval. Priola was contractually bound to give

Amigo and the Corps a satisfactory product as well. Amigo and Priola’s failure to

object to the Corps’ demand or to Miller’s efforts to comply with the Corps’ demand

by redoing the work, prevents them from protesting now that the subsequent work

was neither authorized nor required. Amigo and Priola direct our attention to article

8 of Miller’s contract, which provides:

3 Warranty. Subcontractor [Miller] warrants its work against all deficiencies and defects in materials and/or workmanship and agrees to satisfy same without cost to Owner [Corps] or Contractor [Priola] for a period of one (1) year from date of Substantial Completion of the Project or per Contract Document, whichever is longer.

The contract also provides in Article 2 that the Subcontractor (Miller) was to

perform and complete its work in accordance with Contract Documents and “under

the general direction of Contractor (Priola).” Additionally, an addendum to the

contract dated November 14, 2001 reads as follows:

With respect to all services performed and to be performed under this agreement/contract by Miller for Priola, the latter is recognized as a statutory employer of Contractor’s employees, including but not limited to the Contractor’s direct employees, immediate employees and statutory employees.

Priola, by express written agreement, was the statutory employer of

Miller’s employees performing the work on Building 2273 and provided constant

supervision over those employees and the quality of their work as Priola’s contracts

with Miller and Amigo required it to provide.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Bank & Trust Co. v. Trinity Universal Insurance
205 So. 2d 35 (Supreme Court of Louisiana, 1967)
Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
John Bailey Contractor, Inc. v. State
425 So. 2d 326 (Louisiana Court of Appeal, 1983)
GJ Deville Lumber Company, Inc. v. Chatelain
308 So. 2d 428 (Louisiana Court of Appeal, 1975)
Wilkinson v. Wilkinson
323 So. 2d 120 (Supreme Court of Louisiana, 1975)
Humble Oil & Refining Company v. Boudoin
154 So. 2d 239 (Louisiana Court of Appeal, 1963)
Babin v. Montegut Insurance Agency, Inc.
271 So. 2d 642 (Louisiana Court of Appeal, 1972)
Rodden v. Davis
293 So. 2d 578 (Louisiana Court of Appeal, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Miller Plastering, Inc. v. Amigo Building Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-plastering-inc-v-amigo-building-corporation-lactapp-2009.