Ginger Light and James Justin Light v. Mike Thoma

CourtCourt of Appeals of Texas
DecidedJune 14, 2021
Docket07-20-00311-CV
StatusPublished

This text of Ginger Light and James Justin Light v. Mike Thoma (Ginger Light and James Justin Light v. Mike Thoma) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ginger Light and James Justin Light v. Mike Thoma, (Tex. Ct. App. 2021).

Opinion

In The Court of Appeals Seventh District of Texas at Amarillo

No. 07-20-00311-CV

GINGER LIGHT AND JUSTIN LIGHT, APPELLANTS

V.

MIKE THOMA, APPELLEE

On Appeal from the 99th District Court Lubbock County, Texas Trial Court No. 2019-534,943, Honorable William C. Sowder, Presiding

June 14, 2021 MEMORANDUM OPINION Before QUINN, C.J., and PARKER and DOSS, JJ.

Appellants, Ginger and Justin Light, appeal the trial court’s judgment awarding

damages to appellee Mike Thoma in the parties’ residential construction contract dispute.

On appeal, the Lights challenge the sufficiency of the evidence to support the damages

awarded to Thoma, the trial court’s finding that the Lights materially breached first, and

the trial court’s adverse finding that Thoma did not fraudulently file a mechanic’s and

materialman’s lien against the property. We affirm. Background

In August 2018, the Lights and Thoma entered into a fixed price construction

contract. Through it, Thoma agreed to build the couple’s home for $364,354. The fixed

price would be paid to Thoma through periodic draws when certain milestones or phases

of the construction were substantially completed.

Thoma proposed a draw request form and utilized it in draw requests 1 through 5.

Each were emailed to and approved by the Lights without complaint. Each was also paid

by the Lights. They totaled $224,423.02.

Also included in the Light-Thoma contract was a procedure for change orders.

They came into play when the Lights made revisions or additional requests that were not

included in the original agreement.

By February 5, 2019, Thoma submitted Draw Request #6 and demand for payment

on certain change orders. The Lights refused to pay either. They questioned the detail

or purported lack thereof in the draw request and maintained that they had paid for certain

items included in it. They communicated an offer to modify the contract, which offer

Thoma refused. That, coupled with their failure to resolve their differences, resulted in

Thoma forwarding them a default notice, calling off subcontractors, and ceasing work on

the project. He also sued the Lights for breach of contract, contending that they failed to

pay the draw request and change orders as required by their agreement. The Lights

counterclaimed for breach of contract and fraudulently filing a mechanic’s and

materialman’s lien. The Lights contend that Thoma failed to comply with the agreement’s

draw request procedure and failed to provide the quality and grade of workmanship and

materials as agreed upon in the contract.

2 Thoma sought damages in the form of the amount he was “in the hole” at that point

in the project. As he explained, the arrangement with the lender in this type of agreement

was to pay a certain percentage of the fixed price upon the builder’s substantial

completion of certain phases or “milestones” of the project. Its effect was to have the

contractor cover the construction expenses incurred in reaching that milestone. As

Thoma explained, he was either even or in the hole on a project until it approached

completion. Only as the project reached completion would he begin to realize a profit.

When Draw #6 was submitted, he had expended $249,767 and been paid only

$224,423.02 toward the fixed price. His lost profit also approximated $49,953.

Trial was to the bench. It was tasked with determining which of the two parties

breached first and concluded that the Lights did. That breach occurred when they refused

to pay the submitted draw request and change order. Damages of $24,750 were then

awarded to Thoma. They generally encompassed the difference between his

expenditures and the draws paid by the Lights. In turn, the claims asserted by the Lights

were denied.

Standards of Review

The standard of review is well-settled and need not be reiterated. It is adequately

explained in Tex. Outfitters Ltd., LLC v. Nicholson, 572 S.W.3d 647 (Tex. 2019), City of

Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005), and Cain v. Bain, 709 S.W.2d 175 (Tex.

1986) (per curiam).

Sufficiency of Evidence Concerning Breach

We first address whether Thoma materially breached the contract. In that regard,

the Lights posit:

3 this Court should reverse the district court’s decision and find that Thoma’s refusal was a material breach. Because he never actually provided a compliant draw request, the Lights’ obligation was never triggered. In the alternative, if Thoma’s performance was not material, then the Lights’ performance under the same provision should not be material either. Moreover, even if this Court were to disagree and find that Thoma’s compliance was not material, this Court should still reverse because the undisputed evidence shows that Thoma breached the Contract—whether material or not. As a result, the Lights were entitled to seek their damages against Thoma and at the least, offset Thoma’s damages.

We overrule the issue and begin by assessing the sufficiency of the evidence

underlying the trial court’s pertinent fact finding. The latter consisted of the court stating:

“Thoma did not commit a material breach of the Contract; the defects of Thoma’s

performance of which the Lights complained did not seriously impair the purposes

underlying the Contract.” Those defects consisted of his failure to include information

specified within paragraph 5(C) of the contract in his 6th draw request. The paragraph

said, among other things, that “each draw shall reflect the construction costs and any

compensation to the Builder for the time and effort expended in connection with this

transaction” and “[t]he Draw Request shall include the name and address of each person

who subcontracted directly with Builder and who Builder intends to pay from the

requested funds.” Such was omitted from the sixth request, just as it was from the prior

five. Yet, the Lights paid the prior five in short order and without demanding compliance

with 5(C).

Materiality is an issue “to be determined by the trier of facts.” Bartush-Schnitzius

Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 436 (Tex. 2017) (per curiam).

In making the determination, the Texas Supreme Court outlined a number of nonexclusive

considerations that are “significant in determining whether a failure to perform is material”:

4 (a) the extent to which the injured party will be deprived of the benefit which he reasonably expected;

(b) the extent to which the injured party can be adequately compensated for the part of that benefit of which he will be deprived;

(c) the extent to which the party failing to perform or to offer to perform will suffer forfeiture;

(d) the likelihood that the party failing to perform or to offer to perform will cure his failure, taking account of the circumstances including any reasonable assurances; [and]

(e) the extent to which the behavior of the party failing to perform or to offer to perform comports with standards of good faith and fair dealing.

Id. at 436–37 (Tex. 2017) (quoting Mustang Pipeline Co. v. Driver Pipeline Co., 134

S.W.3d 195, 199 (Tex. 2004) (per curiam)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
PAJ, Inc. v. Hanover Insurance Co.
243 S.W.3d 630 (Texas Supreme Court, 2008)
Aquaplex, Inc. v. Rancho La Valencia, Inc.
297 S.W.3d 768 (Texas Supreme Court, 2009)
Schafer v. Conner
813 S.W.2d 154 (Texas Supreme Court, 1991)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Criswell v. European Crossroads Shopping Center, Ltd.
792 S.W.2d 945 (Texas Supreme Court, 1990)
Texas Department of Public Safety v. Monroe
983 S.W.2d 52 (Court of Appeals of Texas, 1998)
Gulf States Utilities Co. v. Low
79 S.W.3d 561 (Texas Supreme Court, 2002)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Sandoval v. Commission for Lawyer Discipline
25 S.W.3d 720 (Court of Appeals of Texas, 2000)
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104 (Texas Supreme Court, 2010)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)
in Re the State of Texas, Relator
572 S.W.3d 264 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Ginger Light and James Justin Light v. Mike Thoma, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ginger-light-and-james-justin-light-v-mike-thoma-texapp-2021.