Gillioz v. City of Emporia

88 P.2d 1014, 149 Kan. 539, 1939 Kan. LEXIS 89
CourtSupreme Court of Kansas
DecidedApril 8, 1939
DocketNo. 34,023
StatusPublished
Cited by2 cases

This text of 88 P.2d 1014 (Gillioz v. City of Emporia) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gillioz v. City of Emporia, 88 P.2d 1014, 149 Kan. 539, 1939 Kan. LEXIS 89 (kan 1939).

Opinion

The opinion of the court was delivered by

HoCi-i, J.:

This action involves an arbitration award in a controversy between the city of Emporia and a contractor engaged to construct a dam for the city. The award contained fifteen items. The district court approved fourteen items and set one aside. The city appeals as to the fourteen items and the contractor as to the one.

The arbitration proceedings were conducted under the Kansas law relating to arbitration and therefore must be considered with regard to the statutory requirements. Not only did the construction contract provide for arbitration in case of dispute, but the “agreement of submission to arbitration,” entered into on July 17, 1937, between the city of Emporia and M. E. Gillioz, contractor, of Monett, Mo., provided that the controversy was submitted “in accordance with the provisions for arbitration, on pages 10 and 11 of said contract, and otherwise, in accordance with the laws of the state of Kansas in such cases made and provided,” and the parties specifically agreed “to make this submission to arbitration a rule of the district court of Lyon county, Kansas.”

Under the agreement the city chose E. B. Black, of the engineering firm of Black & Veatch, of Kansas City, Mo., as a member of the board; the contractor chose W. R. Holway, of Tulsa, Okla., and it was provided that these two should designate a third arbitrator. They chose D. A. MacCrea, of Little Rock, Ark., who was made chairman.

The matters submitted were definitely set out. The agreement recited that a controversy had arisen over “certain claims made by the contractor for compensation in addition to the amounts certified to him by the final estimate of the city’s engineers under said contract.” These “certain claims” consisted of fifteen separate items, which were marked “Exhibit A,” and by reference made a part of the submission agreement.

• The agreement provided that “The award made by the board of arbitrators herein shall be final and conclusive, and binding upon [541]*541both parties, as to all claims above mentioned, and as to all causes of action, except as otherwise provided in the statutes of the state of Kansas.”

The agreement further provided that the board should make its own rules governing procedure, and contained various provisions which will be noted later to the extent necessary for determination of the matters at issue.

The board was duly organized, held hearings at Emporia from August 23 to August 27 and on September 17, 1937, and on October 12, 1937, filed with the clerk of the district court of Lyon county its report and award, including its answers to special questions submitted by the city. Separate report was made on each item. Three were denied entirely, eight were reduced, three were fixed at the amount claimed and one was slightly increased. The total amount claimed was $37,832.26. The total amount awarded was $17,598.94. The report of the board was unanimous on all fifteen items.

It would serve no helpful purpose to recite here the various motions and other procedural steps taken. Suffice it to say that the matter was regularly heard by the district court of Lyon county and judgment entered. The court sustained the award on all items except item 12, which vras set aside. A slight correction agreed upon by the parties was made on item 14. Judgment was entered against the city in the sum of $16,807.35 with interest thereon at six percent from October 12, 1937, until paid.

In its motion to set aside the award the city alleged that—

“. . . said^award was illegally made, that said board illegally received evidence and based its award thereon, and violated and set aside terms and provisions of the submission agreement and of the construction contract, misbehaved and was biased and prejudiced against the city and was partial to the contractor, and that said award, in several items, is not based upon evidence. . .”

The city also contends that the trial court erred in rejecting certain evidence offered in support of its motion to set aside the award.

It is well to state at the outset two or three general rules of law here applicable. The first one is that the arbitration award having been made under the statute can only be set aside for reasons stated in the statute. (5 C. J. 200, 205; Russell v. Seery, 52 Kan. 736, 35 Pac. 812; Weir v. West, 27 Kan. 650; Thompson v. Barber, 87 Kan. 692, 125 Pac. 33.) The second one is that the report of the arbitrators is to be liberally construed and all reasonable- doubts resolved [542]*542in support of the award. (5 C. J. 205, 244; Russell v. Seery, 52 Kan. 736, 35 Pac. 812.)

The statute (G. S. 1935, 6-111) names three grounds upon which an award may be set aside: (1) Legal defects. (2) Fraud, corruption or other undue means. (3) Misbehavior of the arbitrators.

Before taking up the attacks upon the award itself, let us consider the city’s contention that the court erred in refusing to receive certain testimony offered in support of the motion to set aside the award. The court admitted in evidence all the files in the ease, the original construction contract, the arbitration agreement, the plans and specifications and certain other written exhibits offered by the city. The proffered evidence which was not admitted consisted of various exhibits and testimony that had been presented to the board during the hearings. No stenographic record of the proceedings before the board had been made. At the opening of the hearing the city asked that the testimony be taken down, but the board decided not to do so. Under the terms of the agreement it was clearly within the discretion of the board whether a stenographic record should be made. The court declined to admit testimony offered at the hearing on the ground that it was not the function of the court, under the arbitration statute, to hear de novo the matters heard by the board, and that it would be manifestly improper to receive and consider only part of the testimony when the whole record of the board’s proceedings was not available. The position of the trial court in this matter was correct. (5 C. J. 179, 181.) The court stated that it would receive any competent testimony to show that the award should be set aside for reasons'set out in the statute.

A preliminary issue may be disposed of before proceeding to the substantive questions. The contractor contends that the court was without jurisdiction to hear the city’s motion to set aside the award because it was not verified. The statute provides that the award may be set aside if any legal defects appear in the award or other proceedings, or if it is made to appear “on oath or affirmation, that said award or umpirage was obtained by fraud, corruption, or other undue means, or that said arbitrator or umpire misbehaved.” For several reasons the contention furnishes no basis for reversal. Whether the provision applies to pleadings or motions we need not here consider. No attack on the motion was made at the hearing on the ground that it was not verified. The matter was heard by [543]*543the court without objection and the question of verification was raised for the first time on this appeal. In any event, if error, it was harmless error.

We come to the real questions in issue — were there “legal defects” in the award, was there “fraud, corruption or other undue means” used, or was there proof of “misbehavior?” The second question may be summarily disposed of.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Professional Builders, Inc. v. Sedan Floral, Inc.
819 P.2d 1254 (Court of Appeals of Kansas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
88 P.2d 1014, 149 Kan. 539, 1939 Kan. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gillioz-v-city-of-emporia-kan-1939.