Gillam v. City of Centralia

128 P.2d 661, 14 Wash. 2d 523
CourtWashington Supreme Court
DecidedAugust 21, 1942
DocketNo. 28710.
StatusPublished
Cited by19 cases

This text of 128 P.2d 661 (Gillam v. City of Centralia) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gillam v. City of Centralia, 128 P.2d 661, 14 Wash. 2d 523 (Wash. 1942).

Opinion

Driver, J.

This is an action to recover compensation for damage to real property, by deprivation of access, light, and air, caused by the construction of a viaduct, or overcrossing, to separate the grade of a certain street in the city of Centraba from the grade of an intersecting railroad. The court, after trial without a jury, entered findings, conclusions, and judgment in favor of the plaintiff, and defendant city has appealed.

In the lower court, by demurrer and by answer, the issue was raised that the action had not been commenced within the time limited by law. That is the principal question presented on the appeal. It has a dual aspect, namely, (1) what statute of limitations applies; and (2) when did the statute begin to run?

*525 Respondent asserts that the action is governed by the three-year statute, while the appellant contends that the two-year catch-all statute is controlling. The two statutes, in so far as we need consider them here, read as follows:

“Within three years:
“1. An action for waste or trespass upon real property; . . .
“3. An action upon a contract or liability, express or implied, which is not in writing, and does not arise out of any written instrument; ...” Rem. Rev. Stat., §159 [P. C. §8166].
“An action for relief not hereinbefore provided for shall be commenced within two years after the cause of action shall have accrued.” Rem. Rev. Stat., § 165 [P. C. § 8172],

In support of its position, appellant cites Denney v. Everett, 46 Wash. 342, 89 Pac. 934, State ex rel. Whitten v. Spokane, 92 Wash. 667, 159 Pac. 805, and White v. King County, 103 Wash. 327, 174 Pac. 3 — all of which held that the two-year statute of limitations applied to an action against a municipality for damage to abutting property resulting from a change in grade of a street or highway. They were cited and followed in the later case of Island Lime Co. v. Seattle, 122 Wash. 632, 211 Pac. 285. That was an action by a real property owner to recover for damage from slides caused by the removal of lateral support in the regrading of a city street. Each of the foregoing decisions was based upon the premise that the property owner’s right of action against the municipality was one sounding in tort, and the court did not consider any portion of the three-year statute except subd. 1, relative to waste or trespass upon real property. As there had been no actual taking or direct physical invasion of the property, the court held that the action did not come within *526 that subdivision, and therefore concluded that the three-year statute did not apply. In none of the cases did the court consider the applicability of subd. 3 of the three-year statute.

In Jacobs v. Seattle, 100 Wash. 524, 171 Pac. 662, this court had held that a landowner’s suit to recover compensation for damage resulting from the operation of an incinerator by a city was an action on an implied contract or liability within subd. 3. Judge Parker, the author of the opinion,' pointed out very clearly that, when a city, in the exercise of its power of eminent domain, damages private property for public use, an action brought by the owner of the property against the city is not a tort action, but is based \ipon the implied promise of the city to compensate the owner, as the constitution expressly requires it to do.

Then subsequently, without mentioning Jacobs v. Seattle, both the White case and the Island Lime Company case followed the earlier tort theory decisions upon which appellant here relies. But all this was prior to the leading case of Wong Kee Jun v. Seattle, 143 Wash. 479, 255 Pac. 645. There, the city, in the regrade, of one of its streets, caused slide damage to adjacent property. It was held that the taking and damaging of such property was in contravention of the owner’s constitutional rights, and that it was not necessary for him to file a claim for damages against the city as a condition precedent to suit, as he would have been required to do in an action based upon acts of the city of a tortious nature only.

'Marshall v. Whatcom County, 143 Wash. 506, 255 Pac. 654, was decided at the same time as Wong Kee Jún v. Seattle, and Judge Tolman wrote the opinions in both cases. The Marshall case also was one in which property had been damaged by slides caused by the regrade of a city street, and the question arose as to *527 whether the landowner’s action came within the two-year or the three-year statute of limitations. Judge Tolman gave this concise and definite answer, p. 507:

“Those cases which apply the two-year statute are Island Lime Co. v. Seattle, 122 Wash. 632, 211 Pac. 285, and the cases there cited, which are based upon the tort theory, and since we held in the Wong Kee Jun case that the tort theory cannot be applied in any case where the right invaded is protected by the constitution, it follows logically that the three-year statute is the only one applicable. It was so held in Jacobs v. Seattle, 100 Wash. 524, 171 Pac. 662, L. R. A. 1918E 131, and we think that logically there is no escape from the conclusion that the two-year statute of limitations cannot be applied where the taking is by reason of the sovereign power, as held in the Wong Kee Jun case.”

In Docksteader v. Centralia, 3 Wn. (2d) 325, 100 P. (2d) 377, we held that the depriving of a landowner of access to his tract, by the construction of the identical viaduct involved in the present case, was a taking or damaging of private property within the constitutional inhibition. Since we have already decided in the Docksteader case that the taking or damaging now under consideration is one for which the constitution requires compensation to be made, it follows that, under the authority of Marshall v. Whatcom County, supra, the third subdivision of the three-year statute of limitations applies.

Having concluded that the three-year statute governs the case at bar, we shall now consider when the statute started to run. The viaduct, or overcrossing, was built pursuant to an agreement between appellant city, the state, and the railroad company, by the terms of which agreement the city undertook to furnish the necessary right of way. The actual construction was done by a private contractor under a contract with the state. The contract describes the work as

*528 "... clearing, grading, draining, surfacing with crushed stone and constructing a bituminous surface treatment and a reinforced concrete and steel over-crossing and treated pile and timber trestle, on City-Street, Railroad Overcrossing on Sixth Street in the City of Centralia, ...”

The viaduct runs east and west on Marion street, and the pile and timber trestle on the easterly approach extends across the entire southerly front of respondent’s lot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ed Schumacher v. City Of Aberdeen
Court of Appeals of Washington, 2020
Pacific Highway Park, Llc v. Dept. Of Transportation
Court of Appeals of Washington, 2014
C & G, Inc. v. Canyon Highway District No. 4
75 P.3d 194 (Idaho Supreme Court, 2003)
Federal Financial Co. v. Gerard
949 P.2d 412 (Court of Appeals of Washington, 1998)
Hoover v. Pierce County
903 P.2d 464 (Court of Appeals of Washington, 1995)
Farber v. State
630 P.2d 685 (Idaho Supreme Court, 1981)
Vern J. Oja & Associates v. Washington Park Towers, Inc.
569 P.2d 1141 (Washington Supreme Court, 1977)
Wickwire v. City & Borough of Juneau
557 P.2d 783 (Alaska Supreme Court, 1976)
Vern J. Oja & Associates v. Washington Park Towers, Inc.
549 P.2d 63 (Court of Appeals of Washington, 1976)
Brooks Investment Co. v. City of Bloomington
232 N.W.2d 911 (Supreme Court of Minnesota, 1975)
Cheskov v. Port of Seattle
348 P.2d 673 (Washington Supreme Court, 1960)
Ackerman v. Port of Seattle
348 P.2d 664 (Washington Supreme Court, 1960)
City of St. Louis v. Moehlenhoff
322 S.W.2d 155 (Missouri Court of Appeals, 1959)
Papac v. City of Montesano
303 P.2d 654 (Washington Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
128 P.2d 661, 14 Wash. 2d 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gillam-v-city-of-centralia-wash-1942.