Vern J. Oja & Associates v. Washington Park Towers, Inc.

549 P.2d 63, 15 Wash. App. 356, 1976 Wash. App. LEXIS 1407
CourtCourt of Appeals of Washington
DecidedApril 19, 1976
Docket2984-1
StatusPublished
Cited by7 cases

This text of 549 P.2d 63 (Vern J. Oja & Associates v. Washington Park Towers, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vern J. Oja & Associates v. Washington Park Towers, Inc., 549 P.2d 63, 15 Wash. App. 356, 1976 Wash. App. LEXIS 1407 (Wash. Ct. App. 1976).

Opinion

Farris, J.

The Lakeview Lanai, a 42-unit apartment building located in Seattle, was constructed in 1959 and purchased by Oja & Associates in 1964. Thereafter, Washington Park Towers, Inc., as owner of property adjacent to the Lakeview Lanai, entered into a contract with Cawdrey & Vemo, Inc., for the construction of a condominium apartment building. Cawdrey & Vemo engaged Manson Construction & Engineering Co. to drive the pilings necessary to support the planned building. Manson worked from August 1966 to September 1966. There was no construction activity at the site from September 1966 until October 1967. During this period, Cawdrey & Vemo and Manson were *358 relieved of their responsibilities. Work resumed on the project in the fall of 1967 and Larsen Construction Company completed the pile driving between approximately November 1967 and April 1968. The building was completed in 1969. Oja & Associates filed this action on March 2, 1971, to recover for damage allegedly sustained by the Lakeview Lanai as a result of the pile driving and other construction activity associated with the condominium apartment building. Washington Park Towers, Cawdrey & Vemo, Manson, Larsen, Fifth West, Inc., and R. C. Hedreen Co., Inc., were named as defendants. The claims against Cawdrey & Yerno and Manson were dismissed with prejudice on motions for summary judgment. On April 17, 1974, judgment was entered on a jury verdict against Washington Park Towers for $73,100. In a special verdict, the jury attributed 70 percent of the damage to the pile driving which occurred between August and September of 1966 and the remaining 30 percent to the pile driving which occurred between November 1967 and April 1968. Washington Park Towers appeals; Oja cross-appeals.

Washington Park Towers first assigns error to the refusal of the court to dismiss the cause on the ground that it is barred by the statute of limitations. Both parties agree that the 3-year limitation of RCW 4.16.080 applies, 1 but disagree as to the date that the cause of action accrued under RCW 4.16.010.

Washington Park Towers contends that the cause of action accrued immediately following the commencement of pile driving activities in August of 1966 when the first damage occurred and Oja had a right to apply to the courts for relief. See 51 Am. Jur. 2d Limitation of Actions § 109, at 681 (1970); Jones v. Jacobson, 45 Wn.2d 265, 269, 273 P.2d 979 (1954). It is also argued that, at the latest, the cause of *359 action accrued in September of 1966 when the initial pile driving ceased and the first substantial damage had occurred. See Cheskov v. Port of Seattle, 55 Wn.2d 416, 420-21, 348 P.2d 673 (1960). Thus, Washington Park Towers concludes that because the damage which resulted from the November 1967 to April 1968 pile driving was not different in kind nor greater in degree than the damage which resulted from the initial pile driving, the action for damages for both pile driving periods accrued, at the latest, in September of 1966 and is barred. See Cheskov v. Port of Seattle, supra at 420-21. Finally, even assuming that the pile driving activities constituted separate and distinct situations with a different cause of action arising from each, it is argued that the damages awarded should be reduced by 70 percent because the action on the initial pile driving is barred by the statute of limitations.

In response, Oja first refers to its complaint which alleges that the damage to the Lakeview Lanai was caused by the construction activities engaged in by Washington Park Towers in building its condominium apartment building. It is submitted that the construction activity was of a continuing nature and that Oja’s claim did not accrue until the building was completed in 1969. See Gillam v. Centralia, 14 Wn.2d 523, 529-30, 128 P.2d 661 (1942). See also Papac v. Montesano, 49 Wn.2d 484, 488-89, 303 P.2d 654 (1956). At the earliest, Oja submits that the accrual date for the action is April 1968 when all of the pile driving had been completed.

We have reviewed the Gillam, Papac and Cheskov decisions. While they all involve situations in which a governmental entity has damaged real property without first going through with a condemnation proceeding, that distinction is not determinative here. The general rule which emerges from those decisions is that if substantial damage has already occurred at the time the project is completed, the action accrues at that point. Papac v. Montesano, supra at 488, citing Gillam v. Centralia, supra. However, if the damage has not occurred when the project is completed, *360 the action accrues when the first substantial injury is sustained thereafter. Papac v. Montesano, supra at 488. The' pile driving activity here was all a part of the construction of the condominium apartment building. Although the jury found that 100 percent of the damages alleged flowed from the pile driving activity as a whole (even though it assigned percentages to each time period), nothing in the record persuades us that we should deviate here from the general rule that the cause of action accrued when the building was completed. Thus, since the complaint was filed within 3 years of the 1969 completion date, the statute of limitations does not bar Oja’s action.

In view of this holding, it is unnecessary to adjudicate the contentions by Washington Park Towers that (1) the diary of a certain witness is a physical fact which conclusively establishes that the Lakeview Lanai sustained no noticeable or continued damage after October 31, 1966, and (2) the trial court erred in refusing to grant its motion for a judgment n.o.v. or, in the alternative, a new trial on the ground that the proof offered by Oja relating to the termination date of the second period of pile driving was legally inadequate.

Washington Park Towers next argues that if the dismissal of the actions against Cawdrey & Vemo and Manson Construction & Engineering Co. was proper on the ground that the statute of limitations had expired, then it should also have the benefit of the statute of limitations shield. The basis of the argument is the general rule, as phrased by Washington Park Towers, that “a principal cannot be held derivatively responsible when the agent has been discharged.” Brief for Appellant at 17. See Doremus v. Root, 23 Wash. 710, 717, 63 P. 572 (1901). We disagree. The rule concerning derivative liability is more complex than as expressed by Washington Park Towers:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Felix W. Schuck v. Gordon Beck, et ux
Court of Appeals of Washington, 2021
Verrastro v. Bayhospitalists, LLC
208 A.3d 720 (Supreme Court of Delaware, 2019)
Vasquez v. Markin
731 P.2d 510 (Court of Appeals of Washington, 1986)
Byerly v. Madsen
704 P.2d 1236 (Court of Appeals of Washington, 1985)
Johnson v. Robert's Hawaii Tour, Inc.
664 P.2d 262 (Hawaii Intermediate Court of Appeals, 1983)
Vern J. Oja & Associates v. Washington Park Towers, Inc.
569 P.2d 1141 (Washington Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
549 P.2d 63, 15 Wash. App. 356, 1976 Wash. App. LEXIS 1407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vern-j-oja-associates-v-washington-park-towers-inc-washctapp-1976.