C & G, Inc. v. Canyon Highway District No. 4

75 P.3d 194, 139 Idaho 140, 2003 Ida. LEXIS 126
CourtIdaho Supreme Court
DecidedJuly 29, 2003
Docket28128
StatusPublished
Cited by25 cases

This text of 75 P.3d 194 (C & G, Inc. v. Canyon Highway District No. 4) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C & G, Inc. v. Canyon Highway District No. 4, 75 P.3d 194, 139 Idaho 140, 2003 Ida. LEXIS 126 (Idaho 2003).

Opinions

KIDWELL, Justice.

C & G, Inc. (C & G) sued the Canyon Highway District No. 4 (Highway District) for inverse condemnation after the Highway District built a road through C & G’s property without compensating C & G. The Highway District defended on the ground C & G failed to file its case within the statute of limitations period. However, the district court found the statute of limitations was not triggered until the Highway District completed the construction project, which brought C & G’s suit within the four-year limitation period. The Highway district failed to prove its other affirmative defenses and C & G was awarded damages, together with costs and attorney fees. The Highway District filed this appeal. The judgment of the district court is affirmed.

I.

FACTS AND PROCEDURAL BACKGROUND

C & G owns and operates a farm on 260 acres in Canyon County, Idaho. Martin Gal-vin (Martin) and Patricia Galvin (Patricia), husband and wife, are the only shareholders of C & G, each owning 50% of C & G’s shares. The Old Middleton Road, a winding road with two very sharp curves, ran north and south along the western edge of C & G’s property. By the early to mid 1980’s, the condition of the Old Middleton Road had deteriorated to the point that it was necessary to rebuild and resurface it. At various times between the mid 1980’s and early 1990’s, Martin and representatives of the Highway District discussed the possibility of moving the Old Middleton Road east so it would follow the north/south section line running through C & G’s property.

Based on a 1921 resolution by the Canyon County Commissioners, the Highway District believed it had a 50 foot easement, 25 feet on each side, over the section line. As a result of the alleged easement, the Highway District assumed it could build a road over the section line crossing C & G’s property without compensating C & G. C & G believed the Highway District’s representations regarding the easement without investigating further. In late 1991, the Highway District contracted with a surveyor to mark the location of a proposed New Middleton Road, which was to run north/south along the section line running through C & G’s property. On December 24,1991, the Highway District’s Board of Commissioners (Commissioners) approved construction of New Middleton Road. Due to the alleged easement, none of the affected property owners were compensated for their land.

Construction of the New Middleton Road began in January 1992. Patricia objected to construction of the road at all times relevant. According to the Highway District, Martin was involved in different aspects of the construction project, particularly in the relocation of irrigation canals required by the construction. In order to lessen the road’s grade, the Highway District asked C & G to grant more than the 50-foot easement along a portion of the road that traversed a steep hill on C & G’s property. C & G refused the Highway District’s request. By October 16, 1992, construction had progressed to the [142]*142point that the New Middleton Road’s alignment and width across C & G property were established. By November 6, 1992, the Highway District completed construction of the road’s subbase. The New Middleton Road was opened for public use in May 1993, but paving and oiling was not completed until August 1993.

In January 1997, C & G approached a surveyor about developing its property. At that time, C & G learned there was no easement for the road. On January 31,1997, C & G filed suit against the district seeking damages for inverse condemnation. On September 24, 1998, the Highway District filed a motion for summary judgment on the ground the applicable four-year statute of limitations, Idaho Code § 5-224 (2002), ran before C & G filed its complaint. On November 18, 1998, the district court granted the Highway District’s motion for summary judgment on the basis that, by November 6, 1992, construction on the road had progressed to the point that C & G was aware of the nature and extent of the taking of its property, triggering the limitation of action and placing C & G’s complaint beyond the four-year period.

On November 24, 1998, C & G filed a motion to reconsider, citing additional authority for the proposition that the statute of limitations did not begin running until May 1993, when the road was opened for public use. On January 13, 1999, the district court granted C & G’s motion for reconsideration on the ground the statute of limitations was not triggered until the Highway District completed construction of the road, which brought C & G’s complaint within the time period.

The parties stipulated to the facts of the case, including that the Highway District took 3.16 acres of C & G’s property for purposes of constructing the New Middleton Road. On December 20, 1999, the district court conducted a bench trial on the issues of the Highway District’s affirmative defenses of equitable estoppel, quasi estoppel, and waiver. On January 3, 2000, the district court entered its decision finding the Highway District failed to prove any of its affirmative defenses. On December 3, 2001, a jury trial began on the issue of the value of C & G’s condemned property. On December 12, 2001, based on the jury’s verdict, the district court entered a judgment in favor of C & G in the amount of $430,204.64. On February 21, 2002, the district court entered a judgment awarding attorney fees and costs to C & G.

The Highway District timely filed this appeal.

II.

STANDARD OF REVIEW

The date for when a cause of action accrues may be a question of fact or law. Jemmett v. McDonald, 136 Idaho 277, 279, 32 P.3d 669, 671 (2001) (citing Reis v. Cox, 104 Idaho 434, 660 P.2d 46 (1982)). If no disputed issues of material fact exist, when a cause of action accrues is a question of law for determination by this Court. Id.

This Court will only set aside the district court’s findings of fact if clearly erroneous. I.R.C.P. 52(a) (2002); McCray v. Rosenkrance, 135 Idaho 509, 513, 20 P.3d 693, 697 (2001); In re Williamson v. City of McCall, 135 Idaho 452, 454, 19 P.3d 766, 768 (2001). In deciding whether findings of fact are clearly erroneous, this Court determines whether the findings are supported by substantial, competent evidence. In re Williamson at 454, 19 P.3d at 768. Evidence is substantial and competent if a reasonable trier of fact would accept it and rely on it. Id. Findings based on substantial, competent evidence, even if conflicting, will not be disturbed on appeal. Bolger v. Lance, 137 Idaho 792, 794, 53 P.3d 1211, 1213 (2002).

III.

ANALYSIS

A. C & G’s Action For Inverse Condemnation Is Not Time Barred By The I.C. § 5-224 Limitation Of Action.

Neither party disputes the facts of this case. Therefore, whether C & G filed its inverse condemnation lawsuit within the stat[143]*143ute of limitations is a question of law over which this Court exercises free review.

I.C. § 5-224 contains the statute of limitations for an inverse condemnation claim. Wadsworth v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sommer v. Misty Valley, LLC
Idaho Supreme Court, 2021
Radford v. Van Orden
Idaho Supreme Court, 2021
Walsh v. Swapp Law
Idaho Supreme Court, 2020
Day v. Idaho Transportation Dept
533 P.3d 1227 (Idaho Supreme Court, 2020)
Vawter v. United Parcel Service, Inc.
318 P.3d 893 (Idaho Supreme Court, 2014)
Keybank National Ass'n v. Pal I, LLC
311 P.3d 299 (Idaho Supreme Court, 2013)
Justin S. Reynolds v. Trout, Jones, Gledhill, Fuhrman, P.A.
293 P.3d 645 (Idaho Supreme Court, 2013)
Prince George's County v. Longtin
19 A.3d 859 (Court of Appeals of Maryland, 2011)
Harris v. STATE EX REL. KEMPTHORNE
210 P.3d 86 (Idaho Supreme Court, 2009)
Grover v. Wadsworth
205 P.3d 1196 (Idaho Supreme Court, 2009)
Allen v. Reynolds
186 P.3d 663 (Idaho Supreme Court, 2008)
Ada County Highway District v. Total Success Investment, LLC
179 P.3d 323 (Idaho Supreme Court, 2008)
Darrel McCabe v. Olivia Craven
Idaho Court of Appeals, 2007
Atwood v. Smith
138 P.3d 310 (Idaho Supreme Court, 2006)
Hayden Lake Fire Protection District v. Alcorn
111 P.3d 73 (Idaho Supreme Court, 2005)
Short v. Singer Asset Finance Co.
107 F. App'x 738 (Ninth Circuit, 2004)
C & G, Inc. v. Canyon Highway District No. 4
75 P.3d 194 (Idaho Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
75 P.3d 194, 139 Idaho 140, 2003 Ida. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-g-inc-v-canyon-highway-district-no-4-idaho-2003.