GID Group, LLC v. Village of Algonquin

2026 IL App (2d) 250231-U
CourtAppellate Court of Illinois
DecidedMarch 2, 2026
Docket2-25-0231
StatusUnpublished

This text of 2026 IL App (2d) 250231-U (GID Group, LLC v. Village of Algonquin) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GID Group, LLC v. Village of Algonquin, 2026 IL App (2d) 250231-U (Ill. Ct. App. 2026).

Opinion

2026 IL App (2d) 250231-U No. 2-25-0231 Order filed March 2, 2026

NOTICE: This order was filed under Supreme Court Rule 23(b) and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

GID GROUP, LLC, Plaintiff-Appellant, v. VILLAGE OF ALGONQUIN, Defendant, (Christopher B. Burke Engineering, Ltd., Defendant-Appellee).

Appeal from the Circuit Court of McHenry County. Honorable Joel D. Berg, Judge, Presiding. No. 22-LA-303

JUSTICE MULLEN delivered the judgment of the court. Justices McLaren and Schostok concurred in the judgment.

ORDER

¶1 Held: Summary judgment for defendant was proper on plaintiff’s negligence claim based on damage to its property by fire that occurred while its water service was interrupted for a nearby construction project, where plaintiff pleaded that defendant was the general contractor on the construction project and directly involved in the interruption of the water service, allegations which were refuted by defendant. Plaintiff failed to amend its complaint and therefore its unpled theory of liability, based upon defendant assertedly breaching a voluntary undertaking as project engineer to assist impacted property owners like plaintiff, could not defeat the motion for summary judgment.

¶2 Plaintiff, GID Group, LLC (GID) appeals from an order entering summary judgment in

favor of defendant, Christopher B. Burke Engineering, Ltd. (Burke), on count III of GID’s

amended complaint, which sought recovery under a theory of negligence. We affirm. ¶3 I. BACKGROUND

¶4 GID’s complaint, as amended, alleged that it owned a parcel of improved commercial

property (GID’s property) in the Village of Algonquin (Village) and that it planned to remodel and

open a restaurant in the building on the property. GID alleged that, in 2021, the Village approved

GID’s permit application and its plans to remodel the building. During the same time frame, the

Village was engaged in a construction project adjacent to GID’s property. The project included

improvements to the Village’s municipal water service. According to the amended complaint,

Burke was the general contractor for the project. (Burke denied that allegation.) The complaint

alleged that, at some point, water service to GID’s property was disconnected or shut off “without

notice to GID.” The amended complaint also alleges that “[u]nbeknownst to GID, there was no

water service to the [p]roperty as of July 15, 2002,” when a fire started outside the building and

spread to the interior. The building’s sprinkler system did not function, and the fire caused

extensive damage.

¶5 The amended complaint consisted of four counts 1. Count III sought recovery from Burke

for negligence, alleging that Burke owed GID “a duty to exercise reasonable care in the

performance of [the construction project] to avoid interruption of water service to property owners

and users within the Village, including GID.” The amended complaint alleged that Burke breached

that duty by:

1 Counts I, II, and IV, which sought recovery from the Village for breach of contract and

negligence, were later dismissed and are not part of this appeal.

-2- “a. Directing or allowing its employees or subcontractors to disconnect or shut off

water service to [GID’s] [p]roperty without ensuring or providing for reinstatement of the

water service;

b. Otherwise directing or allowing the water service to [GID’s] [p]roperty to be

disconnected or shut off water [sic] without ensuring or providing for reinstatement of the

water service; or

c. Otherwise failing to take reasonable steps to ensure the continued provision of

water service to [GID’s] [p]roperty.”

¶6 Burke moved for summary judgment. The motion was directed towards refuting the

allegations in the amended complaint that it was the general contractor and had disconnected the

water at the GID property. Exhibits, attached to its motion included transcripts of various

depositions, are summarized below. Attached to the depositions were various documents, which

are discussed below.

¶7 Robert Mitchard (the Village’s public works director during the relevant time) testified that

he was familiar with a bike path and water main improvement project undertaken at a roundabout

connecting Main Street with Cary Road in Algonquin. He was also aware that the project required

the disconnection of water service to GID’s property so that the Village could install a new water

main. Mitchard believed the service to GID’s property was disconnected at the end of October

2021. One of the Village’s maintenance workers, Jason Miller, shut the water off at the valve box

but did not disconnect the pipes to GID’s property. Rather, those pipes were disconnected by

Martam Construction (Martam), the contractor. According to Mitchard, Martam employees

knocked on doors to notify property owners of the service disruption. However, he did not know

-3- how the owners of vacant property, like GID’s property, were notified. He would not expect Burke

to participate in the notification process.

¶8 Asked to describe Burke’s role in the construction project, Mitchard replied, “[Burke] was

the designer. They did *** Phase I engineering, Phase II engineering, and Phase III engineering.”

Asked if the Village has a process for notifying property owners when the Village wants them to

update their pipelines for a water connection, Mitchard replied, “The Village doesn’t make that

determination. That’s up to the property owner. We provide service up to the property line. What

happens after that is up to the property owner.” Mitchard testified that when the new water main

was installed, the Village ran a six-inch waterline to GID’s property line. He noted that, at one

time, the Village required that service for potable water and “fire service” use separate lines.

However, by the time the new water main was installed, the Illinois Plumbing Code required the

use of a single line to the owner’s property line for both types of water service. Property owners

were responsible for the pipelines on their property.

¶9 Mitchard sent a letter to Igor Gantea (one of GID’s owners) dated October 21, 2021, noting

that the parking lot for GID’s building was scheduled to be resurfaced in the coming weeks.

Mitchard recommended that, before the resurfacing, Gantea “hire a plumbing contractor to connect

[GID’s] water service to the newly installed water service stub under the buildings [sic] parking

lot.” The letter advised Gantea that the Village and the project’s contractor were available to meet

with Gantea and his contractor to review the location of the water main and the water service stub.

The letter further advised Gantea to contact Jeff Mysliwiec at Burke with any questions. Mitchard

never heard from Gantea, and he was unaware whether Gantea ever contacted Mysliwiec.

¶ 10 Gantea testified that when GID purchased the property, he opened an account for water

service from the Village. Gantea’s first contact with someone he believed to be from Burke was

-4- with a man whose name Gantea did not remember. Asked how he knew the person he spoke to

was associated with Burke, Gantea replied, “From his conversation.” Gantea’s “[f]irst

conversation” with the man occurred when “they was [sic] digging the road,” but Gantea did not

approximate a date. The man asked if “they” could deposit clay (presumably from the construction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Chicago HMO Ltd. of Illinois
730 N.E.2d 1119 (Illinois Supreme Court, 2000)
Cunis v. Brennan
308 N.E.2d 617 (Illinois Supreme Court, 1974)
Filliung v. Adams
899 N.E.2d 485 (Appellate Court of Illinois, 2008)
Marshall v. Burger King Corp.
856 N.E.2d 1048 (Illinois Supreme Court, 2006)
Simpkins v. CSX Transp., Inc.
2012 IL 110662 (Illinois Supreme Court, 2012)
Thompson v. Gordon
948 N.E.2d 39 (Illinois Supreme Court, 2011)
Claimsone v. Professional Property Management
2011 IL App (2d) 101115 (Appellate Court of Illinois, 2011)
Wolinsky v. Kadison
2013 IL App (1st) 111186 (Appellate Court of Illinois, 2013)
Lacey v. Perrin
2015 IL App (2d) 141114 (Appellate Court of Illinois, 2015)
Abramson v. Marderosian
2018 IL App (1st) 180081 (Appellate Court of Illinois, 2018)
Cole v. Chicago Transit Authority
2025 IL App (1st) 230797-U (Appellate Court of Illinois, 2025)
Sciarrone v. Village of Island Lake, Illinois
2025 IL App (2d) 240153 (Appellate Court of Illinois, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2026 IL App (2d) 250231-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gid-group-llc-v-village-of-algonquin-illappct-2026.