Gibbs Const. Co., Inc. v. Thomas

500 So. 2d 764, 1987 La. LEXIS 8259
CourtSupreme Court of Louisiana
DecidedJanuary 12, 1987
Docket86-C-1208
StatusPublished
Cited by24 cases

This text of 500 So. 2d 764 (Gibbs Const. Co., Inc. v. Thomas) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbs Const. Co., Inc. v. Thomas, 500 So. 2d 764, 1987 La. LEXIS 8259 (La. 1987).

Opinion

500 So.2d 764 (1987)

GIBBS CONSTRUCTION COMPANY, INC.
v.
A.C. THOMAS, et al.

No. 86-C-1208.

Supreme Court of Louisiana.

January 12, 1987.
Rehearing Denied February 12, 1987.

*765 Henry Dart, New Orleans, for applicant.

Henry Mestayer, A.D. Freeman, Satterlee, Mestayer & Freeman, New Orleans, for respondents.

COLE, Justice.

This is a suit for damages for nonperformance of a construction subcontract which existed between Gibbs Construction Company, and A.C. Thomas, doing business as L & L Painting and Drywall Company. Plaintiff Gibbs Construction Company (Gibbs) appeals from the judgment of the court of appeal, which found the contract null on the basis it contained a purely potestative condition. The primary issue is whether the defendant breached the contract by rescinding and refusing to perform, or whether the contract was null and void because of the existence of a purely potestative condition.

FACTS

On July 8, 1983, Gibbs, the general contractor, entered into a written subcontract with L & L. Under this subcontract L & L was to do the painting and drywall portion of construction of a 130-room motel at the intersection of I-10 and Bullard Road in New Orleans, Louisiana. As a condition of the subcontract, the owner of L & L, Mr. A.C. Thomas, was required to post a $25,000 letter of credit to Gibbs in lieu of a performance bond. The purpose of the letter of credit was to protect Gibbs from any default by L & L. The specific language of this provision, inserted in an addendum, reads as follows:

This contract is valid upon receipt of acceptable $25,000 letter of credit from a FDIC insured bank.

As stated by Gibbs and Thomas in their testimony, Thomas obtained the $25,000 letter of credit within a week after execution of the subcontract, but never delivered it to Gibbs.

Because of the order in which the motel was to be constructed and as a result of delays in construction, L & L was not to commence its portion of the work until December 1983 or January 1984. However, on November 10, 1983, Thomas wrote a letter rescinding the subcontract, stating his reasons were unavailability of materials and increased costs of acquisition. As a result of L & L's default, Gibbs was required to seek other means by which to get the work done, eventually performing some of the work itself and contracting with other subcontractors to perform the remainder. The total cost to Gibbs under this arrangement exceeded L & L's original contract price, and Gibbs seeks as damages the difference between the final collective cost and the original subcontract price agreed to by L & L.

The trial court found the subcontract to have been a conditional obligation subject to a suspensive condition. Because this suspensive condition never occurred, the court rendered judgment in favor of the defendant, finding Thomas not liable for breach of contract. The court of appeal affirmed, agreeing the subcontract contained a conditional obligation. However, this court ruled the suspensive condition was made up of two elements, the first of which was fulfilled. This was the procurement of the letter of credit. Not fulfilled, however, was the second element of the contracted condition, which required the actual receipt by Gibbs of the letter of credit. The court determined this second element constituted a purely potestative condition, due to it being totally within the power of Thomas to deliver or not. The court reasoned Thomas' refusal to surrender the letter of credit caused the simple suspensive condition of the first element to be transformed into a purely potestative condition, which made the contract null and void as a matter of law.

Gibbs in brief relies on three assignments of error. He first contends Thomas should not be able to rely on his own misdeeds *766 to defeat his obligations. La. Civ. Code art. 2040.[1] Secondly, he challenges the court of appeal characterization of the language in the addendum as a purely potestative condition. Finally, he argues the court of appeal erred in relying on the trial court's finding the suspensive condition had failed due to non-fulfillment. Because we find merit in all three assigned errors and find the defendant breached his contract, we reverse the judgments of the lower courts and remand for determination of quantum.

FIRST ASSIGNMENT OF ERROR

In Gibbs' initial assignment of error, he urges Thomas' actions in deliberately preventing fulfillment of the suspensive condition should result in the rule of La. Civ. Code art. 2040 being applied to Gibbs' benefit. Gibbs argues the suspensive condition of receipt of the letter of credit by him should thus be considered as having been fulfilled, and the contract should be enforceable.

La. Civ. Code art. 2040 provides as follows:

The condition is considered as fulfilled, when the fulfillment of it has been prevented by the party bound to perform it.

This Court has long recognized the proper interpretation of this article is "the condition is considered fulfilled, when it is the debtor, bound under that condition, who prevents the fulfillment." George W. Garig Transfer v. Harris, 226 La. 117, 75 So.2d 28 (1954); Southport Mill v. Friedrichs, 171 La. 786, 132 So. 346 (1931). This rule is an application of the long-established principle of law providing he who prevents a thing may not avail himself of the non-performance he has caused. This principle is derived from the premise one should not be able to take advantage of his own wrongful act. Cox v. Department of Highways, 252 La. 22, 209 So.2d 9 (1968); Walls v. Smith, 3 La. 498 (1832).

In George W. Garig Transfer, supra, the above rules of law were applied in a suit for damages for breach of a contract to sell a certificate of the Public Service Commission for a common carrier. The contract provided the transfer was conditioned upon approval by the Commission, and the buyer and seller filed a joint petition for transfer of the certificate. The seller withdrew his petition, however, and the Commission denied the transfer, stating it would have approved had the seller not withdrawn. The buyer sued the seller to be declared the owner of the certificate, and this Court ruled as follows:

We are also in full accord with the trial judge's view that the escrow agreement was a binding obligation on both parties, under the Civil law. True, it contained a suspensive condition, but "The contract of which the condition forms a part is, like all others, complete by the assent of the parties; * * *" LSA-C.C. Art. 2028, and "Every condition must be performed in the manner that it is probable that the parties wished and intended that it should be" LSA-C.C. Art. 2037; moreover, the condition is considered as accomplished when the debtor, bound under that condition, has prevented its accomplishment, Art. 2040.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fritscher v. Fritscher, II
M.D. Louisiana, 2025
S. Farm Bureau Life Ins. Co. v. Cox
247 So. 3d 999 (Louisiana Court of Appeal, 2018)
Collins v. Godchaux
86 So. 3d 831 (Louisiana Court of Appeal, 2012)
Tri-Lake of Louisiana, LLC v. Couteau Plateau LLC
59 So. 3d 491 (Louisiana Court of Appeal, 2011)
Mapp Construction, LLC v. Southgate Penthouses, LLC
29 So. 3d 548 (Louisiana Court of Appeal, 2009)
US EX REL. QUALITY TRUST v. Cajun Contractors
486 F. Supp. 2d 1255 (D. Kansas, 2007)
Amoco Production Co. v. Texaco, Inc.
838 So. 2d 821 (Louisiana Court of Appeal, 2003)
SUNRISE CONST. AND DEVELOPMENT CORPORATION v. Coast Waterworks, Inc.
806 So. 2d 1 (Louisiana Court of Appeal, 2001)
Central Louisiana Electric Co. v. Dolet Hills Mining Venture
116 F. Supp. 2d 726 (W.D. Louisiana, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
500 So. 2d 764, 1987 La. LEXIS 8259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbs-const-co-inc-v-thomas-la-1987.