City of Ruston v. Womack & Sons Construction Group, Inc.

CourtLouisiana Court of Appeal
DecidedNovember 15, 2023
Docket55,328-CA
StatusPublished

This text of City of Ruston v. Womack & Sons Construction Group, Inc. (City of Ruston v. Womack & Sons Construction Group, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Ruston v. Womack & Sons Construction Group, Inc., (La. Ct. App. 2023).

Opinion

Judgment rendered November 15, 2023. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 55,328-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

CITY OF RUSTON Plaintiff-Appellant

versus

WOMACK & SONS Defendants-Appellees CONSTRUCTION GROUP, INC.

Appealed from the Third Judicial District Court for the Parish of Lincoln, Louisiana Trial Court No. 61,968

Honorable Thomas Wynn Rogers, Judge

LAW OFFICES OF RUSSELL Counsel for Appellant ALAN WOODARD, JR., LLC By: Russell Alan Woodard, Jr.

KEAN MILLER, LLP Counsel for Appellees By: Michael D. Lowe G. Trippe Hawthorne Thomas D. Bourgeois, Jr.

Before THOMPSON, ROBINSON, and MARCOTTE, JJ.

ROBINSON, J., dissents with written reasons. THOMPSON, J.

In the middle of a large-scale construction project to create a sports

complex, the city of Ruston was faced with a difficult business decision

regarding the synthetic field turf playing surfaces on some of the baseball

fields. It could either stay the course on the original design, which would

delay the completion date and cause it to lose out on hosting a lucrative

inaugural event, or it could modify the design plan to complete the project

timely, which option included a request from the contractor for additional

construction funds for the new design. The city elected the modified

construction design and faster completion date, signed a change order for the

revision, and paid the requested added cost for the revision. The project was

completed on time, and the city hosted the event, resulting in an economic

boon for the city and area businesses. Subsequently, the city sought to

recover the additional costs it paid to the contractor, which, in turn, argued

that a clause in the construction contract acted as a final settlement for all

claims regarding the change order and that it is not required to refund the

funds paid for the revision to the project. The trial court granted a summary

judgment in favor of the contractor, and the city appealed. For the reasons

set forth below, we affirm the trial court.

FACTS AND PROCEDURAL HISTORY

In an effort to expand recreational facilities, generate economic

impact for the region and tax revenue for itself, the City of Ruston (the

“City”) contracted to host the 2019 Dixie World Series. To host this and

potential future large-scale events, the City designed and put out for bid the

Ruston Sports Complex, which comprised of four different complexes and facilities, and included 16 baseball fields. On August 31, 2017, the City

awarded the approximately $35,000,000 public construction contract to

build the complex on U.S. Highway 167 South in Ruston (the “Project”) to

Womack & Sons Construction Group, Inc. (“Womack”). The architect for

the Project was Yeager, Watson & Associates, LLC (“YWA”). This dispute

arises from that part of the Project concerning the construction of the

synthetic field turf playing surfaces on some of the fields. The Project had a

425-day deadline, to enable the City to satisfy its contractual obligations to

host the Dixie League World Series in July, 2019. The World Series was

anticipated to generate over $6,000,000 in economic impact.

On September 26, 2017, the parties executed a written contract

outlining their rights and obligations on the Project. The contract is a

standard form contract prepared by the American Institute of Architects,

known as the AIA Document A101-2007, Standard Form of Agreement

between Owner and Contractor (the “Contract”). Several other documents

were incorporated into the Contract. Article 1 of the Contract describes the

other documents, including (1) Conditions of the Contract (General,

Supplementary, and other Conditions), (2) Drawing Specifications, (3)

Addenda issued prior to execution of this Agreement, and (4) Modifications

issued after execution of this Agreement, “all of which form the Contract,

and are as fully a part of the Contract as if attached to this Agreement or

repeated herein.” The General Conditions are on a standard-form document

prepared by the American Institute of Architects-AIA Document A201-

2007, General Conditions of the Contract for Construction (the “General

2 Conditions”). The Supplementary Conditions were prepared by YWA and

were included within the Project Manual.

The General Conditions allowed for changes to be made to the

Contract during construction, a commonly anticipated occurrence in large

construction projects. Article 7 of the General Conditions provided:

Changes in the Work may be accomplished after execution of the Contract, by Change Order, Construction Change Directive or order for a minor change in the Work, subject to the limitations stated in this Article 7 and elsewhere in the Contract Documents.

Article 7.1.2 of the General Conditions states that “a Change Order

shall be based upon agreement among the Owner, Contractor and Architect.”

Article 7.2.1 defines a Change Order as:

A Change Order is a written instrument prepared by the Architect and signed by the Owner, Contractor and Architect stating their agreement upon all of the following:

.1 The Change in the Work; .2 The amount of adjustment, if any, in the Contract Sum; and .3 The extent of the adjustment, if any, in the Contract Time.

As noted above, the Supplementary Conditions modify the General

Conditions. Article 7.2 of the Supplementary Conditions adds Subparagraph

7.2.2 to Article 7.2 of the General Conditions, and states:

Agreement on any change order shall constitute a final settlement of all matters relating to the change in the Work which is the subject of the Change Order, including, but not limited to all direct and indirect costs associated with such change and any and all adjustments to the Contract Sum and the Contract Time. In the event a Change Order increases the Contract Sum, Contractor shall include the Work covered by such Change Order in Applications for Payment.

There were five change orders executed in connection with the

Project. The change order at issue in the present matter is Change Order No.

3 2, which was executed in February of 2019. Change Order No. 2 directed

Womack to make 16 changes to the project. It added 139 days to the

contract time to accommodate the changes and inclement weather. The

original contract sum was increased by $1,779,682.33 to address the

modifications outlined in Change Order No. 2. YWA prepared and executed

Change Order No. 2 on February 6, 2019. Womack executed it on February

7, 2019, and the City executed it on February 18, 2019. It was recorded in

Lincoln Parish on February 22, 2019.

Change Order No. 2 was required for the Project in order to correct a

problem with the subsurface installed under the turf fields in five of the

baseball fields at the sports complex. Womack had hired a subcontractor,

GeoSurfaces (“Geo”), to install the subsurface base and the turf fields in

accordance with the original contract. The Project design originally called

for compacted dirt, topped with a geomembrane liner, a drainage pad, and

rock. The turf was to be placed on top of the subsurface.

In the late fall of 2018, Geo and Womack discussed the fact that there

was a leak in the geomembrane liner of five of the fields from rain. The

record reflects an email between Womack and Geo, wherein Womack states

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prejean v. Guillory
38 So. 3d 274 (Supreme Court of Louisiana, 2010)
Gibbs Const. Co., Inc. v. Thomas
500 So. 2d 764 (Supreme Court of Louisiana, 1987)
Wolf v. Louisiana State Racing Com'n
545 So. 2d 976 (Supreme Court of Louisiana, 1989)
Giron v. Housing Auth. of City of Opelousas
393 So. 2d 1267 (Supreme Court of Louisiana, 1981)
Campbell v. Melton
817 So. 2d 69 (Supreme Court of Louisiana, 2002)
Sequoia Venture No. 2, Ltd. v. Cassidy
968 So. 2d 806 (Louisiana Court of Appeal, 2007)
Peironnet v. Matador Resources Co.
144 So. 3d 791 (Supreme Court of Louisiana, 2013)
Jackson v. City of New Orleans
144 So. 3d 876 (Supreme Court of Louisiana, 2014)
Walton v. Burns
151 So. 3d 616 (Louisiana Court of Appeal, 2013)
Reynolds v. Bordelon
172 So. 3d 607 (Supreme Court of Louisiana, 2015)
Bilyeu v. National Union Fire Insurance Co. of Pittsburgh
184 So. 3d 69 (Louisiana Court of Appeal, 2015)
Schultz v. Guoth
57 So. 3d 1002 (Supreme Court of Louisiana, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
City of Ruston v. Womack & Sons Construction Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-ruston-v-womack-sons-construction-group-inc-lactapp-2023.