Gering - Fort Laramie Irrigation District v. Baker

606 N.W.2d 826, 8 Neb. Ct. App. 1001, 2000 Neb. App. LEXIS 21
CourtNebraska Court of Appeals
DecidedFebruary 8, 2000
DocketA-98-1247
StatusPublished
Cited by1 cases

This text of 606 N.W.2d 826 (Gering - Fort Laramie Irrigation District v. Baker) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gering - Fort Laramie Irrigation District v. Baker, 606 N.W.2d 826, 8 Neb. Ct. App. 1001, 2000 Neb. App. LEXIS 21 (Neb. Ct. App. 2000).

Opinion

Buckley, District Judge, Retired.

INTRODUCTION

On August 19,1997, Gering - Fort Laramie Irrigation District (district) filed a petition against John T. Baker, doing business as Baker & Associates (Baker), and Marie G. Smith, alleging professional negligence. Baker and Smith filed a motion for summary judgment on October 9, 1998, alleging that the district failed to comply with the applicable statute of limitations, Neb. Rev. Stat. § 25-222 (Reissue 1995). The district then filed a second amended petition on October 21. The district court permitted Baker and the district to submit additional affidavits on November 4. The district court sustained Baker’s motion for summary judgment on November 5. The district appeals. We reverse.

BACKGROUND

In March 1992, the district entered into a contract with Baker to design and oversee the construction of the relocation of irrigation structures along Highway 92 west of Scottsbluff, Nebraska.

Pursuant to that agreement, Baker assigned Smith to be the resident project representative. Smith was a civil engineer, reg *1003 istered with the State of Nebraska since 1975. Smith was responsible for the design and supervision of the district’s structure relocation project and worked for Baker from 1991 to 1996. Paul Reed Construction & Supply, Inc., was hired as the contractor responsible for the actual construction of the project.

Under the agreement between Baker and the district, Baker was expected to supply, in addition to the resident project representative, assistants to aid in overseeing the project. Smith and other employees were required to supervise the work of the contractor and provide information to Baker regarding the contractor’s compliance with the project specifications and deadlines.

According to the uncontradicted evidence submitted by Baker, 100 percent of the actual construction was completed on August 25, 1993. Baker certified the construction project complete on April 5, 1994. During the spring of 1993, the district discovered a leak in a concrete pipe near station 378, but this leak was not in the PVC joints constructed by the contractor. Shortly after finding this leak, another was discovered in the same general area but near the “new bar pit.” Ricky L. Preston, general manager of the district, was unsure what caused this leak, but stated it was fixed by pouring a concrete collar around the area.

The district first discovered a leak in the bend joints in the PVC pipe in the spring of 1994 near station 407. When the district excavated, Preston observed that at the transition point where the PVC pipe changes directions, the two PVC pipes were field cut and wrapped in duct tape. The duct tape was then covered with a concrete collar and wire reinforcement, instead of being joined with a prefabricated PVC coupler. The district did not contact Baker or the contractor regarding the leak, but, instead, fixed it itself. In order to fix the problem, the district replaced the concrete collar with a prefabricated PVC coupler. Preston stated that at that time, he believed that the particular joint was not properly constructed but did not give it much thought, and that he thought there might have been a flaw or something.

Preston testified in his deposition that sometime in June, approximately 2 weeks after the spring 1994 leak was repaired, the district discovered a second leak at approximately station *1004 412. The leak was not causing any damage, and the district decided not to shut down the line at that time. The district excavated the leak near station 412 in the fall of 1994. However, the testimony surrounding the discovery of this leak was unclear. It is difficult to ascertain the nature of the leak, and Preston appeared extremely confused regarding the dates involved.

During the fall of 1996, the district found another leak in a PVC joint. The joint was excavated on November 6, 1996, and found to also be constructed with a concrete collar. The district verbally notified the contractor of the problem. The contractor fixed the joint and backfilled the area. Neither the district nor Baker inspected the repair.

Preston contacted Baker in November 1996 and spoke with an engineer, Barry Swanson. Preston explained that he had discovered a leak in the PVC pipe and had discovered that the bend had been constructed with a concrete collar. Swanson told Preston that the construction was improper. Swanson recalls that they discussed the possibility that there might have been other such improper joints and that they should put the contractor on formal notice. Swanson agreed to draft a letter to the contractor regarding the PVC joint excavated on November 6 and the fact that the joint was repaired without being inspected.

Swanson stated that he delivered the letter to Preston and discussed the contents with him. According to Swanson, Preston wanted the letter to be examined by the district’s attorney before being mailed to the contractor. Swanson checked with Preston on at least one occasion to see if the letter had been approved and forwarded to the contractor and was told that it had not been forwarded. Swanson said he never received directions to send the letter to the contractor, and therefore, it was never mailed. Although Preston stated he did not specifically recall advising Swanson that the district’s attorney had reviewed the letter and that it needed to be mailed to the contractor, he stated that he had a signed copy of the letter in his files. The copy he had faxed to the attorney had been unsigned. According to Leo Temple, corporate secretary of the contractor, the letter was never received by the contractor.

A third PVC joint was excavated on June 4, 1997, after the district discovered a clogged pipeline in the area. This joint was *1005 also constructed with duct tape and a concrete collar rather than prefabricated PVC couplers. The district advised the contractor of the problem via a letter dated June 9, 1997. The letter essentially notified the contractor that the construction of the PVC joints did not meet contract requirements and that the district expected the contractor to rectify the situation. It also stated that according to the engineer, the concrete collars were not authorized by him. The contractor responded that all of the PVC joints or bends had been constructed with concrete collars instead of prefabricated PVC couplers. The contractor further stated that the use of the concrete collars was approved by Smith. Based on pay estimates, the district suspected that approximately 40 joints were constructed in this manner.

All of the joints or bends in question were below ground. The file maintained by Baker for the project contained a memorandum from Smith to Preston purporting to enclose a new “marked up” set of plans for the Department of Roads, among other documents. These would have been the “as-built” drawings. The district alleges that it never received the as-built drawings from Baker. However, Smith testified that a copy of the as-built plans was submitted to the Department of Roads’ Bridgeport construction office.

ASSIGNMENTS OF ERROR

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gering - Fort Laramie Irrigation District v. Baker
612 N.W.2d 897 (Nebraska Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
606 N.W.2d 826, 8 Neb. Ct. App. 1001, 2000 Neb. App. LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gering-fort-laramie-irrigation-district-v-baker-nebctapp-2000.