Gering - Fort Laramie Irrigation District v. Baker

612 N.W.2d 897, 259 Neb. 840, 2000 Neb. LEXIS 158
CourtNebraska Supreme Court
DecidedJune 30, 2000
DocketS-98-1247
StatusPublished
Cited by91 cases

This text of 612 N.W.2d 897 (Gering - Fort Laramie Irrigation District v. Baker) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gering - Fort Laramie Irrigation District v. Baker, 612 N.W.2d 897, 259 Neb. 840, 2000 Neb. LEXIS 158 (Neb. 2000).

Opinion

Meller-Lerman, J.

NATURE OF CASE

Gering - Fort Laramie Irrigation District filed a petition in the district court for Scotts Bluff County against John T. Baker, doing business as Baker & Associates (Baker), and Marie G. Smith, alleging professional negligence in connection with a project relocating irrigation structures along Highway 92, west of Scottsbluff, Nebraska. Baker and Smith filed a motion for summary judgment on October 9, 1998, claiming that the district failed to comply with the 2-year professional negligence statute of limitations, Neb. Rev. Stat. § 25-222 (Reissue 1995). The district thereafter filed a second amended petition on October 21, and the district court permitted the parties to submit additional affidavits. The district court concluded the action was time barred and that the doctrine of fraudulent concealment was unavailable to the district. The district court sustained Baker and Smith’s motion for summary judgment on November 5.

The district appealed to the Nebraska Court of Appeals, which reversed the district court’s grant of summary judgment based in part on the Court of Appeals’ determination that a genuine issue of material fact existed as to whether the district’s discovery of one improperly constructed joint would lead a reasonably prudent person to inquire regarding the construction of the *842 remaining joints. Gering - Ft. Laramie Irr. Dist. v. Baker, 8 Neb. App. 1001, 606 N.W.2d 826 (2000). Baker and Smith petitioned for further review of the Court of Appeals’ decision. We granted Baker and Smith’s petition for further review and now reverse the Court of Appeals’ decision.

STATEMENT OF FACTS

A more complete recital of the underlying facts in this case may be found in the Court of Appeals’ opinion, Gering - Ft. Laramie Irr. Dist. v. Baker, supra. The facts of particular relevance on further review are summarized herein.

The district hired Baker to design and oversee the construction of the relocation of irrigation structures near Scottsbluff, Nebraska. Baker assigned Smith, an engineer employed by Baker, to design the project and to provide construction supervision. Paul Reed Construction & Supply, Inc., was hired as the contractor responsible for the actual construction. The contractor was not named as a defendant in this action. Construction was substantially completed on August 25,1993. Baker certified the construction project complete on April 5, 1994.

The record in this case contains an affidavit of Smith which establishes that Smith prepared payment estimate No. 7 covering cost overruns and underruns for the relocation project for the period June 26 to August 25, 1993. Payment estimate No. 7 noted, among other things, that 37 “concrete bends,” or joints, had been used in the structure relocation project during this period. The record also contains a copy of a letter dated November 24, 1993, from Ricky Preston, general manager of the district, to Jim Jensen, district engineer for the State Department of Roads, enclosing copies of several documents, including payment estimate No. 7 containing the reference to the 37 concrete bends.

The district discovered a leak in the joints in the PVC pipe near station 407 in the spring of 1994. When the district excavated, Preston observed that at the transition point where the PVC pipe changes directions, the two PVC pipes were field cut and wrapped in duct tape. The duct tape was then covered with a concrete collar and wire reinforcement, instead of utilizing a prefabricated PVC coupler to join the ends of the PVC pipe. The *843 district did not contact Baker or the contractor regarding the leak, but fixed the leak itself by replacing the concrete collar with a prefabricated PVC coupler. In his deposition testimony, Preston admitted that at the time he inspected the joint for the district in the spring of 1994, he determined that the joint was not properly constructed. Preston further stated that he did not give any thought as to whether other joints were similarly constructed.

Approximately 2 weeks after the leak near station 407 was repaired, a second leak became apparent at another point in the system. As the leak was not causing damage, the district decided not to shut down the line. The site of this leak was not excavated nor was the leak repaired at this time.

The district found another leak in a PVC joint in the fall of 1996. The joint was excavated on November 6, 1996, and found to be improperly constructed. The district notified the contractor, which fixed the joint and backfilled the area. Neither the district nor Baker inspected the repair. Preston contacted Baker at that time and spoke with an engineer who told Preston that the construction Preston described was improper, that there might have been other such improperly constructed joints, and that the district should put the contractor on formal notice.

An additional PVC joint was excavated on June 4,1997, after the district discovered a clogged pipeline in the area. This joint was also found to be improperly constructed. The district advised the contractor of the problem by letter dated June 9, 1997. The contractor responded that all of the PVC joints or bends had been constructed in the same manner and that use of that method of construction had been approved by Smith. The district filed the present professional negligence action against Baker and Smith on August 19. Following entry of summary judgment in favor of Baker and Smith, the district appealed to the Court of Appeals, which reversed the district court. Baker and Smith filed a petition for further review, which we granted.

ASSIGNMENTS OF ERROR

On further review, Baker and Smith assert the Court of Appeals erred in reversing the district court’s order which had concluded the action was time barred and had granted summary *844 judgment. Specifically, Baker and Smith claim the Court of Appeals erred in (1) holding that discovery of one defective joint did not constitute discovery as a matter of law under § 25-222 and therefore reversing the district court’s order, which had determined that the district discovered its cause of action within the 2-year period of the statute of limitations and (2) reversing the district court’s grant of summary judgment on the issue of fraudulent concealment.

STANDARDS OF REVIEW

In reviewing a summary judgment, an appellate court views the evidence in a light most favorable to the party against whom the judgment is granted and gives such party the benefit of all reasonable inferences deducible from the evidence. Sherrets, Smith v. MJ Optical, Inc., ante p. 424, 610 N.W.2d 413 (2000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Konecne v. Abram, LLC
319 Neb. 966 (Nebraska Supreme Court, 2025)
Dondlinger v. Nelson
305 Neb. 894 (Nebraska Supreme Court, 2020)
Bonness v. Armitage
305 Neb. 747 (Nebraska Supreme Court, 2020)
Wehrer v. Dynamic Life Therapy & Wellness
302 Neb. 1025 (Nebraska Supreme Court, 2019)
Wehrer v. Dynamic Life Therapy & Wellness, P.C.
302 Neb. 1025 (Nebraska Supreme Court, 2019)
Bruna v. Bradford & Coenen
Nebraska Court of Appeals, 2014
Guinn v. Murray
Nebraska Supreme Court, 2013
Steen v. Murray
955 F. Supp. 2d 1030 (D. Nebraska, 2013)
Auto Services Co., Inc. v. KPMG, LLP
537 F.3d 853 (Eighth Circuit, 2008)
Inman v. Nebraska Methodist Hosp.
754 N.W.2d 767 (Nebraska Court of Appeals, 2008)
Anonymous v. Vasconcellos
727 N.W.2d 708 (Nebraska Court of Appeals, 2007)
Manker v. Manker
644 N.W.2d 522 (Nebraska Supreme Court, 2002)
Sack Bros. v. Tri-Valley Cooperative, Inc.
616 N.W.2d 786 (Nebraska Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
612 N.W.2d 897, 259 Neb. 840, 2000 Neb. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gering-fort-laramie-irrigation-district-v-baker-neb-2000.