Gerard v. Salter

304 P.2d 237, 146 Cal. App. 2d 840, 1956 Cal. App. LEXIS 1546
CourtCalifornia Court of Appeal
DecidedDecember 14, 1956
DocketCiv. 5284
StatusPublished
Cited by18 cases

This text of 304 P.2d 237 (Gerard v. Salter) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerard v. Salter, 304 P.2d 237, 146 Cal. App. 2d 840, 1956 Cal. App. LEXIS 1546 (Cal. Ct. App. 1956).

Opinion

*842 .GRIFFIN, J.

This appeal concerns the validity of awards of a board of arbitrators and the court's order confirming the awards, in consolidated actions Numbers 62436, In the Matter of the Arbitration between Sherman E. Salter and Corinne Gerard, and action Number 62557, Corinne Gercurd v. Sherman E. Salter. The arbitration concerned numerous matters arising out of the contractual work of the builder, respondent Salter, in the construction of a building for the appellant Gerard. The contract was signed on May 2, 1953, for the construction of a commercial building in Laguna Beach. Disagreements arose as to the charge for extras, the quality of workmanship and related matters. Under a provision in the original contract each party appointed one arbitrator who in turn appointed a third. They consisted of one Clarke, Hodgdon and Anderson. The builder claimed approximately $2,000 for extras. On December 10, 1953, they determined that Salter was entitled to a total of $1,760.09, less certain credits, leaving the amount of $1,262.29 due the contractor. They made their award in writing and delivered it to the parties. On March 30, 1954, Salter filed an application in the superior court for an order confirming the award of the arbitrators. Appellant Gerard made certain objections thereto and the matter came on for hearing before the trial court. It was stipulated that the entire matter be -referred back to the same arbitrators for reconsideration and consolidation with case Number 62557 which was an action for damages for $8,000 for breach of contract, claiming that the building had not been built in a proper manner and the contractor had failed to complete it within the time prescribed. The stipulation was not too specific but the court’s minutes show that it was stipulated and ordered that the two cases be consolidated and treated as one matter and that the parties proceed under the arbitration sections of the code (Code Civ. Proc., § 1280 et seq.). The reporter’s transcript shows that respective counsel agreed that the same arbitrators be used and that all matters having heretofore been gone into and all new matters raised in the separate action be submitted to them and they were then to make their findings and report back to the court on the entire matter. Thereafter the three arbitrators met at various places, including the building itself, took evidence for several days, and many witnesses were sworn and examined. It was agreed by them that the former award of $1,262.29 in case Number 62346 for extras, would *843 stand and made written findings to this effect. The findings then recite that the • arbitrators have not reached a unanimous decision with regard to the question of Mrs. Gerard’s claim arising under case Number 62557, and in this regard two members of the board of arbitration, Hodgdon and Anderson, found that the owner, Mrs. Gerard, was not entitled to any of those claims since it was their opinion that Mr. Salter performed all the work in a manner required of him to be done according to his contract and according to the plans and specifications which are a part of the contract; that the other member of the board, Clarke, reserved the right to hand in a minority decision or report on this question. “Therefore, a majority of the Board hereby agrees that the owner, Mrs. Gerard, is not entitled to any damages from the contractor.” All did agree on the amount of fees each arbitrator should have but made no mention of attorneys’ fees, interest or other costs. This finding was signed by all three arbitrators, although it was not acknowledged by Clarke. No minority report was filed by Clarke. On motion to confirm the awards and to fix attorneys’ fees, objections were filed by appellant claiming that the question of damages in action Number 62557 was outside the scope of the power of the arbitration board, outside of the provisions of the original contract regarding arbitration, and that appellant believed the arbitration agreement required that the award of damages in this case, if any, must be agreed upon by all three arbitrators; that this award was secured through fraud; that arbitrators Anderson and Hodgdon were guilty of misconduct and were biased and prejudiced and that they all met, as arbitrators, and in effect agreed that they would take no action on the damage element of the case but would refer that matter back to the court, and without the consent or knowledge of one arbitrator, the other two entered a new and different decision denying damages. Further objection was made that the allowance of $750 as attorneys’ fees was excessive and unauthorized. Evidence was taken by the trial court on the objections made and the award was affirmed as reported by the arbitrators. Interest was allowed by the court from December 10, 1953, the date of the first award by the arbitrators in case Number 62436, including an allowance of $750 as attorneys’ fees. Appellant claims on this appeal that the court erred in so doing.

We see no merit to the first claim that the arbitrators _ had no power or jurisdiction to determine the issues presented *844 by the agreement and the subsequent stipulation and order of the court respecting the damage action. The issues were fairly submitted by stipulation to arbitrators for determination under section 1280 et seq. of the Code of Civil Procedure. No action was ever taken in the court by appellant to be relieved of the stipulation. No sufficient revocation is indicated as suggested by section 1280 of the Code of Civil Procedure. A hearing was had, findings were made, and the court, after a full consideration of the entire matter, adopted those findings and rendered judgment in accordance with them. Once a controversy is submitted to arbitration, it remains before the arbitrators until they have completed their determination of the matter, unless the parties mutually agree to withdraw it. Thus, when the parties agree upon an umpire and to abide by his decision, neither of them, without the consent of the other, may, in the absence of fraud, withdraw the question of performance from the common arbiter for the purpose of referring it to a court or jury. (5 Cal.Jur.2d 100, § 26; Church v. Shanklin, 95 Cal. 626 [30 P. 789, 17 L.R.A. 207].)

Complaint is next made that the award was not made by all three arbitrators. If appellant’s stipulation could be interpreted, as may well be, that the arbitrators were proceeding under the original written agreement pertaining to the appointment and service of the arbitrators in respect to both actions, by its very terms, the finding of two out of three of their number was sufficient. If appellant relies upon the statute indicated in the stipulation, section 1053 of the Code of Civil Procedure is also applicable. It provides that when there are three arbitrators all must meet, but two of them may do any act which might be done by all. In the absence of any contractual agreement or stipulation of submission between the parties on the subject, the statutory provisions would be applicable. (Pacific Fire Rating Bureau v. Bookbinders, etc. Union, 115 Cal.App.2d 111, 114 [251 P.2d 694] ; Bierlein v. Johnson, 73 Cal.App.2d 728, 733 [

Related

Milder v. ADR Services CA2/5
California Court of Appeal, 2024
Flores v. Kertel Communications, Inc. CA5
California Court of Appeal, 2022
Norcal Mutual Insurance Company v. Newton
100 Cal. Rptr. 2d 683 (California Court of Appeal, 2000)
Moncharsh v. Heily & Blase
832 P.2d 899 (California Supreme Court, 1992)
Tate v. Saratoga Savings & Loan Assn.
216 Cal. App. 3d 843 (California Court of Appeal, 1989)
Remole v. Sullivan
20 V.I. 434 (Supreme Court of The Virgin Islands, 1984)
Cabus v. Dairyland Insurance Co.
656 P.2d 54 (Colorado Court of Appeals, 1982)
Helzel v. Superior Court
123 Cal. App. 3d 652 (California Court of Appeal, 1981)
Arrieta v. Paine, Webber, Jackson & Curtis, Inc.
59 Cal. App. 3d 322 (California Court of Appeal, 1976)
City of Sunrise v. Inman, Inc.
307 So. 2d 860 (District Court of Appeal of Florida, 1975)
Allstate Insurance v. Shmitka
12 Cal. App. 3d 59 (California Court of Appeal, 1970)
Precision Automotive v. Northern Ins. Co.
252 Cal. App. 2d 1036 (California Court of Appeal, 1967)
Goossen v. Adair
185 Cal. App. 2d 810 (California Court of Appeal, 1960)
Ulene v. Murray Millman of California, Inc.
346 P.2d 494 (California Court of Appeal, 1959)
Downer Corp. v. Union Paving Co.
342 P.2d 64 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
304 P.2d 237, 146 Cal. App. 2d 840, 1956 Cal. App. LEXIS 1546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerard-v-salter-calctapp-1956.