Gerald R. Rouillard, III, d/b/a International Gear Technologies

Armed Services Board of Contract Appeals·Decided October 8, 2014·No. ASBCA No. 58459·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Gerald R. Rouillard, III, d/b/a ) ASBCA No. 58459 International Gear Technologies ) ) Under Contract No. SPM7MC-10-M-2339 )

APPEARANCE FOR THE APPELLANT: Steven J. Boretos, Esq. Everett, WA

APPEARANCES FOR THE GOVERNMENT: Daniel K. Poling, Esq. DLA Chief Trial Attorney Matthew 0. Geary, Esq. Co Ileen T. Loughran, Esq. Trial Attorneys DLA Land and Maritime Columbus, OH

OPINION BY ADMINISTRATIVE JUDGE PAUL ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

This is a timely appeal of a contracting officer's (CO' s) final decision terminating appellant Gerald R. Rouillard, III, d/b/a International Gear Technologies' (IGT's) supply contract for default. The Contr.act Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, is applicable. The government has filed a motion for summary judgment. IGT opposes the government's motion; it has not filed a cross-motion. We grant the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 8 December 2009, the Defense Supply Center, Columbus, Ohio (Maritime Supply Chain) (DSSC) issued request for quotations (RFQ) No. SPM7MC-l 0-0302 for the purchase of 445 spur gears, National Stock Number (NSN) 3020-00-888-0130 (R4, tab 87 at 4, 6). The RFQ included a procurement history for this NSN, dating back to 10 July 2007. As awarded, unit costs for the earlier contracts ranged from $106.00 to

1 The government filed separate motions for summary judgment in ASBCA Nos. 58458 and 58459; however, appellant's opposition brief and the government's reply brief dealt jointly with the two appeals. Because the facts of each appeal differ, the Board is issuing separate decisions. $210.95. (Id. at 2) The RFQ also contained a first article test (FAT) requirement which consisted of one additional unit (id. at 6).

2. The government's estimated unit price was $119.81. It received quotations with unit prices ranging from $110.25 to $490.00. IGT quoted a unit price of $110.25. The next two lowest offerors quoted unit prices of$1l1.00 and $112.70. (R4, tab 88) 2

3. On 1 February 2010, DSSC awarded Contract No. SPM7MC-10-M-2339 to appellant for the supply of 317 spur gears at a unit price of $107.75 and $110.25 for 128 spur gears. Within 120 days, IGT was also required to submit a First Article (FA) at a unit price of$1,250. The total fixed-price contractual amount was $50,152.75. (R4, tab 1at1, 3, 5-6) As awarded, the FA unit was to be delivered 120 days after date of the order or by 1 June 2010, and the remaining spur gears were to be delivered by 6 June 2011 (id. at 5-6).

4. The contract contained FAR 52.209-4, FIRST ARTICLE APPROVAL- GOVERNMENT TESTING (SEP 1989). Also included in the contract were FAR 52.233-1, DISPUTES (JUL 2002); and FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE (APR 1984). (R4, tab 1at9, 11)

5. IGT did not deliver the FA by 1 June 2010 (R4, tabs 5-6). As of 20 October 2011, IGT still had not delivered the FA. On that date appellant notified the CO that it had "found an issue with the root diameter of the gear teeth on the first article part, we need to either request a waiver, or furnish another first article from a second lot we had started months ago." (R4, tab 44 at 4)

6. On 3 January 2012, the CO issued bilateral Modification No. P00003 to the contract. It established a new FA delivery date of 17 February 2012 and extended the delivery date for the 445 spur gears to 26 ,July 2012. (R4, tab 53) The modification also provided that failure of the FAT would result in termination of the contract for default (id.).

7. IGT did not deliver the FA by 17 February 2012. On 1March2012, appellant advised the CO that the FA unit had been completed (R4, tab 56 at 2). On 1 April 2012, IGT stated in an email to the CO: "When I get to my office tomorrow I will send you the FAT tracking info" (R4, tab 57). On 3 April 2012, appellant forwarded the promised information to the CO (R4, tab 58 at 1-2). On 10 April 2012, the CO stated that he had "checked the tracking and apparently they have not shipped yet" (R4, tab 59 at 2). On 12 April 2012, IGT stated: "I will be back in the office tomorrow to resolve FAT shipment, yes, we do have a large lot of parts waiting to ship once FAT is approved" (R4,

2 In the "ABSTRACT OF QUOTES," appellant's bid was coded as "CAGE" "5HFP7" (R4, tab 88).

2 tab 60). As of 18 April 2012, the FA still had not been completed (R4, tab 61at3); and as of 3 May 2012, it had not been shipped (R4, tab 64 at 2-3).

8. On 14 June 2012, the FA unit was conditionally approved (R4, tab 67). On 20 June 2012, the CO forwarded the notice of conditional approval to IGT, noting six discrepancies. He also requested by attached letter that appellant inform him of a revised delivery date for "the production supplies" by 25 June 2012. (R4, tab 69 at 1, 3)

9. IGT did not comply with this request; and, on 26 June 2012, the CO again requested the delivery schedule by close of business on that day (R4, tab 71). On that same date, appellant responded that it would forward "a complete schedule" by 29 June 2012. He also stated: "I can tell you that we have separated 50 from a 160 piece lot and are expediting the 50 pieces for shipment asap." (R4, tab 72) On 28 June 2012, IGT advised the CO that it would ship 50 units "around July 20th" (R4, tab 76 at 1). On 9 July 2012, the CO, once again, requested a complete delivery schedule (R4, tab 77 at 1).

10. On 11July2012, Mr. Gerry Rouillard, III, IGT's president, forwarded a lengthy letter to the CO in which he alleged that as a result of various increased costs, its actual unit cost was $276.79, as opposed to the contractual prices of $107.75 and $110.25 (SOF ~ 3). He also contended that, as a part of IGT's bid, he had relied on his father for "a large number of volunteer hours." Unfortunately, as a result of a heart condition, the elder Mr. Rouillard had been unable to work on the contract. Finally, IGT alleged that there had been a mutual mistake when it formulated its bid. Alleging that it had paid $1,680 for inspection of a single unit, appellant described the $1,500 payment to the government contained in a modification to another contract as an inspection fee, and concluded that it had grossly underestimated the actual costs of producing the spur gears. (R4, tab 78)

11. On 16 July 2012, the CO forwarded the following response to Mr. Rouillard:

In response to your 7/11/12 request for a price increase on contract SPM7MC10M2399 for NSN number 3020-00-888-0130, your request is hereby denied.

This is a firm fixed price contract. Your proposal in response to RFQ SPM7MlOQ0302 offered a set unit price. The subject contract was awarded accordingly. You are obligated to perform to the terms of the contract.

Within 5 calendar days from the date of this notice, you are requested to advise the undersigned in writing whether you will continue to perform the subject contract in accordance

3 with the existing terms and conditions. Failure to respond by [sic] will lead to termination for default proceedings.

The Government is not invoking its rights under FAR 52.249-8 - - Default (Fixed-Price Supply and Service), at this time. Please be advised, however, that notice of intention not to perform, or failure to perform, under the provisions of the contract may result in the subject contract being terminated for default, subject to the notice provisions of the default clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Gerald R. Rouillard, III, d/b/a International Gear Technologies, (asbca 2014).

Gerald R. Rouillard, III, d/b/a International Gear Technologies (Gerald R. Rouillard, III, d/b/a International Gear Technologies) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related