Georgia Power Co. v. Georgia Public Service Commission

396 S.E.2d 562, 196 Ga. App. 572
CourtCourt of Appeals of Georgia
DecidedJuly 13, 1990
DocketA90A0494, A90A0495
StatusPublished
Cited by39 cases

This text of 396 S.E.2d 562 (Georgia Power Co. v. Georgia Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia Power Co. v. Georgia Public Service Commission, 396 S.E.2d 562, 196 Ga. App. 572 (Ga. Ct. App. 1990).

Opinions

Beasley, Judge.

Pursuant to OCGA § 50-13-20, we here review a decision of the superior court made under OCGA § 50-13-19 (h) and the case law construing it.

On April 2, 1987, Georgia Power Company (the Company) filed its request for a rate increase of approximately $805 million with the Public Service Commission (PSC) to recoup its share of the approximately $6.3 billion investment in Unit 1 of the Plant Vogtle nuclear generating plant. This was the largest rate request ever submitted to the commission and resulted in its longest proceedings — 42 days of hearings over five months, producing over 12,000 pages of transcripts and 502 exhibits. An increase of approximately $464 million was authorized.

The appeal revolves around the rate base. The PSC denied rate recognition of $951 million of the Company’s submitted costs. The superior court affirmed, and the Company disputes $896 million of the superior court’s affirmance. The significance of the disallowances is that they substantially reduce the figure on which the rate increase is computed, to the Company’s detriment.

The trial court in a comprehensive, detailed order described the issues, the facts which it decided were supported by evidence, the related law, and the court’s rationale with respect to each issue. It is most helpful and provides the opportunity for an intelligent review, because it gives the specific foundations for its rulings. See Atlanta Transit System v. Harcourt, 94 Ga. App. 503 (95 SE2d 41) (1956), regarding awards of the State Board of Workers’ Compensation; the same applies to any appealable order.

The American Association of Retired Persons (AARP), one of numerous intervenors in the proceedings, appeals the affirmance of the PSC’s findings based in part on alleged ex parte communications and the superior court’s failure to reopen the record to allow evidence of that issue.

Case No. A90A0495 (AARP)

1. The initial order of the PSC was issued October 1, 1987. AARP moved for reconsideration, but it did not include any ground based on the allegedly improper ex parte communications. On the same day, another intervenor, Consumers’ Utility Counsel, filed a motion which included the allegation of ex parte communications. The motion was [573]*573not adopted or joined by AARP. Both motions were denied. The PSC supplemented its original order thereafter, and appeal to the superior court ensued.

Although filing a motion for reconsideration before the agency is not a prerequisite to superior court review, “no objection to any order or decision of any agency shall be considered by the court upon petition for review unless such objection has been urged before the agency.” OCGA § 50-13-19 (c).

The court correctly held that AARP’s failure to raise the issue before the PSC precluded the court’s consideration of it. “The authorization to the superior court set forth in [OCGA § 50-13-19 (g)] to hear evidence relating to alleged irregularities in procedure before the agency that are not shown in the record is an exception to the principle that review by the superior court shall be confined to the record but is not an exception to the principle stated in [OCGA § 50-13-19 (c)] requiring objections to agency decisions or orders to be urged in the first instance before the agency.” Georgia Real Estate Comm. v. Burnette, 243 Ga. 516 (1) (255 SE2d 38) (1979). See Georgia Public Svc. Comm. v. Southern Bell, 254 Ga. 244, 247 (327 SE2d 726) (1985); State Bd. of Equalization v. Trailer Train Co., 253 Ga. 449, 450 (320 SE2d 758) (1984); North Fulton &c. Hosp. v. State Health &c. Agency, 168 Ga. App. 801, 803 (1) (310 SE2d 764) (1983).

Since AARP failed to present the issue to the agency, it is not necessary to address the substantive arguments presented.1

Case No. A90A0494 (Georgia Power Company)

A construction budget request for Plant Vogtle was originally proposed by the Company in 1971, when power demands were increasing and the need for additional sources of energy was being addressed nationwide. During this period, planning, proposing, and construction startup were occurring for many of the nuclear plants now in existence or later cancelled. The original construction budget for Plant Vogtle was $660 million. It was to be a four-unit plant with two units optional for later expansion.

The Company served as its own construction manager2 during the project, selecting as architect/engineer the Bechtel Corporation. Significant design responsibilities for the Nuclear Steam Supply System and the piping hanger system were assigned to Southern Com[574]*574pany Services, a component of the Southern Company, the parent of Georgia Power Company, and Westinghouse. The project was to follow the “design-build” or “fast track” method; i.e., no full project design existed as the project began but was being prepared contemporaneously.3

The cost estimate continued to escalate until 1973, when it was made even higher by the oil embargo and general economic conditions. By October 1977, the estimate was $2.7 billion and the projected start date for commercial operation of Unit 1 slipped to November 1984.

In March 1979, the Three Mile Island accident occurred, increasing regulation and oversight of such plants by the Nuclear Regulatory Commission. In October 1979, the Phase I Definitive Estimate based on site drawings and projected manhour and material costs was raised to $3.4 billion. Cost increases and schedule slips continued. By July 1985 the estimate hit $8.4 billion. Although costs rose even higher, the Company agreed in March 1986 to cap the costs in its rate request at $8.4 billion.

The Company’s appeal alleges eight enumerations, five of which (1, 2, 3, 4, & 6) deal with three categories of costs disallowed by the PSC and affirmed by the court: 1) embed plate fabrication and installation and 2) batch plant operations, both of which impacted the schedule of the project (the $516 million schedule disallowance), and 3) costs attributable to the Company’s imprudence in managing the productivity of its work force (the $380 million productivity disallowance).

Two enumerations (7 & 8) cite error in the court’s not requiring the PSC to explain why it did not offset alleged benefits to customers resulting from the delay in completion and the decision to attempt to minimize delay at the expense of productivity.

Enumeration 5, addressed first, alleges error in the trial court’s failure to hold that the admission of the expert opinion testimony of John Orr on productivity was error.

2. In July 1985, because of the overruns and schedule problems experienced at Plant Vogtle, the PSC retained the consulting firm of O’Brien-Kreitzberg & Associates (OKA) to examine the prudence of the Company’s management of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GEORGIA POWER COMPANY v. AMY N. CAZIER
Court of Appeals of Georgia, 2021
C&M Enterprises of Georgia, LLC v. Williams.
816 S.E.2d 44 (Court of Appeals of Georgia, 2018)
Amy N. Cazier v. Georgia Power Company
793 S.E.2d 668 (Court of Appeals of Georgia, 2016)
Albert Guyton Davis v. State
Court of Appeals of Georgia, 2013
Davis v. State
746 S.E.2d 890 (Court of Appeals of Georgia, 2013)
Excelsior Electric Membership Corp. v. Georgia Public Service Commission
745 S.E.2d 870 (Court of Appeals of Georgia, 2013)
Karen Taylor v. State
Court of Appeals of Georgia, 2013
Taylor v. State
740 S.E.2d 327 (Court of Appeals of Georgia, 2013)
Anthony Hargis v. State
Court of Appeals of Georgia, 2012
Hargis v. State
735 S.E.2d 91 (Court of Appeals of Georgia, 2012)
In Re Dd
713 S.E.2d 440 (Court of Appeals of Georgia, 2011)
In the Interest of D. D.
713 S.E.2d 440 (Court of Appeals of Georgia, 2011)
Jackson Electric Membership Corp. v. Georgia Public Service Commission
668 S.E.2d 867 (Court of Appeals of Georgia, 2008)
Professional Standards Commission v. Alberson
614 S.E.2d 132 (Court of Appeals of Georgia, 2005)
Gwinnett County v. Lake Lanier Ass'n
593 S.E.2d 678 (Court of Appeals of Georgia, 2004)
General Motors Acceptance Corp. v. Jackson
542 S.E.2d 538 (Court of Appeals of Georgia, 2000)
Georgia Public Service Commission v. ALLTEL Georgia Communications Corp.
536 S.E.2d 542 (Court of Appeals of Georgia, 2000)
Municipal Electric Authority v. Georgia Public Service Commission
525 S.E.2d 399 (Court of Appeals of Georgia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
396 S.E.2d 562, 196 Ga. App. 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-power-co-v-georgia-public-service-commission-gactapp-1990.