George Weis Co. v. Stratum Design-Build, Inc.

227 S.W.3d 486, 2007 Mo. LEXIS 116, 2007 WL 1953428
CourtSupreme Court of Missouri
DecidedJuly 6, 2007
DocketSC 88194
StatusPublished
Cited by8 cases

This text of 227 S.W.3d 486 (George Weis Co. v. Stratum Design-Build, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Weis Co. v. Stratum Design-Build, Inc., 227 S.W.3d 486, 2007 Mo. LEXIS 116, 2007 WL 1953428 (Mo. 2007).

Opinion

LAURA DENVIR STITH, Judge.

George Weis Company (“Weis”) was a subcontractor on a construction project. When Weis was not paid for its services, it sued the owner and other entities involved in the project for breach of contract and in tort. The trial court dismissed ah of Weis’ claims for lack of subject matter jurisdiction because it beheved that section 429.300, RSMo 2000, 1 required Weis to raise its claims by intervening in a prior equitable mechanic’s lien suit brought by other subcontractors of the same construction project, rather than by bringing a separate tort or breach of contract action.

The trial court’s judgment is reversed, and the case is remanded. Section 429.300 simply requires ah mechanics’ hen claim *488 ants bring their claims in a single action. Weis is not a lien claimant; its only claims are against the owner and others. Therefore, section 429.300 does not require Weis to join its claims with the mechanic’s lien action brought by those seeking to recover on a lien against the property. To the extent that prior cases hold to the contrary, they are no longer to be followed.

1. FACTUAL AND PROCEDURAL BACKGROUND

Stratum Design-Build, Inc. (“Stratum”) was general contractor for a construction contract with Hurlbut Investments, LLC (“Hurlbut”), which owned the property upon which the construction project was undertaken. As part of the process by which Hurlbut secured funding for the construction project, four companies— Hurlbut; Stratum; Title Insurers Agency, Inc. (“TIA”), as escrow agent; and Southwest Bank of St. Louis (“Southwest”), as lender — entered into a construction escrow agreement that detailed the process by which funds would be disbursed to pay those providing supplies or performing services for the construction project.

Weis was the drywall subcontractor hired by Stratum for the project. Weis completed all of its work on the project by August 22, 2003, and submitted its invoices to Stratum. Stratum billed Hurlbut, which paid Stratum 90% of the cost of the work performed by Weis. 2 Stratum, however, did not pay these funds over to Weis as required by the construction escrow agreement. In July 2005, Weis filed the present action against Stratum, Hurlbut, TIA, and Southwest (collectively “Defendants”). Count I of Weis’ petition alleged breach of the subcontract agreement between Weis and Stratum and violation of the prompt payment act, sec. 431.180. Count II alleged that TIA breached its fiduciary duties to Weis in the administration of the escrow fund. Counts III and IV alleged breach of the construction escrow agreement by Hurlbut and Southwest, respectively, and that Weis was a third-party beneficiary to that agreement.

In October 2005, Hurlbut and Southwest filed a joint motion to dismiss, alleging that, because Weis failed to intervene in a prior equitable mechanic’s lien suit filed by various other subcontractors involved in the construction project, 3 the trial court had no subject matter jurisdiction over Weis’ claims against Defendants.

The trial court took judicial notice of the equitable mechanic’s lien suit. Weis was not a party to that case. Nonetheless, the trial court found that the existence of the mechanic’s lien case barred Weis’ claims against Defendants because, the court believed, under section 429.300 “a contractor or supplier on a construction project cannot recover in a breach of contract suit if a mechanic’s lien suit is filed by a different entity which did work on the same job, unless the breach of contract suit is joined with the mechanic’s lien suit.” (emphasis added by trial court). Accordingly, the trial court dismissed the action. 4 Weis appeals.

*489 II. STANDARD OF REVIEW

“Whenever it appears ... that the court lacks jurisdiction of the subject matter, the court shall dismiss the action.” Rule 55.27(g)(3). “Generally, the decision to dismiss for lack for subject-matter jurisdiction is a question of fact left to the sound discretion of the trial court, and it will not be reversed on appeal absent an abuse of that discretion.” Mo. Soybean Ass’n v. Mo. Clean Water Comm’n, 102 S.W.3d 10, 22 (Mo. banc 2003). But when, as here, the facts of a case are uncontested and the resolution of the issue turns solely on the interpretation of pertinent statutes, “a question as to the subject-matter jurisdiction of a court is purely a question of law, which is reviewed de novo.” Id.; Barker v. Barker, 98 S.W.3d 532, 534 (Mo. banc 2003).

III. DISCUSSION

In determining the meaning of a statute, “the primary rule is to consider words in their plain and ordinary meaning.” StopAquila.org v. City of Peculiar, 208 S.W.Sd 895, 902 (Mo. banc 2006). “[I]t is appropriate to take into consideration statutes involving similar or related subject matter when such statutes shed light upon the meaning of the statute being construed.” Cook Tractor Co., Inc. v. Dir. of Rev., 187 S.W.3d 870, 873 (Mo. banc 2006).

Section 429.300 is part of a series of statutes setting out the procedure whereby any person performing services or providing materials for a construction project can obtain a mechanic’s lien. They describe both the means to enforce such hens and the effects of their enforcement. See generally secs. 429.010 to 429.340. Section 429.270 provides that “any and all” mechanics’ liens may be adjudicated and that “[s]uch action shall be an equitable action for the purpose of determining the various rights, interest and hens of the various mechanics’ lien claimants.” (emphasis added). Section 429.290 warns that once such an equitable action is brought, it “shall be exclusive of other remedies for the enforcement of mechanics’ liens.” (emphasis added). Section 429.300 further provides:

ah other suits that may have been brought on any mechanic’s lien claim or demand shall be stayed and no further prosecuted, and the parties in any such other suit shah be made parties to such equitable action.... “After the institution of such equitable action no separate suit shah be brought upon any mechanic’s lien or claim against said property, or any of it, but the rights of ah persons shah be adjusted, adjudicated and enforced in such equitable suit.”

(emphasis added).

This Court agrees with Mabin Construction Co. v. Historic Constructors, Inc., 851 S.W.2d 98, 102 (Mo.App. W.D.1993), that the plain and ordinary language of section 429.300 and the related statutes quoted above states that these statutes govern only the enforcement of rights of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mills v. Director of Revenue
407 S.W.3d 124 (Missouri Court of Appeals, 2013)
St. Louis County v. Berck
322 S.W.3d 610 (Missouri Court of Appeals, 2010)
Fru-Con Construction Corp. v. Controlled Air, Inc.
574 F.3d 527 (Eighth Circuit, 2009)
Missouri Public Service Commission v. Missouri Interstate Gas, LLC
266 S.W.3d 881 (Missouri Court of Appeals, 2008)
Gash v. Lafayette County
245 S.W.3d 229 (Supreme Court of Missouri, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
227 S.W.3d 486, 2007 Mo. LEXIS 116, 2007 WL 1953428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-weis-co-v-stratum-design-build-inc-mo-2007.