George Hanna v. Pickett and Dunn Roofing and Sheet Metal, Inc.

CourtCourt of Appeals of Kentucky
DecidedNovember 15, 2024
Docket2023-CA-0708
StatusUnpublished

This text of George Hanna v. Pickett and Dunn Roofing and Sheet Metal, Inc. (George Hanna v. Pickett and Dunn Roofing and Sheet Metal, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Hanna v. Pickett and Dunn Roofing and Sheet Metal, Inc., (Ky. Ct. App. 2024).

Opinion

RENDERED: NOVEMBER 15, 2024; 10:00 A.M. NOT TO BE PUBLISHED

Commonwealth of Kentucky Court of Appeals

NOS. 2023-CA-0708-MR & 2023-CA-0753-MR

GEORGE HANNA; AND NAHED HANNA APPELLANTS/CROSS-APPELLEES

APPEAL FROM FAYETTE CIRCUIT COURT v. HONORABLE THOMAS L. TRAVIS, JUDGE ACTION NO. 11-CI-00686

PICKETT AND DUNN ROOFING AND SHEET METAL, INC. APPELLEES/CROSS-APPELLANTS

OPINION AFFIRMING IN APPEAL NO. 2023-CA-0708-MR; REVERSING AND REMANDING IN APPEAL NO. 2023-CA-0753-MR

** ** ** ** **

BEFORE: ECKERLE, GOODWINE, AND MCNEILL, JUDGES.

ECKERLE, JUDGE: This dispute involves primarily claims of breach of contract

and warranty stemming from the installation of a residential roof.

Appellants/Cross-Appellees, George and Nahed Hanna (collectively, “the Hannas”), seek review of orders and a judgment of the Fayette Circuit Court

following a jury verdict in favor of Appellees/Cross-Appellants, Pickett and Dunn

Roofing and Sheet Metal, Inc (“Pickett & Dunn”). The Hannas appeal from the

Trial Court’s orders: granting Pickett & Dunn’s motion to amend the complaint

and denying their motion to file an amended complaint; granting partial summary

judgment for Pickett & Dunn on the breach-of-contract claims; denying their

motion for directed verdict; and excluding or allowing the admission of certain

evidence at trial. In its cross-appeal, Pickett & Dunn argues that the Trial Court

abused its discretion by denying its motion for attorneys’ fees and costs as

provided for by the contract.

After careful review, we find no error or abuse of discretion in the

rulings addressed in the appeal. However, we conclude that the Trial Court failed

to make sufficient findings justifying its decision to deny attorneys’ fees in the

cross-appeal. Hence, we reverse this order and remand for additional findings of

fact and conclusions of law.

I. Facts and Procedural History

On October 6, 2008, the Hannas entered into a contract with Pickett &

Dunn Roofing for installation of a roof on their house located at 4241 Bridle Ridge

Lane in Lexington. The roof consisted of areas that were to be covered with

shingles and a large turret that was to be covered by metal. The parties agreed on a

-2- total price of $90,000.00, with one-third to be paid at signing, one-third to be paid

on delivery of the materials, and the final third to be paid upon completion. The

contract also set out several warranties for the materials and workmanship.

Between October 9, 2008, and December 12, 2008, the parties

negotiated four revisions of the contract. One of the revisions specified that the

material for the turret was to consist of 26-gauge, standing seam metal. The

second required that shingles were to be colored stone-gate grey. The third

provided that Pickett & Dunn would install 16-ounce copper standing seam

valleys. And the fourth and final modification reflected the parties’ agreement that

Pickett & Dunn were not to perform any carpentry or woodwork on the house.

The Hannas made the first installment payment after the execution of

the final contract revision, and they made the second upon delivery of the

materials. Pickett & Dunn began work in January of 2009 and completed the

shingle work by early February. However, the turret work did not run smoothly.

Pickett & Dunn claimed that the Hannas had not selected a color for that part of the

job, and it could not begin work until they did. The Hannas countered that they

had requested copper roofing for the turret and demanded that Pickett & Dunn

install it for the quoted price. The parties were unable to achieve agreement on the

material or the cost for the turret, and Pickett & Dunn ceased work.

-3- The Hannas then hired a different roofer to complete the work. They

also opined that much of the roofing work performed by Pickett & Dunn had been

done incorrectly. Consequently, on February 11, 2011, George Hanna filed a

complaint against Pickett & Dunn alleging breach of contract and breach of

warranty. In its answer, Pickett & Dunn also asserted counterclaims for breach of

contract and fraud. Nahed Hanna was later added as a party to both the complaint

and counterclaims.

This litigation has proceeded ever since, encompassing more than a

decade. After extensive discovery, the parties filed cross-motions for summary

judgment. In an Order entered more than ten years after the case began, on

November 30, 2021, the Trial Court granted Pickett & Dunn’s motion for summary

judgment. The Trial Court concluded that the contract clearly specified 26-gauge

standing sheet metal for the turret. The Trial Court also found, as a matter of law,

that the Hannas’ refusal to allow installation of the agreed-upon material

constituted a breach of contract that prevented Pickett & Dunn from full

performance of the contract. Thus, the Trial Court dismissed the Hannas’ breach-

of-contract claim and granted summary judgment in favor of Pickett & Dunn on its

countervailing breach-of-contract claim. The Trial Court separately granted

summary judgment for the Hannas on Pickett & Dunn’s fraud claim.

-4- Over a year later, the case went to a jury trial from March 8, 2023, to

March 15, 2023. The jury found for Pickett & Dunn on the Hannas’ warranty

claims, specifically finding that Pickett & Dunn substantially performed its duties

to install the shingled portion of the roof in a good and workmanlike manner and

that Pickett & Dunn did not fail to correct any defects prior to leaving the job site.

The jury also awarded Pickett & Dunn $30,000.00, representing the unpaid portion

of its contract with the Hannas.

The Trial Court subsequently denied the Hannas’ motion for a

judgment notwithstanding the verdict. The Trial Court also denied Pickett &

Dunn’s motion for attorneys’ fees and costs of litigation. However, the Trial Court

granted Pickett & Dunn’s motions for prejudgment interest. This appeal and cross-

appeal followed. Additional facts will be set forth below as necessary.

II. Motions to Amend the Complaint

The Hannas challenge two of the Trial Court’s rulings regarding

amending the complaint: (1) adding Nahed Hanna as a party; and (2) declining to

add a claim for constructive trust. As to the first argument, Pickett & Dunn had

moved to add Nahed Hanna as a plaintiff and co-defendant to its counterclaim on

November 11, 2016, claiming that she was an indispensable party because she co-

owned the property. The Hannas countered that Nahed Hanna was not

-5- indispensable and that the motion was untimely. Following a hearing, the Trial

Court granted Pickett & Dunn’s motion.

The decision whether to add necessary or indispensable parties rests

within the sound discretion of the Trial Court. Jones by & through Jones v. IC

Bus, L.L.C., 626 S.W.3d 661, 669 (Ky. App. 2020) (citing Commonwealth, Dep’t

of Fish & Wildlife Res. v. Garner, 896 S.W.2d 10, 14 (Ky. 1995)). Joinder of

parties is governed by Kentucky Rule of Civil Procedure (“CR”) 19.01, which

provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liquor Outlet, LLC v. Alcoholic Beverage Control Board
141 S.W.3d 378 (Court of Appeals of Kentucky, 2004)
Abney v. Nationwide Mutual Insurance Co.
215 S.W.3d 699 (Kentucky Supreme Court, 2007)
Bear, Inc. v. Smith
303 S.W.3d 137 (Court of Appeals of Kentucky, 2010)
Steelvest, Inc. v. Scansteel Service Center, Inc.
807 S.W.2d 476 (Kentucky Supreme Court, 1991)
Dalton v. Mullins
293 S.W.2d 470 (Court of Appeals of Kentucky (pre-1976), 1956)
Milligan v. Schenley Distillers, Inc.
584 S.W.2d 751 (Court of Appeals of Kentucky, 1979)
Daniels v. CDB BELL, LLC
300 S.W.3d 204 (Court of Appeals of Kentucky, 2009)
West v. Goldstein
830 S.W.2d 379 (Kentucky Supreme Court, 1992)
Peyton v. Commonwealth
253 S.W.3d 504 (Kentucky Supreme Court, 2008)
National Collegiate Athletic Ass'n v. Hornung
754 S.W.2d 855 (Kentucky Supreme Court, 1988)
Goodyear Tire and Rubber Co. v. Thompson
11 S.W.3d 575 (Kentucky Supreme Court, 2000)
Clephas v. Garlock, Inc.
168 S.W.3d 389 (Court of Appeals of Kentucky, 2004)
Radioshack Corp. v. ComSmart, Inc.
222 S.W.3d 256 (Court of Appeals of Kentucky, 2007)
Rice v. Steele
295 S.W.3d 453 (Court of Appeals of Kentucky, 2009)
Miller v. Eldridge
146 S.W.3d 909 (Kentucky Supreme Court, 2004)
Woodall v. Grange Mutual Casualty Co.
648 S.W.2d 871 (Kentucky Supreme Court, 1983)
Bierman v. Klapheke
967 S.W.2d 16 (Kentucky Supreme Court, 1998)
Scifres v. Kraft
916 S.W.2d 779 (Court of Appeals of Kentucky, 1996)
COM. DEPT. OF FISH & WILDLIFE v. Garner
896 S.W.2d 10 (Kentucky Supreme Court, 1995)
Rossi v. CSX Transportation, Inc.
357 S.W.3d 510 (Court of Appeals of Kentucky, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
George Hanna v. Pickett and Dunn Roofing and Sheet Metal, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-hanna-v-pickett-and-dunn-roofing-and-sheet-metal-inc-kyctapp-2024.